Thank you to my predecessors for initially creating and then taking on the updating of this thread.
This first post lists only those stations considered to have a good chance of being delivered in a reasonable timescale. I have taken the list ‘as is’ at December 2020 and will update it when there is new information from a reliable source, which essentially means a public statement by Network Rail or a TOC. Statements by a funding body, a development partner, a Local Authority or Government will also be considered.
Post 254 provides a list of all the stations discussed in this thread up to the end of December 2020 (65 in total). In preparing to take over the thread I have identified over 150 ‘proposed stations’ plus a number of ‘proposed lines’ where individual stations are not listed. Some of these proposals are very speculative (wouldn’t it be a good idea if …..), others were serious proposals which appear to have fallen by the wayside.
For the latest updates please refer to the latest thread posts, for the up-to-date comprehensive summary refer to the following table.
There is a separate thread for the more speculative proposals: New Stations and Schemes - a comprehensive list of speculative proposals
Note: Updates will be mentioned in a new post at the end of the thread, and reflected in the above table.
This first post lists only those stations considered to have a good chance of being delivered in a reasonable timescale. I have taken the list ‘as is’ at December 2020 and will update it when there is new information from a reliable source, which essentially means a public statement by Network Rail or a TOC. Statements by a funding body, a development partner, a Local Authority or Government will also be considered.
Post 254 provides a list of all the stations discussed in this thread up to the end of December 2020 (65 in total). In preparing to take over the thread I have identified over 150 ‘proposed stations’ plus a number of ‘proposed lines’ where individual stations are not listed. Some of these proposals are very speculative (wouldn’t it be a good idea if …..), others were serious proposals which appear to have fallen by the wayside.
For the latest updates please refer to the latest thread posts, for the up-to-date comprehensive summary refer to the following table.
There is a separate thread for the more speculative proposals: New Stations and Schemes - a comprehensive list of speculative proposals
Opened in 2024 | Status | Location | Notes | |
patiently waiting | ||||
2024 and beyond (dated) | Anticipated opening date | Status | Location | Notes |
Cameron Bridge [CBX] | 2 June 2024 | under construction | branch from Thornton North Junction | Discussion here |
Leven [LEV] | 2 June 2024 | under construction | branch from Thornton North Junction | Discussion here |
Ashington [ASL] | 2024 | under construction | proposed Northumberland Line | Discussion here |
Ashley Down [ASD] | 2024 | under construction | between Filton Abbey Wood and Stapleton Road | Discussion here |
Darlaston [DAS] | 2024 | under construction | between Walsall and Wolverhampton | |
Newsham [NWH] | 2024 | under construction | proposed Northumberland Line | Discussion here |
Seaton Delaval [SEJ] | 2024 | under construction | proposed Northumberland Line | Discussion here |
Willenhall [WIA] | 2024 | under construction | between Walsall and Wolverhampton | |
White Rose [WRO] | later in 2024 | under construction | between Cottingley and Morley | Discussion here. New Stations Fund - 'round 4' |
Kings Heath [KIH] | late 2024 | under construction | between Birmingham New Street and Kings Norton (Camp Hill Route) | Discussion here |
Moseley Village [MOV] | late 2024 | under construction | between Birmingham New Street and Kings Norton (Camp Hill Route) | Discussion here |
Pineapple Road [PIR] | late 2024 | under construction | between Birmingham New Street and Kings Norton (Camp Hill Route) | Discussion here |
Winslow [WNO] | possibly late 2024 | under construction | between Bicester and Bletchley | Discussion here |
Bedlington [BEJ] | 2025 | under construction | proposed Northumberland Line | Discussion here |
Belfast Grand Central | 2025 | under construction | north of present Belfast Great Victoria Street | |
Blyth Bebside [BLI] | 2025 | under construction | proposed Northumberland Line | Discussion here |
Butetown [was Loudoun Square] | 2025 | under construction | between Queen Street and Cardiff Bay | General South Wales Metro discussion here. A completion date of 2025 is now being suggested |
Cambridge South [CMS] | 2025 | under construction | between Cambridge and Shelford | Discussion here |
Northumberland Park [NOP] | 2025 | under construction | proposed Northumberland Line | Discussion here |
