• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Gospel Oak to Barking Line (GOBLIN) electrification

Status
Not open for further replies.

Class 170101

Established Member
Joined
1 Mar 2014
Messages
8,353
Twitter feed saying that MML to T&H link not being wired as part of the scheme :roll:

Anyone know anything or is what is up thread still correct?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Philip Phlopp

Established Member
Joined
31 May 2015
Messages
3,003
Twitter feed saying that MML to T&H link not being wired as part of the scheme :roll:

Anyone know anything or is what is up thread still correct?

It's a funding thing - TfL stumping up some of the money to get the Gospel Oak to Barking (Riverside) service electrified, so their interest isn't in wiring the link to the MML. Just like the Crossrail v NR funding pots for GWML electrification.

That will come as part of the MML scheme, though it could be done as an extension to the current works by the current contractor, depending on what can be (or has been) agreed.
 

class303

Member
Joined
5 Sep 2011
Messages
391
It's a funding thing - TfL stumping up some of the money to get the Gospel Oak to Barking (Riverside) service electrified, so their interest isn't in wiring the link to the MML. Just like the Crossrail v NR funding pots for GWML electrification.

That will come as part of the MML scheme, though it could be done as an extension to the current works by the current contractor, depending on what can be (or has been) agreed.

Seems strange to leave such a short bit unwired. suppose there's very limited uses until the MML north of bedford is wired anyway.
 

Taunton

Established Member
Joined
1 Aug 2013
Messages
11,093
Seems strange to leave such a short bit unwired. suppose there's very limited uses until the MML north of bedford is wired anyway.
It's only used for freight. No electric locos run on the MML and none are planned to, while beyond Barking the freight points such as Thamesport have no wiring either and all freight needs to be diesel. If this line was wired no electric traffic would use it.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
31,977
Seems strange to leave such a short bit unwired. suppose there's very limited uses until the MML north of bedford is wired anyway.

It's also an absolute pig to do, as the tunnel clearance is insufficient. Very expensive to clear for very little benefit.
 

Philip Phlopp

Established Member
Joined
31 May 2015
Messages
3,003
Seems strange to leave such a short bit unwired. suppose there's very limited uses until the MML north of bedford is wired anyway.

There is that, but equally, it could be done at any time, just under the auspices of a different contract and a different pot of money.

It's not quite as straight forward as being made out though - in addition to the above, it will need to have a neutral section and isolation equipment, so engineering with the T&H doesn't require isolations on the MML, and vice versa.

It's perhaps best done with the planned OLE reliability modifications between St Pancras and Bedford, when much of the old Mark 3b equipment will be replaced with Series 1 to enable 12 car EMU operations.
 

Alfie1014

Member
Joined
27 Jun 2012
Messages
1,177
Location
Essex
It's only used for freight. No electric locos run on the MML and none are planned to, while beyond Barking the freight points such as Thamesport have no wiring either and all freight needs to be diesel. If this line was wired no electric traffic would use it.

That's not the case, Ripple Lane yard is wired, as is the connection to HS1, Dagenham Dock sidings (Fords) and Tilbury Freightliner terminal. So if and when the MML and beyond is wired there are terminals accessible to electric traction. It is correct that the Thameshaven branch to London Gateway isn't wired though it was the original scheme scope, subject to funding.
 

RichmondCommu

Established Member
Joined
23 Feb 2010
Messages
6,906
Location
Richmond, London
That's not the case, Ripple Lane yard is wired, as is the connection to HS1, Dagenham Dock sidings (Fords) and Tilbury Freightliner terminal. So if and when the MML and beyond is wired there are terminals accessible to electric traction. It is correct that the Thameshaven branch to London Gateway isn't wired though it was the original scheme scope, subject to funding.

Just out of interest how much traffic does Tilbury Freightliner terminal see?
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
31,977
There's no potential container traffic from Tilbury (or anywhere else) up the MML, as the latter isn't cleared for high gauge containers. And it would be very expensive to clear it south of St Albans.
 

Mikey C

Established Member
Joined
11 Feb 2013
Messages
7,512
Seems strange to leave such a short bit unwired. suppose there's very limited uses until the MML north of bedford is wired anyway.

Could electric locos with "last mile diesel capability" make it through this section? That would avoid having to electrify an expensive section of track which will get little relatively little use.
 

TRAX

Established Member
Joined
2 Dec 2015
Messages
1,710
Location
France
There are more factors to investigate before considering buying LMD locos but why not.

Or why not bi-mode locos, that could perhaps make the business case more worthwhile network-wide.
 
Last edited:

Freightmaster

Established Member
Joined
7 Jul 2009
Messages
3,808
Just out of interest how much traffic does Tilbury Freightliner terminal see?
Four/five departures a day:

- direct trains to Lawley Street and Garston

- two local trips to London Gateway with traffic for Coatbridge/Leeds

- the as required 'wineliner' to Bristol (runs from Gateway instead some nights)


Despite being electrified, all trains to and from Tilbury FLT are currently
diesel-hauled (the Gateway trips are top and tailed to aid reversal at Grays)


MARK
 

Class 170101

Established Member
Joined
1 Mar 2014
Messages
8,353
It's also an absolute pig to do, as the tunnel clearance is insufficient. Very expensive to clear for very little benefit.

The main benefit I see to this link being wired at this time is an extra feed for the T&H and security of traction supply. Also does coming back and wiring the link mean an additonal possession(s) will be needed on the T&H when the link is finally up for wiring? Or will Junction Road junction be sufficiently wired via the T&H Project not require possessions of the line when linkage to MML is done?
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
31,977
The main benefit I see to this link being wired at this time is an extra feed for the T&H and security of traction supply. Also does coming back and wiring the link mean an additonal possession(s) will be needed on the T&H when the link is finally up for wiring? Or will Junction Road junction be sufficiently wired via the T&H Project not require possessions of the line when linkage to MML is done?

