The Modernisation Plan was signed off by Govt in 1955 it was suppose to take until 1975 to complete. Marples when appointed Transport Minister in 1958 brought the end date forward to 1970. Therefore in 1963 it still had 7 years to run many of the proposed marshaling yards were never built. The lines closed were not the ones that had been electrified or given over to DMU working with a handful of exceptions, they were the ones at the back of queue for investment. By declaring them unviable the investment tap could be diverted.
Yes, the Thetford line was probably a line that that would only survive with subsidy however the report also tried to make out the York to Beverley route was a basket case example. The quoted movements costs on the line are steam hauled based substitute them with DMU ones and its a different case. This was a line that the traffic survey categorized in the 5000-10000 passenger per week bracket. BR were on the verge of single tracking a lot of route and installing automatic level crossings. Theres a campaign today to reopen it, it wasn't a 10000 a week plus line but was viable if modernised.
Stopping services according to the report cost £56.1 million and ran for 90 million train miles. Giving in decimal a cost of £0.62 per train mile ran. The reports model on which the magic figure of 10000 passengers a week to break even is based has a cost per train mile of £1.09.
--- old post above --- --- new post below ---
In the Reshaping of British Railways Part 1: Report (table on page 9) the cost of the 5900 single track route miles is given as 15.5% of £110 million (£17.1 million). This is the figure for signalled track (i.e. formation, track and signalling for passenger services) and therefore amounts to an overall average of £2900 per mile per annum. This excludes sidings, yards, stations, depots and all train running costs. When you add in the cost of stations and train running expenses it is only to be expected that the revenue needed to cover the costs of operating the railway needs to be much higher than the signalled track cost.
direct from Page 10 - you can see that the cost the report quotes to run the single track routes was £20 million.
"The lightly used part of the system includes most
of the single track branch line, of which there are 5,900 miles and of which 2,700
miles are open to freight traffic only. The proportion of British Railways' total,
passenger and freight revenue corresponding with this proportion of total traffic
movement is £4 1/2 m., while the cost of providing this route is some £20 m".
Marples became Minister of Transport on 14th October 1959.
If Marples brought forward the end date for the Modernisation Plan would that not increase spending in the short term at least not reduce it and make it more difficult to transfer money to the roads programme?
The 5 planks of the modernization plan were;
1 Track and signaling to allow 100mph running
2 Electric and diesel to replace steam traction
3 Modernisation of coaching stock
4 Freight....(vacuum brakes, marshaling yards etc)
5 Other (Ports, office mechanisation, research)
As far as I can see 1, 2 , 3 and 5 went ahead reasonably as expected. The single major project that did not happen was the electrification of the ECML but conversely the electrification to Bournmouth that wasnt planned did go ahead (with the IoW!).
The real nightmare was item 4 where I dont think the investment did much good in the long term and added to the railways debt. It was unfortunately only later that the freight side managed to find its real trainload markets and exploit them better although still loosing money hand over fist on the dregs of the old business. A couple of minutes on google and I found 12 yards new or reconstructed in the 1958-65 period not cheap.
As far as the train costs go the table at the top of P17 (which I assume is where the 10,000 passenger break-even point comes from) is derived from the costs of running a DMU at £0.54/train mile not a steam train at £1.09/train mile.
System cost
..£77/m
Movement cost
£168/m
steam
£77 + £168 = £245.
£245/224 = £1.09/m
Movement cost
..£45/m
..DMU
£77 + £45 = £122
£122/224 = £0.54/m
I dont recognize the figure of £56.1m for 90m train miles is it a typo for £56.9? Even so the £0.62m/train mile figure for movement costs for all stopping services over the network sounds reasonable for a mix of DMU and steam services and is consistent with the figures in the rest of the document.
In the case of the Hull York service via Beverley the report gives the following figures;
Train miles
.260,000
Movement expenses (£).....84,000
Cost/train mile (£/m)
....0.323 (or 6s-6d/m)
This seems quite consistent with the earlier figures for a mostly DMU service. The reduction in track and signaling costs of £43,000 for 30 miles of double track doesnt seem excessive either especially given the 22 level crossings.
I could not comment on the rest of the costs quoted for this route as they dont make any sense to me.
I now see the origin of the £20m compared to my figure of £17m. The difference is the cost of stations, which are separated out in the table on page 16 and the associated data but not on page 10.
The problem of the lightly used railways was not that the report had inconsistencies, the problem was that there was not enough traffic to justify the number of railway lines open in Britain. The line from Thetford to Swaffham is reported as having 9 passengers on each of the 12 trains per day. Geleneagles to Comrie is reported to have had 5 passengers on 20 trains per day.
What is remarkable is that by 1963 when the report was published BTC/BR had already shut 3429 miles of railway since 1948 so the passenger numbers/freight totals on those must have been really really poor. After the Beeching report BR only shut another 3633 miles of railway up till 1970 when closures more or less stopped.