Viscount702
Member
- Joined
- 7 Sep 2011
- Messages
- 331
Does anyone know what is planned for Stalybridge Station because I presume they will do any remodeling before putting up the wires
Thats a pretty large sum of money for 8 miles of upgrade so presumably it covers all aspects of TRU otherwise it would have been cheaper to build HS2 Eastern Leg.According to this document published as part of the papers for the TWAO application, spending on Huddersfield to Westtown is expected to be timed like this:
£479M in CP6 (the current period, ending March 2024)
£946M in CP7 (April 2024 - March 2029)
£34M in CP8 (begins April 2029).
No, that's correct, that's how much its going to cost for those 8 milesThats a pretty large sum of money for 8 miles of upgrade so presumably it covers all aspects of TRU otherwise it would have been cheaper to build HS2 Eastern Leg.
Ludicrous cost and am surprised DofT just roll over and support it.No, that's correct, that's how much its going to cost for those 8 miles
Which to be fair, is a complete rebuild and upgrade of those 8 miles: from an ageing 2/3 track mixed-use line with very little grade-separation to a 4-track railway built to modern standards with fast services almost fully segregated from other traffic. Significant rebuilds of three stations (Deighton, Mirfield and Ravensthorpe) also adds to the cost (AIUI the Huddersfield work is costed separately).No, that's correct, that's how much its going to cost for those 8 miles
All transport capital projects cost a lot today. TRU is not worse than others.Ludicrous cost and am surprised DofT just roll over and support it.
Will they make same mistake again though...
Indeed but if the industry doesn't get a grip of the costs risk is investment will be dialled back.All transport capital projects cost a lot today. TRU is not worse than others.
I should think this particular TRU cost will be in the IRP funding.Indeed but if the industry doesn't get a grip of the costs risk is investment will be dialled back.
If they can't four track and electrify 8miles for 1.5B they might as well give up nowI should think this particular TRU cost will be in the IRP funding.
But NR still has to deliver it on time and budget, or it will impact other projects like the GW project did.
Again, it's not as simple as laying an extra two tracks and stringing up the wires. There's a lot of structures that need significant work such as the viaduct at Huddersfield. Those structures would need refurbishment even if the railway was being put back "as-is". Then there's replacing Deighton's "MFI Flatpack" station with something more significant, with room for the fast lines to pass.If they can't four track and electrify 8miles for 1.5B they might as well give up now
Timescales longer than a whole world war too. Ill be dead before I see the full TRU.If they can't four track and electrify 8miles for 1.5B they might as well give up now
If you've any ideas on how to build it quicker and cheaper then please feel free to enlighten the project team.Timescales longer than a whole world war too. Ill be dead before I see the full TRU.
Any successful business will tell you to be competative you need to be slick.
With the current pace of doing things in this country we would have lost both wars. End of moan.
K
Well it has been rather over engineered but as a result the new flying jcn at Ravensthorpe is largely on a greenfield site so can be built without needing possessions and then the four track section is largely using the existing formation so again much of the work can be executed without possession. So five years seems excessive timeline should have been nearer three years.Again, it's not as simple as laying an extra two tracks and stringing up the wires. There's a lot of structures that need significant work such as the viaduct at Huddersfield. Those structures would need refurbishment even if the railway was being put back "as-is". Then there's replacing Deighton's "MFI Flatpack" station with something more significant, with room for the fast lines to pass.
The main gain is allowing fast services to overtake slow services. The length of four-tracking is enough to allow this. It's not 1-2mins for 1.5B.Well it has been rather over engineered but as a result the new flying jcn at Ravensthorpe is largely on a greenfield site so can be built without needing possessions and then the four track section is largely using the existing formation so again much of the work can be executed without possession. So five years seems excessive timeline should have been nearer three years.
Also I will profess not be knowledgeable of this area but what is the benefit from all this work other than providing fast lines to separate the stopping service can't see it provides that much benefit when it goes back to 2 track at Dewsbury. I see the fast lines will be 100mph where possible but given the geometry of the rest of the route it will give 1-2mins for 1.5B. Would have been better to have kept the works inside the existing railway boundaries and saved two to three hundred million on the heavy civil works.
