Transpennine Route Upgrade and Electrification updates

Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
2,586
Location
Nottingham
Absolutely rapid progress being made.
Can we say yet when will TRU electrification east of the Pennines will be complete enough for diesel or bimode services to converted to EMU?

Now that Staybridge is done, I guess that means when will Neville Hill to Colton Junction be completely wired, so that local services can switch to fully electric.
 

WAO

Member
Joined
10 Mar 2019
Messages
888
Can we say yet when will TRU electrification east of the Pennines will be complete enough for diesel or bimode services to converted to EMU?

Now that Stalybridge is done, I guess that means when will Neville Hill to Colton Junction be completely wired, so that local services can switch to fully electric.
If you read posts 8776 and 8789 you will learn of eye-witness progress not PR statements. There will be more piles in than masts erected and there will be about 20 masts per km. That means that mast erection could be complete this year, East of Leeds. Bridge work may (or not) take longer as it has to be planned ahead more. SPS and wiring can be quite speedy so it is not impossible to have East of Leeds wiring live in 2026. There is always ORR sign-off (can be quick) and staff training and stock testing to add to the timescale before a full new timetable can start. We might just be pleasantly surprised. There is however a lot to do West of Leeds before we're all-electric.

WAO
 

Halish Railway

Established Member
Joined
26 Apr 2017
Messages
2,016
Location
West Yorkshire / Birmingham
If you read posts 8776 and 8789 you will learn of eye-witness progress not PR statements. There will be more piles in than masts erected and there will be about 20 masts per km. That means that mast erection could be complete this year, East of Leeds. Bridge work may (or not) take longer as it has to be planned ahead more. SPS and wiring can be quite speedy so it is not impossible to have East of Leeds wiring live in 2026. There is always ORR sign-off (can be quick) and staff training and stock testing to add to the timescale before a full new timetable can start. We might just be pleasantly surprised. There is however a lot to do West of Leeds before we're all-electric.

WAO
Not to mention there are still quite a few blockades in the forthcoming months where progress can really ramp up.

Of course thanks to the Neville Hill and Leeds East viaduct works we’re still a few years off seeing EMUs deployed on the local stopping services which is when we’ll really see the greatest benefits of electrification. Until then there’s not going to be a noticeable change for the passenger experience if it’s just 802s using the wires and if the linespeed remains at 90mph for the most part.
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
2,586
Location
Nottingham
Of course thanks to the Neville Hill and Leeds East viaduct works we’re still a few years off seeing EMUs deployed on the local stopping services which is when we’ll really see the greatest benefits of electrification. Until then there’s not going to be a noticeable change for the passenger experience if it’s just 802s using the wires and if the linespeed remains at 90mph for the most part.
That's what I thought. Thank you.
 

yorkie

Forum Staff
Staff Member
Administrator
Joined
6 Jun 2005
Messages
72,858
Location
Yorkshire
Just a gentle reminder to stick to actual infrastructure updates in this thread, please.

Any discussion regarding timetabling, diagramming, traction and/or anything of a speculative nature should be posted in a separate thread, please.


Some posts have been moved to:
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
2,586
Location
Nottingham
Do we know what the Manchester-Leeds journey time is expected to be when the Transpennine Route Upgrade is complete?
 

jfollows

Established Member
Joined
26 Feb 2011
Messages
7,852
Location
Wilmslow
Do we know what the Manchester-Leeds journey time is expected to be when the Transpennine Route Upgrade is complete?
https://thetrupgrade.co.uk/benefits/ says

Faster journeys​

We’re speeding up journeys so you can travel to your favourite towns and cities more quickly. Our fastest journey times are forecast to be 63-66 minutes between Manchester and York and 41-42 minutes between Manchester and Leeds.
 

Grumpy

Member
Joined
8 Nov 2010
Messages
1,170
A couple of photos taken today from the Dragon bridge in Leeds. The electrification works towards Morley can be seen on the westbound shot, and the lack of same on the eastbound shot looking towards Leeds. The gap between the new works and the existing OHLE at Leeds is approx 1000 yards.

1737905323923.jpeg

1737905502475.jpeg



The grey industrial unit in the westbound shot lies approximately on the site of the former Farnley and Wortley station. This would have to be demolished if "they" ever saw sense and brought the former viaduct line back into use (together with another bridge over the canal in Leeds) giving unconflicted access into the southern platforms. Something that would probably have given more benefits at a fraction of the cost of the Ravensthorpe works
 

Midland Man

Member
Joined
10 Jun 2017
Messages
33
A couple of photos taken today from the Dragon bridge in Leeds. The electrification works towards Morley can be seen on the westbound shot, and the lack of same on the eastbound shot looking towards Leeds. The gap between the new works and the existing OHLE at Leeds is approx 1000 yards.