Beaulieu Park | 2025/26 | under construction | between Chelmsford and Hatfield Peverel | Discussion here |
Pill [PIA] | 2026 | Development Consent Order approved | branch from Parson Street | Discussion here |
Portishead [POH] | 2026 | Development Consent Order approved | branch from Parson Street | Discussion here |
Birmingham Curzon Street | 2029 - 2033 | under construction | HS2 | |
Birmingham Interchange | 2029 - 2033 | route works commenced | HS2 | |
Old Oak Common | 2029 - 2033 | under construction | HS2 | |
Other proposals being progressed | Status | Location | Notes | |
Balgray (was Barrhead South) | undated | proposed | between Whitecraigs and Neilston | Discussion here. A completion date of Autumn 2025 has been suggested. |
Beeston Castle and Tarporley | undated | proposed | between Crewe and Chester | Discussion here. Restoring Your Railway: Ideas Fund Round Two |
Cardiff Parkway | undated | planning application 'called in' | between Cardiff Central and Newport | Discussion here. A completion date of 2024 has been suggested. |
Charfield | undated | planning permission granted | between Yate and Cam & Dursley | A completion date of late 2024 has been suggested. |
Cottam Parkway | undated | planning permission granted | between Preston and Salwick | Discussion here. A completion date of '2030 at the latest' has been suggested. |
Crwys Road | undated | prior approval granted | between Queen Street and Heath High Level | General South Wales Metro discussion here. Completion dates of 2023, 2024 or 2025 have been mentioned. |
Cullompton | undated | proposed | between Tiverton Parkway and Exeter St Davids | A completion date of 2025 has been suggested. |
Deeside Industrial Park/Northern Gateway | undated | proposed - funded to further develop proposals | between Hawarden Bridge and Neston | New Stations Fund - round 3 |
East Leeds Parkway / Thorpe Park | undated | proposed | between Cross Gates and Garforth | New Stations Fund - 'round 4' |
Edginswell | undated | planning permission granted | between Newton Abbot and Torre | New Stations Fund - round 3 |
Elland [ELN] | undated | planning permission granted | between Brighouse and Halifax / Sowerby Bridge | Discussion here. A completion date of 2026 has been suggested. |
Ferryhill | undated | proposed | between Darlington and Durham | Restoring Your Railway: Ideas Fund Round Two |
Gabalfa | undated | proposed | between Cathays and Llandaf | A completion date of 2028 has been suggested. |
Golborne | undated | proposed | between Wigan North Western and Warrington / Newton-le-Willows / Patricroft | Discussion here. A completion date of 2025 has been suggested. |
Haxby P & R | undated | planning application submitted | between York and Malton | Discussion here. New Stations Fund - round 3. A completion date of 2026 has been suggested. |
Henbury | undated | proposed | between Filton Abbey Wood and St Andrews Road | A completion date of 2025/26 has been suggested. |
Langport & Somerton | undated | proposed | between Castle Cary and Taunton | Restoring Your Railway: Ideas Fund Round Two |
Leeds Bradford Airport Parkway | undated | proposed | between Horsforth and Bramhall Tunnel | Most recent discussion here. A completion date of 2025 has been suggested. |
Liverpool Baltic | undated | proposed | between Liverpool Central and Brunswick | Most recent discussion here. A completion date of 2025 has been suggested. |
Lydeway | undated | proposed | between Westbury and Pewsey | |
North Filton | undated | planning permission granted | between Filton Abbey Wood and St Andrews Road | A completion date of 2025/26 has been suggested. |
Okehampton Parkway | undated | proposed, funded | between Sampford Courteney and Okehampton | Being discussed here and here. A completion date of 2025 has been suggested. |
St Annes Park | undated | proposed | between Bristol and Keynsham | Restoring Your Railway: Ideas Fund Round Two |
St Clears | undated | proposed | between Carmarthen and Whitland | New Stations Fund - round 3 |
Surrey Canal [was Surrey Canal Road or New Bermondsey] | undated | planning permission granted | between Queens Road Peckham and Surrey Quays | Discussion here. A completion date of early 2025 has been suggested. |
Waverley (South Yorkshire) | undated | proposed | between Darnall and Woodhouse | Restoring Your Railway: Ideas Fund Round Two |
Wellington | undated | proposed | between Taunton and Tiverton Parkway | A completion date of 2025 has been suggested. |
Wixams | undated | planning permission granted | between Bedford and Flitwick | Old discussion here, current discussion here. A completion date of 2024 has been suggested. |
Note: Updates will be mentioned in a new post at the end of the thread, and reflected in the above table.