The flying jcn at ravensthorpe require huge land take to build it along with a new four track structure over river calder which at the Leeds end merges straight back into two track. The existing alignment could have been retained with a flat jcn. Likewise at Heaton Lodge a lot of expense to improve 70PSR to 100PSR by building a mile of new track on a complete new alignment in a deep cutting. There was plenty of railway land that could have been used. Anyhow DofT could have told them to go back and come up with something cheaper but they haven't so I will follow with interest as it get constructed and look forward to seeing what the finally benefits are sometime after 2030 by the looks of it.The main gain is allowing fast services to overtake slow services. The length of four-tracking is enough to allow this. It's not 1-2mins for 1.5B.
How would keeping within the existing railway boundaries save money? Building green field is cheaper because, as you say, it can be done without possessions.
Compare this to the WCML Trent Valley which opened in 2008. That was £350m for 12 miles: longer, but few if any really big structures to rebuild. Then factor construction inflation over the last 15 years and you'll probably get something approaching £1.5B.
It's a massive piece of engineering with new grade separated junctions, so bound to be expensive.If they can't four track and electrify 8miles for 1.5B they might as well give up now
Ravensthorpe may be a "greenfield site", but the landscape around there is pretty rough. The site currently between the Dewsbury and Wakefield lines is/was used as (I think) some sort of landfill- it's very uneven and partially flooded. The new junction and approaches will need substantial earthworks. As far as any less-expensive options go, what do you sacrifice?Well it has been rather over engineered but as a result the new flying jcn at Ravensthorpe is largely on a greenfield site so can be built without needing possessions and then the four track section is largely using the existing formation so again much of the work can be executed without possession. So five years seems excessive timeline should have been nearer three years.
Also I will profess not be knowledgeable of this area but what is the benefit from all this work other than providing fast lines to separate the stopping service can't see it provides that much benefit when it goes back to 2 track at Dewsbury. I see the fast lines will be 100mph where possible but given the geometry of the rest of the route it will give 1-2mins for 1.5B. Would have been better to have kept the works inside the existing railway boundaries and saved two to three hundred million on the heavy civil works.
The ‘looping’ of stopping trains will be done between Huddersfield and Ravensthorpe to provide for more productive dynamic overtaking.I'm also slightly baffled by the Dewsbury plan- building out the Down platform to meet the fast line strikes me as a sledgehammer to crack a nut, the 'nut' being the slow approach into the loop for stopping trains.
Yes, I think I remember it being a storage location for coal for Thornton power station. Then I think it was quarried for sand / gravel after that, then partly backfilled. (?)The site currently between the Dewsbury and Wakefield lines is/was used as (I think) some sort of landfill- it's very uneven and partially flooded.
Ive have no idea why things take so long in the UK but red tape, lack of future commitments from gov to encourage contractors to invest in sufficent plant to do things quicker along with a cant do culture springs to mind.If you've any ideas on how to build it quicker and cheaper then please feel free to enlighten the project team.
Certainly the ongoing failure by government to provide a clear direction on long term investment is a strategic problem. But 'red tape' and 'can't do culture' are rather vague 'go to' phrases which don't mean much. The electrification schemes you mention are likely slowed by a deliberate decision by Network Rail to ensure an active electrification programme is maintained while the government dithers.Ive have no idea why things take so long in the UK but red tape, lack of future commitments from gov to encourage contractors to invest in sufficent plant to do things quicker along with a cant do culture springs to mind.
Modern Railways recently reported that the Stalybridge electrification rate was just 3 miles a year. I suspect the 5 mile Church Fenton - Colton jnc may be even slower.
K
Take it you are forgetting the route via Bradford?
Compare this to the WCML Trent Valley which opened in 2008. That was £350m for 12 miles
Pedant/typo alert: Thornhill power station.Thornton power station.
Like Network Rail invested heavily in HOPS High Output Plant System only for it to hardly be used.Ive have no idea why things take so long in the UK but red tape, lack of future commitments from gov to encourage contractors to invest in sufficent plant to do things quicker along with a cant do culture springs to mind.
Modern Railways recently reported that the Stalybridge electrification rate was just 3 miles a year. I suspect the 5 mile Church Fenton - Colton jnc may be even slower.
K
Thank you - correcting!Pedant/typo alert: Thornhill power station.