The ambitions were set out HERE, including maps.
Local reports are that Phase 2A, level crossing closures at Yarnton etc, is postponed / abandoned, because lots of new freight paths are not currently being demanded.
Phase 2B, faster turnouts north of Oxford, is I think completed.
Phase 2C, replacement and enhancement of Botley Road rail bridge, is now admitted to be months (/years?) behind schedule, and widely assumed to be hugely over budget. A new span to serve the intended platform 5 is presumably still thought worthwhile. On the other hand, the significant road widening and wide pedestrian/cycle ways both sides might now be deemed, by the new government, unaffordable.
Phase 2D seems, on the ground, already to be de-scoped to 'add a new platform face (to be numbered 5) to the existing platform 4'. A new western entrance might be deemed, by the new government, to be unaffordable.
What do forum members think, or are able to reveal?
Local reports are that Phase 2A, level crossing closures at Yarnton etc, is postponed / abandoned, because lots of new freight paths are not currently being demanded.
Phase 2B, faster turnouts north of Oxford, is I think completed.
Phase 2C, replacement and enhancement of Botley Road rail bridge, is now admitted to be months (/years?) behind schedule, and widely assumed to be hugely over budget. A new span to serve the intended platform 5 is presumably still thought worthwhile. On the other hand, the significant road widening and wide pedestrian/cycle ways both sides might now be deemed, by the new government, unaffordable.
Phase 2D seems, on the ground, already to be de-scoped to 'add a new platform face (to be numbered 5) to the existing platform 4'. A new western entrance might be deemed, by the new government, to be unaffordable.
What do forum members think, or are able to reveal?