Peter Sarf
Established Member
Order ?. I doubt it.I just noticed that.
Hinting possible order?
More likely hinting that SE could use the things that SWR don't seem to think they need !.
Order ?. I doubt it.I just noticed that.
Hinting possible order?
Could be both. Surplus of SWR sets transfer plus a top-up of a new order. SWR had an option for additional sets, if it hasn’t expired it could be activated to avoid tendering the requirement.Order ?. I doubt it.
More likely hinting that SE could use the things that SWR don't seem to think they need !.
It's already blue!Almost certain Steve White (Southeastern MD) isn’t teasing something… but an interesting tweet nonetheless. https://x.com/stevewhiterail/status/1779045011943776324?s=46
(A picture of a 701 with the caption “Doesn’t this train look good in blue. Just saying “)
More cost effective in the long run doesn't provide tax breaks to your donors in the short-run.Yes most likely, thats what happens when you let your industries become foreign owned, its happened time and time again and we never seem to learn (or those in charge don't care anyway).
Expired - The option was 5 extra 10-car units if ordered before October 2020. Alstom would probably still do it but would likely price higher.Could be both. Surplus of SWR sets transfer plus a top-up of a new order. SWR had an option for additional sets, if it hasn’t expired it could be activated to avoid tendering the requirement.
The other option would be to specify any tender in such a way that the only option would be Aventras. "Compatibility with existing Class 701 fleet" or similar. The same way that London Midland procured the Class 350/3s by specifying compatibility with their existing Class 350 fleet.Expired - The option was 5 extra 10-car units if ordered before October 2020. Alstom would probably still do it but would likely price higher.
Nowhere near enough spare to see off the BREL/ABB 465s (97 of them), though there should be enough within the fleet to take over 376 operations.
Plus any SWR don’t need…..Expired - The option was 5 extra 10-car units if ordered before October 2020. Alstom would probably still do it but would likely price higher.
Nowhere near enough spare to see off the BREL/ABB 465s (97 of them), though there should be enough within the fleet to take over 376 operations.
Nissan Sunderland most certainly does bend metalNewport and Goole are pure assembly but then so is Nissan Sunderland! Few people would say no cars are made there. What matters to UK economy is where the parts are from.
No the ideal is 12 car on Charing Cross or Cannon Street if SDO were to be fitted (in the previous tender) or 8car for Victoria or Blackfriars (10 car with SDO would work for many of these station as there are plenty of easy extensions.Plus any SWR don’t need…..
Do 5 or 10 car 701s match the train lengths/platforms on any SE routes?
There are more class 701 vehicles on order than the combined class 455, 458 and 707 fleet currently in use.Is there an excess of Class 701s in the SWR order?
That runs into siding space issues.You could probably get extra vehicles in the new order by extending the 10-car Class 701s to 12-car for Southeastern, for those routes which can take them.
Are the 10 car 701 units, the same length as Networker 12 car units?Is there an excess of Class 701s in the SWR order? You could probably get extra vehicles in the new order by extending the 10-car Class 701s to 12-car for Southeastern, for those routes which can take them.
No, they are about 202m (12car networker is about 242m) from memory.Are the 10 car 701 units, the same length as Networker 12 car units?
At the time of ordering (in 2017) there were almost same number of vehicles already, compared to 750 ordered, consisting 91x4 (455), 24x2 (456), 36x5 (458), 30x5 (707) =742, so was almost one for one replacement, not an expansion (although the 707s were still entering service back in 2017)There are more class 701 vehicles on order than the combined class 455, 458 and 707 fleet currently in use.
Given that this was to cover an expanded service - particularly to Reading and Windsor - there would appear to be less sets now needed. As Reading now no longer has peak extras, and there appears to be no intention of bringing them back, then you'd think at least 10 x 10-car sets would now be surplus.No, they are about 202m (12car networker is about 242m) from memory.
No doubt someone will be along and quote length to a milimetre
At the time of ordering (in 2017) there were almost same number of vehicles already, compared to 750 ordered, consisting 91x4 (455), 24x2 (456), 36x5 (458), 30x5 (707) =742, so was almost one for one replacement, not an expansion (although the 707s were still entering service back in 2017)
No the ideal is 12 car on Charing Cross or Cannon Street if SDO were to be fitted (in the previous tender) or 8car for Victoria or Blackfriars (10 car with SDO would work for many of these station as there are plenty of easy extensions.
Brixton southbound if the stopping point isn't changed (which is do-able if a little unusual to have the door not opening at the front rather than the back with SDO)However won't a 10 coach unit foul some of the junctions on the routes out of Victoria towards Lewisham & Orpington?
Currently in use is the key though. SWR has a shortage of units and key routes often end up with short forms (although many in spirit in that they are diagramed shorter than they should be)There are more class 701 vehicles on order than the combined class 455, 458 and 707 fleet currently in use.
Indeed! They make engines there as well, and a battery plant is being built next door, it's a major manufacturing site, much more so than Alstom Derby.Nissan Sunderland most certainly does bend metal
A good, constructive meeting with @Alstom Group CEO Henri Poupart-Lafarge on the future of train manufacturing in the UK.
Intensive discussions are taking place, to conclude no later than the end of May.
You get the feeling that things are starting to move forward. Be interesting to see how many trains (if any) get ordered.The transport Secretary has met with the Alstom CEO today
So it would seem.... Can't imagine Harper going to FranceSo the CEO is visiting the UK?
We are now in a period of intense discussions with the UK Government and Transport for London about a potential train order for the Elizabeth line, given the levels of passenger demand. This could help secure the future of our Derby Litchurch Lane site. (1/2)
All parties have agreed to conclude discussions as soon as possible - and no later than the end of May. We will be making no further comment at this time. (2/2)
So just when anyone good has found alternative employment they’ll try to restart with all contractors, quality will be low and then that will be the last contract that is delivered by DerbyYou get the feeling that things are starting to move forward. Be interesting to see how many trains (if any) get ordered.
The Rail Minister took an urgent question on the matter in Parliament today. Two key points made among others were that any award to Derby needs to be legally watertight in the context of there being four manufacturers with plant in the UK, and that trains are built for a life of 35 to 40 years.You get the feeling that things are starting to move forward. Be interesting to see how many trains (if any) get ordered.
Oh yes, VERY legally watertight. Can only be through an existing option.The Rail Minister took an urgent question on the matter in Parliament today. Two key points made among others were that any award to Derby needs to be legally watertight in the context of there being four manufacturers with plant in the UK, and that trains are built for a life of 35 to 40 years.
Kicking the can down the road in the hope an election is called and Purdah kicks in....Re: post 859: "Discussions to be concluded by the end of May" - they needed an order months ago. If one IS placed at the end of may it will mean a complete restart of the whole sourcing/building process - some of those suppliers have apparently already ceased trading and staff have found new jobs. Nothing will actually start to take shape for months and what do they do with the staff in the meantime ? I can see a bit of a fiasco building here........