View attachment 173489

View attachment 173490



The grey industrial unit in the westbound shot lies approximately on the site of the former Farnley and Wortley station. This would have to be demolished if "they" ever saw sense and brought the former viaduct line back into use (together with another bridge over the canal in Leeds) giving unconflicted access into the southern platforms. Something that would probably have given more benefits at a fraction of the cost of the Ravensthorpe works
I understood the viaduct line was taken out of use as it had a very severe speed restriction due to curvature which would also prevent use of modern stock unless the line were singled.
 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
18,490
Location
Yorkshire
I understood the viaduct line was taken out of use as it had a very severe speed restriction due to curvature which would also prevent use of modern stock unless the line were singled.
Agreed- the curvature of that viaduct was such to render it utterly unsuitable for modern stock. The only way it could be of practical use for transit would be as part of a tram system. Maybe if it had been demolished once the track was lifted, it wouldn't get brought up so often. The idea that it would offer the same sort of benefits as the grade separation at Thornhill LNW Junction is frankly laughable.
 

Grumpy

Member
Joined
8 Nov 2010
Messages
1,170
Agreed- the curvature of that viaduct was such to render it utterly unsuitable for modern stock. The only way it could be of practical use for transit would be as part of a tram system. Maybe if it had been demolished once the track was lifted, it wouldn't get brought up so often. The idea that it would offer the same sort of benefits as the grade separation at Thornhill LNW Junction is frankly laughable.
I think the Mods will get upset if we discuss this here. I have made a posting on the Speculative Discussions "Suggestions for new shortish lines" thread to amplify this.
 

Swaine

Member
Joined
11 Sep 2019
Messages
10
Location
Penistone
I’ve been following the progress of the TRU on the forum.
I recently travelled between Huddersfield and York. The first time for a while. I was surprised at the general level of engineering activity all along this stretch of the line.
Nothing prepares you though for the work between Huddersfield and Ravensthorpe. The scale of the civil engineering works is immense and very impressive. Well worth the trip!
 

grdc

Member
Joined
19 Feb 2023
Messages
18
Location
Morley
I wonder if the replacement bridge adjacent to Neville hill depot has the same headroom as the previous.

Was passing today, so thought I'd have a look.

The headroom appears to have been reduced, at least according to the signage.

Height restriction is now showing as 13'3" (4.0m)

Before the works it as 14'3" (4.3m)
 

Attachments

  • PXL_20250201_133117649.MP.jpg
    PXL_20250201_133117649.MP.jpg
    5.6 MB · Views: 198
  • PXL_20250201_133204376.MP.jpg
    PXL_20250201_133204376.MP.jpg
    3.8 MB · Views: 196

Spartacus

Established Member
Joined
25 Aug 2009
Messages
3,319
Was passing today, so thought I'd have a look.

The headroom appears to have been reduced, at least according to the signage.

Height restriction is now showing as 13'3" (4.0m)

Before the works it as 14'3" (4.3m)

Looking at photos I think that's mostly down to the bridge now being wider, taking up the full abutment when it didn't previously, so is now more at risk from long vehicles on the slopes up & down then previously. If so it's a smart decision to lower the height limit even if the bridge isn't any lower to the road directly below it.
 

stibz

Member
Joined
7 May 2014
Messages
72
I’ve been following the progress of the TRU on the forum.
I recently travelled between Huddersfield and York. The first time for a while. I was surprised at the general level of engineering activity all along this stretch of the line.
Nothing prepares you though for the work between Huddersfield and Ravensthorpe. The scale of the civil engineering works is immense and very impressive. Well worth the trip!
As a local down and around the works everyday, depending on weather. The progress seen is always at snailspace to me. on one section they started and sort of 1/2 done if that, Nothing has changed since April 2023, machines all went off hire, still the same today. but elsewhere slow progess, afterall no rush it's taxpayers money. Like any big government funded project, it will run late and over budget IMO
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
26,591
Location
Nottingham
It's posted on RMWeb that a signal with a junction indicator has appeared, along with markings on the rails giving the positions of two crossovers to be added between Greenfield and Saddleworth Viaduct.
 

Halish Railway

Established Member
Joined
26 Apr 2017
Messages
2,016
Location
West Yorkshire / Birmingham
It's posted on RMWeb that a signal with a junction indicator has appeared, along with markings on the rails giving the positions of two crossovers to be added between Greenfield and Saddleworth Viaduct.
Must be the same idea as the crossover to the north east of Batley, allowing trains to terminate and turnaround at Greenfield whilst works take place on Marsden tunnel.
 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
18,490
Location
Yorkshire
Must be the same idea as the crossover to the north east of Batley, allowing trains to terminate and turnaround at Greenfield whilst works take place on Marsden tunnel.
I thought trains could already turn back at Diggle loop, can they not? They can turn back at Marsden station (the other end of Standedge tunnel) but this does mean using platform 3 which is awkward due to the positioning of the starting signal*.

The Batley turnback crossover is for the longer blockades when the new junction at Ravensthorpe is plugged in, though it may also come in useful in the other direction when Morley Tunnel is being worked on.

