Crossrail - Construction updates and progress towards opening (now expected 24 May 2022)

Status
Not open for further replies.

iphone76

Member
Joined
6 Nov 2010
Messages
917
Location
South Essex
The late running, including one train arriving at Abbey Wood exactly 2 hours late was not planned. The plan at this stage was all automatic mode running to get drivers accustomed to the system with perhaps the odd glitch.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

kevin_roche

Member
Joined
26 Feb 2019
Messages
930
It'd be interesting to understand if the later running services are due to planned "service disruption" (and recovery) type testing as part of the trial running? Or if this is the kind of teething trouble to be expected on the first attempt at trial running (I appreciate trial running is building upon many previous days of dynamic testing)? Or is this unexpected (I've seen on the 345 thread that two stock transfers through the core were also delayed) - possibly there was a more general infrastructure issue)?

There was a plan to move two FLUs from Old Oak To Gidea Park today via the COS. It seems it all went wrong when they tried to leave the COS at Pudding Mill Lane. More details on the Class 345 Progress Thread. My guess it that the recovery from that caused the delays.
 
Last edited:

itfcfan

Member
Joined
7 May 2011
Messages
327
The late running, including one train arriving at Abbey Wood exactly 2 hours late was not planned. The plan at this stage was all automatic mode running to get drivers accustomed to the system with perhaps the odd glitch.
Thank you for explaining @iphone76.

There was a plan to move two FLUs from Old Oak To Gidea Park today via the COS. It seems it all went wrong when they tried to leave the COS at Pudding Mill Lane. More details on the Class 345 Progress Thread. My guess it that the recovery from that cause the delays.
I thought that might be it too, but the later than scheduled running was present from early in the morning (very few services ran within 10 mins of their booked times, e.g. 9Y14 leaving Bond Street at 07:20 instead of 07:01 was fairly typical) while the stock movement later (5Y52 not departing until 10:24).

The run times today are also later than scheduled, but (so far) the delays are lower (e.g. 9Y20 leaving Bond Street at 07:38 instead of 07:31 is the equal most delayed).
 

kevin_roche

Member
Joined
26 Feb 2019
Messages
930
The run times today are also later than scheduled, but (so far) the delays are lower (e.g. 9Y20 leaving Bond Street at 07:38 instead of 07:31 is the equal most delayed).
9Y29 seems to have been very delayed. 10 mins late arriving at Canary Wharf. Something went wrong after Custom House. https://www.realtimetrains.co.uk/train/F06256/2021-05-11/detailed

It looks like an FLU was moved to Gidea Park today.

 
Last edited:

Snow1964

Established Member
Joined
7 Oct 2019
Messages
6,165
Location
West Wiltshire
The latest Elizabeth Line Board papers are now available
the juicy stuff pages 51 to 194 are unfortunately not public

section 3.9 (page 16) says Bond Street and Canary Wharf are exceptions, not achieving SC3 (substantial completion)

Section 3.12 (page 17) says Woolwich and Liverpool St both now in T-12 (12 weeks to handove)

section 5.2 (page 20) trial running starting at 4 trains, building up to 12 trains within couple of months

 

rebmcr

Established Member
Joined
15 Nov 2011
Messages
3,849
Location
St Neots
section 3.9 (page 16) says Bond Street and Canary Wharf are exceptions, not achieving SC3 (substantial completion)
Odd, I thought CW was done years ago (even downstairs that hasn't opened yet). I must have been mistaken.
 

InOban

Established Member
Joined
12 Mar 2017
Messages
4,216
I think that CW was done so long ago, and by the private sector, that it doesn't meet current specifications.
 

stuu

Established Member
Joined
2 Sep 2011
Messages
2,749
Fairly sure the fire safety system needed reworking/replacing
 

kevin_roche

Member
Joined
26 Feb 2019
Messages
930
With the London Mayoral and Assembly elections complete, TfL has been able to publish the latest updates on Crossrail progress from Mark Wild. There are therefore two new update letters available.

https://content.tfl.gov.uk/london-assembly-mothly-update-09-april-2021.pdf

On 28 March 2021, the Great Western Main Line transition was commissioned. Crossrail infrastructure is now connected to the Great Western for test trains across that route. The first System Testing with a train session was undertaken with six runs completed.

