I just got this emailed from the BML project people. Apologies if well known:
We are delighted to confirm that the final phase of work will now take place as follows:
We are delighted to confirm that the final phase of work will now take place as follows:
- Sunday, 25 August 2019 - Newhaven Harbour Level Crossing will close permanently
- Sunday, 15 September 2019 - preparation for the main work will take place and buses will replace trains
- Thursday, 28 November to Sunday 1, December 2019 - line closure for four days as work takes place to commission the new signalling systems and de-commission the signal boxes at Lewes, Newhaven Town and Newhaven Harbour. As a result, buses will replace trains. Please check