• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

a quick concrete sleeper question...

Status
Not open for further replies.

Cowley

Forum Staff
Staff Member
Global Moderator
Joined
15 Apr 2016
Messages
17,150
Location
Devon
Evening folks.
A friend asked me this actually.
He was wondering why the former Southern region didn't use concrete sleepers when Exmouth Junction concrete works were turning out so many other prefabricated things such as footbridges, lamp posts, fencing etc?
I thought that it was possibly because concrete sleepers started being used when continuous welded rail started to become the norm and that the sleepers used were of a far higher quality concrete than could be produced at the EJCW? Although I'm really not sure hence asking here.
Any advice gratefully received.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

John Webb

Established Member
Joined
5 Jun 2010
Messages
3,437
Location
St Albans
Most timber for sleepers was imported, so when WW2 affected the import of timber, the Building Research Station at Garston, north of Watford, was involved in a major investigation and research into concrete sleepers from 1942 onwards. The early designs tended to crack when used next to rail joints, and it was only the spread of welded track after WW2 that encouraged the widespread use of concrete sleepers as the rail joints were eliminated.
I have no information if the Exmouth works was involved in the early development of concrete sleepers.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
32,803
Given the reputation for rubbish off the local beaches being used at Exmouth Jn works it’s probably good they didn’t make sleepers...
 

Cowley

Forum Staff
Staff Member
Global Moderator
Joined
15 Apr 2016
Messages
17,150
Location
Devon
Given the reputation for rubbish off the local beaches being used at Exmouth Jn works it’s probably good they didn’t make sleepers...
It's funny to think that you'd now get into trouble for taking pebbles away from Budleigh beach...
 

Cowley

Forum Staff
Staff Member
Global Moderator
Joined
15 Apr 2016
Messages
17,150
Location
Devon
Most timber for sleepers was imported, so when WW2 affected the import of timber, the Building Research Station at Garston, north of Watford, was involved in a major investigation and research into concrete sleepers from 1942 onwards. The early designs tended to crack when used next to rail joints, and it was only the spread of welded track after WW2 that encouraged the widespread use of concrete sleepers as the rail joints were eliminated.
I have no information if the Exmouth works was involved in the early development of concrete sleepers.
That's what I'd wondered too John. Thanks for that.
 

yorksrob

Veteran Member
Joined
6 Aug 2009
Messages
41,317
Location
Yorks
DOW-MAC and COSTAIN were very notable on the Southern in my day
 

DarloRich

Veteran Member
Joined
12 Oct 2010
Messages
31,049
Location
Fenny Stratford

What a brilliant idea (if it works)

no it isn't - at least not in the short term. They might replace wood in due course but not imminently.

Evening folks.
A friend asked me this actually.
He was wondering why the former Southern region didn't use concrete sleepers when Exmouth Junction concrete works were turning out so many other prefabricated things such as footbridges, lamp posts, fencing etc?
I thought that it was possibly because concrete sleepers started being used when continuous welded rail started to become the norm and that the sleepers used were of a far higher quality concrete than could be produced at the EJCW? Although I'm really not sure hence asking here.
Any advice gratefully received.

I suspect it is a combination of period in time, technology and quality of concrete. There is an awful lot of science involved in making a concrete sleeper to the required tolerances. Your recipe has to be right as does your rebar. It isn't just a case of a bag of ready mix ;)
 

John Webb

Established Member
Joined
5 Jun 2010
Messages
3,437
Location
St Albans
..........I suspect it is a combination of period in time, technology and quality of concrete. There is an awful lot of science involved in making a concrete sleeper to the required tolerances. Your recipe has to be right as does your rebar. It isn't just a case of a bag of ready mix ;)
Quite! Hence the involvement of the Building Research Station in 1942; it gets quite a significant mention in their 1971 book when it speaks guardedly about the work they did 1939-45.
 

Dr_Paul

Established Member
Joined
3 Sep 2013
Messages
1,472
Many years back I saw somewhere -- I think it was the now lifted siding on the down side east of Norbiton station -- some track using concrete sleepers of a type that were two blocks joined by a metal bar. I imagine that these were used only for sidings.

I also saw some concrete sleepers on the Bluebell Railway that were fitted with chairs for bull-head rails. That was quite a surprise, as I thought that they were used only with flat-bottom rails.
 

Ploughman

Established Member
Joined
15 Jan 2010
Messages
2,978
Location
Near where the 3 ridings meet
Many years back I saw somewhere -- I think it was the now lifted siding on the down side east of Norbiton station -- some track using concrete sleepers of a type that were two blocks joined by a metal bar. I imagine that these were used only for sidings.

I also saw some concrete sleepers on the Bluebell Railway that were fitted with chairs for bull-head rails. That was quite a surprise, as I thought that they were used only with flat-bottom rails.
Modern versions of the Twin block sleeper are in use on TGV lines in France and on HS1.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
9,332
Location
Dalton GA USA & Preston Lancs
I suspect it is a combination of period in time, technology and quality of concrete. There is an awful lot of science involved in making a concrete sleeper to the required tolerances. Your recipe has to be right as does your rebar. It isn't just a case of a bag of ready mix ;)

Exactly but I am biased as my 2nd degree is in Material Science and Engineering and spent most of my working life in this endeavor. Same goes for plastics, composites and metals btw.
 