https://content.tfl.gov.uk/london-assembly-mothly-update-12-may-2021.pdf

In recent weeks the project has achieved three major milestones that are necessary for activities in the central section to begin and, crucially, for delivering passenger services in our opening window. These are the commissioning of the Great Western Main Line (GWML) and Great Eastern Main Line (GEML) fringes and the assumption by Rail for London Infrastructure (RfU) of responsibility for relevant infrastructure as an Infrastructure Manager under Railways and Other Guided Transport Systems (Safety) Regulations 2006 (ROGS), which gives TfL the ability to allow the infrastructure to be used for operating the trains.
Connecting the GWML and GEML lines to the Central Operating Section is a significant moment for the project as we now have, for the first t ime, a fully joined up railway.
 

itfcfan

Member
Joined
7 May 2011
Messages
327
Some interesting articles have been published on newcivilengineer.com in the past week re: progress to Crossrail opening.

2021-05-14: Schedule pressures at four Crossrail stations threaten to jeopardise entire programme

Schedule pressures and cost increases at four of Crossrail’s Central London stations threatens to jeopardise the project’s programme, according to project representative (Prep) Jacobs.

In the latest publicly available report on the project’s progress (Prep 12), Jacobs warns that outstanding work at Bond Street, Whitechapel, Paddington and Canary Wharf threatens to delay Crossrail’s programme to get the Elizabeth Line open during the first half of 2022.

In particular, Jacobs warns that “effective mitigations” will be required at the four stations to avoid a delay in entering trial operations, which involves tests and trials to demonstrate that TfL is capable of operating the railway.

Source: https://www.newcivilengineer.com/la...en-to-jeopardise-entire-programme-14-05-2021/

2021-05-21: Crossrail to enter June construction blockade after trial running delay

Crossrail will enter another construction blockade in “late June” to accelerate work which has not yet been undertaken due to the delay in starting trial running.

At an Elizabeth Line committee meeting yesterday, Crossrail Ltd chief executive Mark Wild said the blockade will enable teams to “catch up” some of the construction work “missed in this period”.

Crossrail officially entered trial running last week, with four trains per hour currently running through the project's central London tunnels. Rail staff had been prepared to start trials in late March and again at the end of April.

Source: https://www.newcivilengineer.com/la...lockade-after-trial-running-delay-21-05-2021/
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
6,099
Location
Surrey
Some interesting articles have been published on newcivilengineer.com in the past week re: progress to Crossrail opening.
Hang on Wilde told us how successful the previous blockade had been in August/Sep 20 that put them back on programme only for them to have another blockade in November 20 and and now we need another one. Whilst undoubtedly the most productive way to get stuff done in the tunnels what more needs doing that wasn't previously completed?

Also the revised Delivery Control Schedule to get them from now to formal opening gets delayed again.

I can get the sense of ranging a window for opening was sensible ten years ago but if they can't put a firm date on it with a year to go then they are lacking significant confidence in my view.
 

Dstock7080

Established Member
Joined
17 Feb 2010
Messages
2,767
Location
West London
Email to staff suggests the following station handover to TfL dates:
Woolwich 25 June 2021
Abbey Wood 2 July 2021
Liverpool Street 5 July 2021
Paddington 23 July 2021
Bond Street 17 August 2021
Canary Wharf 19 August 2021
Whitechapel 21 August 2021
 

JaJaWa

Established Member
Joined
14 Feb 2013
Messages
1,705
Location
New progress update today:

New video from Tottenham Court Road today:
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,489
Location
Between Peterborough & Bedlington
Digging around on Greater Anglia's website, it looks like the GEML will be entirely shut west of Marks Tey (and the Southend branch west of Billericay) on Sunday the 5th of September.
Track renewal is occurring, but of more interest to the Crossrail works, the power supply of the OLE is due to be upgraded.

Perhaps the autotransformers between Pudding Mill Lane & Shenfield are due to come on stream?
 

ijmad

Established Member
Joined
7 Jan 2016
Messages
1,810
Location
UK
Anyone been down to the open sections to watch the trial running yet?
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
6,165
Location
West Wiltshire

matt_world2004

Established Member
Joined
5 Nov 2014
Messages
4,504
Something looks odd with the picture of the mayor leaving the train, it’s only just within the platform doors, the train departing indicator is lit, and there appear to be cables hanging from the overhead handrails.

In the photo inside the carriage appear to be cardboard boxes lying around and what looks like a boat life jacket on seat

What exactly is going on here ?
There backpacks and hivis probably a requirement for testing if they need to retrain