The line will have plenty of feeds. And even if it did need an extra one, it would be a fraction of the cost to run an insulated 25kv feeder through the tunnel without Going to the expense of lowering the track and installing OLE.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
26,595
Location
Nottingham
The line will have plenty of feeds. And even if it did need an extra one, it would be a fraction of the cost to run an insulated 25kv feeder through the tunnel without Going to the expense of lowering the track and installing OLE.

Or even just a feed between the MML and the NLL at one of the several places they cross over each other? If there isn't one already!
 

Philip Phlopp

Established Member
Joined
31 May 2015
Messages
3,003
The main benefit I see to this link being wired at this time is an extra feed for the T&H and security of traction supply. Also does coming back and wiring the link mean an additonal possession(s) will be needed on the T&H when the link is finally up for wiring? Or will Junction Road junction be sufficiently wired via the T&H Project not require possessions of the line when linkage to MML is done?

The possession needed to wire a diverging route, when planned properly, is fairly minimal. It's generally easily do-able during routine work where the OLE is de-energised.

The key is to ensure there's somewhere for additional cantilever arms and tensioning equipment to be mounted, so there's no need to be piling for more masts and adding more mounting brackets on cutting walls.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
Press release

http://www.networkrailmediacentre.c...-starts-to-prepare-for-longer-electric-trains

From this Saturday (24 September) there will be no service between Gospel Oak and Barking (seven days a week) until February 2017 while work takes place to electrify the route ready for new trains that will carry twice as many passengers.

1,700 metres of track is currently being lowered between Blackhorse Road and Walthamstow Queens Road Station as part of major work to electrify the last diesel-operated London Overground route, from Gospel Oak to Barking. Track is being lowered to increase clearance under bridges and make way for new masts that will carry overhead wires to power the new electric trains.

Electricity will be provided by three new power switching stations along the route and one of these is already in place at Gospel Oak. A second near South Tottenham is almost complete and a third will be installed close to Barking station in the coming months. Each switching station links to two power supplies at Acton and West Ham, so if one supply breaks down engineers can switch to the other, minimising disruption for passengers.

Part of the line has been closed since the beginning of June, with trains running from South Tottenham to Gospel Oak only on weekdays, while work takes place. From Saturday (24 September) the whole route between Gospel Oak and Barking will be closed, in order for the final phase of work to be carried out. During this period, two areas of track on the western end of the route will be lowered, one between Crouch Hill and Harringay Green Lanes and another between Gospel Oak and Upper Holloway.
 

jopsuk

Veteran Member
Joined
13 May 2008
Messages
12,773
none of the new stock is going to be ready by February is it? Going to be some upset punters when the line reopens with the 172s trundling along it!
 

Peter Mugridge

Veteran Member
Joined
8 Apr 2010
Messages
16,068
Location
Epsom
none of the new stock is going to be ready by February is it? Going to be some upset punters when the line reopens with the 172s trundling along it!

It has always been the plan that the 172s would resume after the closure until the new stock is available.
 

tom1649

Member
Joined
5 Jul 2010
Messages
974
A shame they couldn't use some PEPs as a stop-gap. I like the idea of PEPs running on that line for some reason. However I've heard that it isn't practical or cost effective.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,005
Location
Mold, Clwyd
none of the new stock is going to be ready by February is it? Going to be some upset punters when the line reopens with the 172s trundling along it!

The wires won't be up by then though.
The current phase is for route upgrade and clearance work.
Wiring will follow next year, hopefully without further line closures.
 

Bringback309s

Member
Joined
22 Aug 2013
Messages
334
Once complete, will trains from Barking run through to Richmond or Clapham Junction? Is there any reason why they couldn't?
 

Domh245

Established Member
Joined
6 Apr 2013
Messages
8,425
Location
nowhere
Is there any reason why they couldn't?

Capacity on those routes is rather limited now with the 4tph per branch and the 8tph (per direction) at Gospel Oak Junction. Throw in the District Line and the other services on the WLL, and there is just no room for it.
 

DynamicSpirit

Established Member
Joined
12 Apr 2012
Messages
8,839
Location
SE London
Out of interest, does anyone know what is happening during the closure to all the freight that would normally use the route - the freight whose presence is usually cited as the reason that passenger frequencies cannot be greater than 4tph? :)
 

PeterC

Established Member
Joined
29 Sep 2014
Messages
4,368
Out of interest, does anyone know what is happening during the closure to all the freight that would normally use the route - the freight whose presence is usually cited as the reason that passenger frequencies cannot be greater than 4tph?
via Stratford and Forest Gate which means a lot of stuff trundling across all four tracks of the GEML. The line is still open between Barking and Forest Gate Junction.
 
Last edited:

cle

Established Member
Joined
17 Nov 2010
Messages
4,596
via Stratford and Forest Gate which means a lot of stuff trundling across all four tracks of the GEML. The line is still open between Barking and Forest Gate Junction.

Has a flyover ever been thought of for the freight over the GEML?

Cost and inconvenience-wise, would something else big to divert Thames freight make more sense?
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
31,977
Has a flyover ever been thought of for the freight over the GEML?

Cost and inconvenience-wise, would something else big to divert Thames freight make more sense?

There is a flyover for freight over the GEML; it's currently closed for electrification!

If, however you meant a flyover from the GEML to the NLL, yes it has been considered, and because of the proximity of other lines, dense housing, stations and the Olympic Park, it's simply not practical.
 
Status
Not open for further replies.

Top