Cowley

Forum Staff
Staff Member
Global Moderator
Joined
15 Apr 2016
Messages
17,150
Location
Devon
I've been having a full internet/phone/EE vs Vodafone meltdown today (I'd quite like to introduce a concrete sleeper from a great height onto the phone actually).
But thanks for the above interesting replies.
 

Dstock7080

Established Member
Joined
17 Feb 2010
Messages
3,078
Location
West London
no it isn't - at least not in the short term. They might replace wood in due course but not imminently.
LU have piles of these new composite sleepers at Lillie Bridge track formation plant, destined for points and crossings I understand.
 

theageofthetra

On Moderation
Joined
27 May 2012
Messages
3,565
Location
Beckenham
Quite! Hence the involvement of the Building Research Station in 1942; it gets quite a significant mention in their 1971 book when it speaks guardedly about the work they did 1939-45.
Did they make those concrete barges used around the D Day landings?
 

mcmad

Member
Joined
11 Mar 2015
Messages
1,011
no it isn't - at least not in the short term. They might replace wood in due course but not imminently.
Might be sooner than you think since softwood sleepers are being phased out due to creosote being banned.
 

John Webb

Established Member
Joined
5 Jun 2010
Messages
3,437
Location
St Albans
Did they make those concrete barges used around the D Day landings?
The 1971 history book doesn't give a mention of any involvement in this area. They may have offered advice on the concrete to be used, they wouldn't have built them - too far inland for a start! And that wasn't how the Building Research Station worked anyway; they passed on their findings for others to use. They still do as "BRE Ltd.", having been taken out of the Civil Service in 1997. (I had worked there up until that point but left as numbers were being cut back.)
 
Last edited:

furnessvale

Established Member
Joined
14 Jul 2015
Messages
4,730
i thought sleepers were hardwood. They haven't been creosoted for several years.
I should imagine that softwood is still used for secondary lines and sidings where CWR is not used. It could well be that plastic will be initially suitable to replace softwood but that further work is required before hardwood can be replaced.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,624
Did they make those concrete barges used around the D Day landings?
The actual building was done many firms including by Balfour Beatty, Mowlem, Nuttall, Costain, Laing, Bovis, McAlpine, Taylor Woodrow, Wates and what become Carillion
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
5,928
The actual building was done many firms including by Balfour Beatty, Mowlem, Nuttall, Costain, Laing, Bovis, McAlpine, Taylor Woodrow, Wates and what become Carillion
...but probably not at places that didn't have a canal or a navigable river to float them down! There were quite a few boat/shipyards around Northwich and higher up the Weaver and the Dane and I thought some of the VIC puffers were built there, but I can't find confirmation now.
Reminds me of the last few chapters of "Riddle of the Sands."
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
26,609
Location
Nottingham
I should imagine that softwood is still used for secondary lines and sidings where CWR is not used. It could well be that plastic will be initially suitable to replace softwood but that further work is required before hardwood can be replaced.
I don't think new timber sleepers are used anywhere except in replacement of existing ones and perhaps for some specialised situations. Modern switches and crossings are normally on concrete and steel is usually used for sleepers on secondary routes.
 
Last edited:

mcmad

Member
Joined
11 Mar 2015
Messages
1,011
the majority of bullhead track is on softwood sleepers, vast areas of which still exist in the more rural parts of Scotland, Wales, East Anglia and Western Routes.
 

Mugby

Established Member
Joined
25 Nov 2012
Messages
2,018
Location
Derby
the majority of bullhead track is on softwood sleepers, vast areas of which still exist in the more rural parts of Scotland, Wales, East Anglia and Western Routes.

Quite true. The majority of any plain line track on wooden sleepers, not just bullhead, is softwood. The only exceptions are locations where CWR needs to be on wooden sleepers due to local conditions or over bridges (to save weight) in which case hardwood is used.

The reason hardwood isn't used in plain like is because it's considerably more expensive that softwood. Under S&C is a different matter where mostly hardwood timbers were used to provide better resistance to lateral pressures.

I didn't know that creosote is now banned but in my time on the P/Way, softwood sleepers were generally expected to have a lifespan of about twenty years.
 

Tim M

Member
Joined
9 Jul 2016
Messages
196
A couple of comments from the Ffestiniog Railways Infrastructure Manager (he previously held a senior position on London Underground permanent way) regarding plastic sleepers. Note the comments about use by London Underground:
—————
Price is volume dependent. For us (the FR) it is still cheaper than Ekki, nobody uses jarrah nowadays. Life expectancy in lab tests achieved 100yrs simulated loading before the fastenings failed. The beauty is that the sleeper can be returned to the makers ground down and reformed to make another sleeper. We send back all our off cuts and swarf to go back in the mix.

Not the same composition as used on garden furniture etc. [in response to another comment]. These have passed the stringent fire testing regime imposed for anything used Underground following the tragic Kings Cross fire in the 1980’s.

We have now used plastic sleepers in several locations for both plain track and point-work.
—————
Seeing the condition of some of the wooden sleepers that came out of the recent work at Victoria/Battersea Park makes you wonder if spot renewals using plastic would be a way forward and much cheaper than renewal of a complete turnout with concrete sleepers. Lasting at least 100 years is a bit better than 40 years.
 
Status
Not open for further replies.

Top