Or Nuneaton - Leicester- St Pancras like in 1991 if there’s still capacity.Liverpool-Stafford-Banbury-Chiltern line-Marylebone using 805s?
Or Nuneaton - Leicester- St Pancras like in 1991 if there’s still capacity.Liverpool-Stafford-Banbury-Chiltern line-Marylebone using 805s?
Nothing like the spare capacity that was available in 1991.Or Nuneaton - Leicester- St Pancras like in 1991 if there’s still capacity.
The station rebuild in the mid 60s was done largely concurrent with electrification. Although in the main the track layout was not significantly altered. It was done by diverting most of the traffic away - Birmingham trains to Paddington, Manchester trains and some Scotland passengers to St Pancras, postal traffic to a temporary facility on the south / west side of the tracks near Kilburn High Road (there’s still a Royal Mail facility there now). Commuting numbers on what is now the LNR services were much less than today. Took a few years.
For the remodelling 1999-2000, the staton itself was largely untouched (except for making the ramp down to 16-18 much wider), but all the tracks, signalling and OLE (but not all the gantries) were replaced. There was a year and a half of prep works and some of the less disruptive stuff, mostly involving weekend / overnight works where some of the tracks were worked on, but the station remained open. Then from Easter to October 2000 there was a temporary timetable with reduced service levels and roughly one third of the station taken out of use at a time. From memory 15-18 were taken out for the first few weeks, then 12-18, then 8-14, and finally 1-7.
The service reductions took out a handful of peak Virgin services, about 30% of the Silverlink peak (partly offset with 12 coach trains where possible) and the DC (overgrounds) were diverted to the NLL for the duration. Sleepers were a bit tricky as there was only one platform for them throughout, so they had to follow each other in; if the first arrival was late the second had to be held in Wembley or Kensal Green Loop until the platfrom was free. Of course this was in the days when there were fewer services - the standard off peak pattern was 5/6 Virgins, 5 Silverlinks, and 3 DC services (Silverlink Metro). Essentially the timetable was 12 trains per hour max, keeping a path clear in the off peak and squeezing another path in during the peak. It also helped that back then the morning Silverlink peak was done by 0900, whereas the Virgin peak was 0900-1000.
It all worked pretty well, except for the contractor cutting through the air main to the points on day one. Also Hatfield happened about a week after the main blockade finished, so it was a while until passengers felt the benefit of the new layout as temproary timetables were in force.
I’ve found this thread fascinating. Clearly Euston needs rebuilding, and it does get crowded, however I have never found it to be unsafe. I use it about 4 times a week, generally at peak time.
One thing - plans for the rebuilding of Euston have been under development for some time - a lot of time and effort (and money) has gone into it. The HS2 change of strategy has of course affected the timing and design of the conventional station rebuild. Regardless, it is a massive job and will not be cheap.
Between Watford traffic and slower train times, I think RRBs from Hemel to St. Albans instead (or as well, if they could be provided) would be preferable. St. Albans traffic can be poor at times as well though, although hopefully other Thameslink MML services being too full wouldn't be an issue as there'd be the Sutton services and Leighton Buzzard alone probably wouldn't overload the Medway ones.For LNWR run to Watford, but also run RRBs from MK to Bedford, Leighton Buzzard to Luton, Tring and Berkhamstead to Chesham, Hemrl & Kings Langley to Watford Met.
Apparently stuff has/is being built at Stanmore which makes that difficult now?Wehn we used Hemel for RRBs back in 2002/3, it was buses to Stanmore for the Jubilee. By far the quickest option, and the one with most capacity for passengers.
Given the push for TfL to raise more cash is being met by building on outer station carparks that will only get worse.Wehn we used Hemel for RRBs back in 2002/3, it was buses to Stanmore for the Jubilee. By far the quickest option, and the one with most capacity for passengers.
Could you feasibly run some trains through to Waterloo via the WLL? Maybe even throw in a Vauxhall stop for the Victoria Line. Of course only 350/1s and 805/807s would be able to do this.
Apologies, I just meant the 805s.The 807s would need a good run up…
If platform closures were limited to 2 at a time, could a normal-ish service (maybe 3 tph total to Birmingham, no Chester services, some Tring terminators dropped in favour of Milton Keynes ones or more stops on LNR Birmingham ones) be managed for enough time to get work done? I know that the answer's likely "depends on what said work is".
Trouble is how are you going to take the parcels deck down 2 platforms at a time? That's in the way of any new over-station development, which I think we all agree is desirable even if it's just a boarding lounge.
errr - some of it has already come down 2 at a time, notably the part above 17/18. More was due to come dwon above 15/16.
If you are looking at a plan like a two track timetable (6 Avanti 4 LNWR) you could take 4 platforms out without too much hassle. Trains would be very busy, but you could do it.If we've established that that is indeed possible, then that could be an option. As I mentioned you could reduce LNR's platform occupation by removing peak extras (aside from those cases where a Bletchley starter/terminator is just an extended Tring semifast operating in service because it might as well, because that has no effect on Euston) and running peak trains 12-car instead. You could reduce Avanti by removing the Birmingham semifast and putting the stops back in the Glasgow/Edinburgh, making the Chester/North Wales a connection, not starting the second Liverpool, dropping a Manchester etc. You could even drop the Tring semifasts entirely and rediagram, but I think that might lead to excessive overcrowding.
Maybe make Avanti services mandatory reservation up until / from the last station after / before Euston if necessary, and provide some RRBs on top of that? So for e.g. Manchester – London there'd be the options of having a seat reservation, avoiding Avanti entirely (Northern / TfW and LNR or via Sheffield), or getting off at Milton Keynes and going to London via Luton?Trains would be very busy, but you could do it.
No one would use the buses.Maybe make Avanti services mandatory reservation up until / from the last station after / before Euston if necessary, and provide some RRBs on top of that? So for e.g. Manchester – London there'd be the options of having a seat reservation, avoiding Avanti entirely (Northern / TfW and LNR or via Sheffield), or getting off at Milton Keynes and going to London via Luton?
That's fair; Avanti passengers from Coventry / Nuneaton and north would get seat reservations, those from Rugby and south would likely use LNR services, and passengers from the places the RRBs would be running from wouldn't use them either as there'd still be LNR.No one would use the buses.
If you're running fewer trains anyway, could you give more time at stations and run longer trains with some carriages without doors opening at any stations, selective door opening dependent? Or would that have too many safety issues / be otherwise impractical?I think its going to have to be trying to get passengers onto the smallest possible number of trains on the WCML.
LNWR could run all trains as 12 car 350/10 car 730 if needed. Lose a set at Northampton but other than that. UDS/ASDO is already in operation on anything longer than 4 cars on Trent Valley servicesIf you're running fewer trains anyway, could you give more time at stations and run longer trains with some carriages without doors opening at any stations, selective door opening dependent? Or would that have too many safety issues / be otherwise impractical?
Call it Watford DC. We don't accept these bad names.Could Overground trains on Lioness line be sent via Kensington Olympia to Clapham junction (and are there enough dual voltage 710s)?
Can LNWR turn around at Wembley Central or would they need to turn around at Watford Junction?
Things would probably be similar to when the area was closed for upgrades in the Virgin era
TFW can figure out a replacement.North Wales gets no service if you do that. You probably wouldnt have enough 805s either.
Why would they? Its not their problem.Call it Watford DC. We don't accept these bad names.
TFW can figure out a replacement.
The real question is how workable building a HS2 station separately from the rest of the reconstruction is.What timeline are people taking into consideration here? Would not the most obvious thing to do be getting new HS2 platforms to operational stage before taking any other platforms out of service?