*= That particular issue may have been fixed now, it was certainly a problem in the past as 185s had to be local door only.
 
Joined
8 Feb 2021
Messages
747
Location
York
I thought trains could already turn back at Diggle loop, can they not? They can turn back at Marsden station (the other end of Standedge tunnel) but this does mean using platform 3 which is awkward due to the positioning of the starting signal*.

The Batley turnback crossover is for the longer blockades when the new junction at Ravensthorpe is plugged in, though it may also come in useful in the other direction when Morley Tunnel is being worked on.

*= That particular issue may have been fixed now, it was certainly a problem in the past as 185s had to be local door only.
Marsden P2 can also be used for turnbacks. P3 is still awkward
 

billh

Member
Joined
7 Jan 2015
Messages
278
I thought trains could already turn back at Diggle loop, can they not?
I was at Diggle last week, the loop line looked rather derelict , the sleeper ends near the canal tunnel mouth are undermined and to my eye , unsafe. Is the loop to be dispensed with in the near future? There was a lot of new cable ducting being installed on the other side, also east of Greenfield Station.
 

61653 HTAFC

Veteran Member
Joined
18 Dec 2012
Messages
18,490
Location
Yorkshire
Marsden P2 can also be used for turnbacks. P3 is still awkward
Thanks. Though P2 isn't accessible, so turning back there is presumably a no-no? Is taxiing people who can't use the steps from Slaithwaite or Huddersfield acceptable from that perspective?

I was at Diggle last week, the loop line looked rather derelict , the sleeper ends near the canal tunnel mouth are undermined and to my eye , unsafe. Is the loop to be dispensed with in the near future? There was a lot of new cable ducting being installed on the other side, also east of Greenfield Station.
IIRC the Diggle loop is being decommissioned as part of the upgrade, don't know if it's already beyond use but your description suggests it might be. In which case, an alternative facility will be needed while Standedge is blocked.
 

superkev

Established Member
Joined
1 Mar 2015
Messages
2,759
Location
west yorkshire
This week's Sara Bell Youtube reports the setting up of a huge crane at Colne bridge for this weekends possession.. Not sure exactly what happening but Colne bridge road is down to one lane.
K
See

A further (long) Sarah Bell Youtube concerning last weekend works shows amongst much more the large crane has lifted the new Colne Bridge abutment faces into place as well as much piling near Bradley junction for the new bridge abutments. Much track works was taking place at Huddersfield Station as well as a glimpse of a short section of new roof.
K
 
Last edited:

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
9,325
Location
Dalton GA USA & Preston Lancs
Just got this from New Civil Engineer via LinkedIn


AtkinsRéalis has been selected by Network Rail to oversee design integration for the 29km middle section of the Transpennine Route Upgrade (TRU) between Stalybridge and Huddersfield.

The appointment falls under an eight-year Lead Design Organisation (LDO) framework, where AtkinsRéalis will be responsible for a variety of services crucial to the project’s success. These include engineering management, design integration, schedule coordination, Building Information Modelling (BIM) and survey management.

The scope of work will involve the strengthening of up to 40 bridges, renewing 62km of track and remodelling four stations, among other infrastructural improvements.

The TRU is a multi-billion-pound initiative aimed at enhancing passenger connections and promoting sustainable travel within the North of England, linking key cities such as Manchester, Huddersfield, Leeds and York. The programme is part of broader ambitions to reduce journey times and facilitate greener travel options through the electrification of the railway.

Currently, the Stalybridge to Huddersfield route section, known as W2BC, is under survey by specialist teams. This preparatory work aims to gather in-depth information about terrain and potential obstacles before construction begins, ensuring that planning is informed by an accurate understanding of the route’s characteristics.
 

josh-j

Member
Joined
14 Sep 2013
Messages
222
Remodelling four stations - I know Mossley is being moved and Greenfield reconfigured but I didn't realise the others were being worked on as well? There are only four stations between Stalybridge and Huddersfield!

Nice to see things gradually progressing.
 

Class 170101

Established Member
Joined
1 Mar 2014
Messages
8,351
Also here if you cannot read New Civil Engineer.


RailUK said:
AtkinsRéalis, a world-class engineering services and nuclear company with offices around the world, has been appointed by Network Rail to lead design integration for a central section of the Transpennine Route Upgrade (TRU), the 18-mile leg from Stalybridge to Huddersfield.

Under an eight-year Lead Design Organisation (LDO) framework, AtkinsRéalis will provide critical integration and design services to Network Rail including engineering management, design integration, schedule integration, BIM and survey management – spanning from design through to construction. This will involve strengthening up to 40 bridges, 62km of track renewals, and remodelling four stations, among other work.
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
2,586
Location
Nottingham
Is three tracking between Huddersfield and Marsden still in the scope of TRU?

EDIT: I assume not, because 2 x 29km plus the existing loops at Marsden and Diggle amount to nearly 62km.
 
Last edited: