East Coast Timetable Dec 24

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
6,133
Location
Surrey
The current impasse seems to arise because the various train and freight operating companies have competing rights which are unable to be timetabled given the current infrastructure on the East Coast Main Line. So I thought it might be useful to go back in history to look at the decision to grant those rights.

In 2016 the Office of Rail and Road approved the current track access rights for the East Coast after detailed analysis of the various competing claims.

In a letter of 24 March 2016 ORR set out their understanding of the various capacity constraints existing at that time and the services that could be possibly delivered following an all parties meeting earlier that month.

Looking at this it would appear that the expectations for infrastructure improvements have not been achieved (such as at Woodwalton).




In ORR's decisions letter of 12 May 2016 there was an additional comment about the uncertainty of DfT financing. https://www.orr.gov.uk/sites/default/files/om/2016-05-12-ecml-decision-letter.pdf
Given that you have to wonder why there have now been two abortive attempts to revamp the timetable especially the most recent attempt. My guess is the current timetable will now stay until Trans Pennine Upgrade is completed.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,443
The current impasse seems to arise because the various train and freight operating companies have competing rights which are unable to be timetabled given the current infrastructure on the East Coast Main Line. So I thought it might be useful to go back in history to look at the decision to grant those rights.

In 2016 the Office of Rail and Road approved the current track access rights for the East Coast after detailed analysis of the various competing claims.

In a letter of 24 March 2016 ORR set out their understanding of the various capacity constraints existing at that time and the services that could be possibly delivered following an all parties meeting earlier that month.

Looking at this it would appear that the expectations for infrastructure improvements have not been achieved (such as at Woodwalton).




In ORR's decisions letter of 12 May 2016 there was an additional comment about the uncertainty of DfT financing. https://www.orr.gov.uk/sites/default/files/om/2016-05-12-ecml-decision-letter.pdf
I made the very same point last month, post #119, that the 2016 list of infrastructure changes, (including for example at Woodwalton), had not all been completed, but I think it got lost in the general discussion.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
15,974
Given that you have to wonder why there have now been two abortive attempts to revamp the timetable especially the most recent attempt. My guess is the current timetable will now stay until Trans Pennine Upgrade is completed.
Thats a long way away, a solution or variant will be found before then.
 