But it's surely about proportion, asbestos was killing thousands of people a year !We made massive use of asbestos in the past. Then we realised the risks, came up with safer alternatives and phased out its use.....
Just because something has been around a long time does not mean that it meets current standards. If it wasn't for the cost and disruption l'm sure that third rail would have been completely replaced.
The extension also provides an opportunity to
trial the operation of The Independently Powered Electric Multiple-Unit (IPEMU) rolling
stock as an alternative to extension of the third rail electrification. This should provide
efficiencies and opportunities for other potential projects across the LCR and its wider
travel-to-work hinterland.
11.2 Wider Implications – Liverpool City Region Long Term Rail Strategy
The Liverpool City Region LTRS, published in 2014 and revised in 2018, contains significant
reference to extensions of the current Merseyrail network beyond the current extents to serve
new markets, destinations and attractors, creating the opportunity for new journey opportunities
and increasing the accessibility of the residents of Liverpool City Region. As battery-electric bi-
mode operation was in its infancy when this strategy was published, it was initially envisaged
that these extensions would be facilitated by costly electrification of lines adjacent to the
Merseyrail network, and the equipping of the new Merseyrail trains with dual voltage AC and DC
capability.
The opportunities provided by the rapid development of battery technology cannot be
overstated in this regard since this provides the potential to facilitate a proportion of the network
extensions without further electrification (either AC or DC). This in turn will allow Merseyrail
services to run, without interruption, on to destinations beyond the current extents of the Wirral
and Northern Lines, and onto sections of the current City Line helping to realise the original
vision of Merseyrail as a 360 degree network.
In particular, the equipping of additional class 777 units for battery-electric bi-mode operation
has the potential to allow Merseyrail services from central Liverpool to be extended in the
following ways (shown in Figure 11.1):
● The onward running of Northern Line services beyond Headbolt Lane to Skelmersdale and
Wigan Wallgate via the line through Rainford;
● The onward running of Northern Line services beyond Ormskirk to Burscough and Preston
via Rufford and Croston;
● The onward running of Northern Line services beyond Hunts Cross to Warrington via the
Cheshire Lines Committee route;
● The onward running of Wirral Line services beyond Bidston to Heswall, Shotton and
Wrexham via the Borderlands line;
● The onward running of Wirral Line services beyond Chester to Crewe; and
● The onward running of Wirral Line services beyond Ellesmere Port to Helsby, Frodsham and
Runcorn East.
I didn't read it all but used "control F" and "third Rail" but could find nothing saying that the ORR would have no problems with the third rail extension. It just talked about using the 0.8mile stretch as a testing ground for battery powered trains. Is it some where else in the document ?The premise of this thread, that third rail electrification to Headbolt Lane was ruled out on safety grounds, is incorrect. Up to and including the Outline Business Case stage of the Headbolt Lane station project it was assumed that the third rail would be extended, and that ORR approval could be obtained on the grounds it would only be a short extension of the existing network. Indeed the Class 777 trains were not originally specified with battery capability, and it was only in 2021 that Merseyrail carried out testing to validate the 777 battery conversion.
The Headbolt Lane Full Business Case document makes clear that a key consideration in the decision to switch to battery operation was the strategic benefit of an operational trial of the battery technology, to support the case for future Merseyrail extension projects without the costs of electrification:
The FBC does not say that the ORR would have no problems with third rail, because the decision to use batteries instead was made before the third rail safety case was presented to the ORR for approval.I didn't read it all but used "control F" and "third Rail" but could find nothing saying that the ORR would have no problems with the third rail extension. It just talked about using the 0.8mile stretch as a testing ground for battery powered trains. Is it some where else in the document ?
The "outstanding determinations" presumably means approval of the safety case. But the ORR third rail policy predates the Headbolt Lane project, so the project would not have progressed to the OBC stage unless there was a reasonable expectation that the third rail extension would be approved. The case would no doubt have relied on section 6 of the ORR policy:At the [Outline Business Case] stage there were outstanding determinations as to whether the existing DC ‘third rail’ MEL network could be extended to Headbolt Lane from Kirkby. Since the conclusion of the OBC (December 2020), the LCR CA in partnership with Merseytravel and Merseyrail Electrics commissioned the testing of a converted Class 777 bi-mode electric and battery train, which confirmed that a class 777 unit under battery power could easily run between Kirkby and Headbolt Lane and back again, meeting timetable requirements, without requiring a recharge. However, following testing, the preferred option for a new station at Headbolt Lane has been modified slightly to remove the need to provide an extension of third rail electrification between Kirkby and Headbolt Lane, instead including the modification of 6no class 777 units to battery-electric capability and the purchase of an additional battery unit.
6. No significant geographic extension of third rail electrification has taken place on the
mainline railway for many years. However, smaller third rail renewal and very minor
extension schemes have been – and continue to be – proposed. For these small-
scale projects, duty holders may be able to demonstrate that simple extension or
replacement of the third rail is the only viable option in the circumstances.
This is simply not true.ALL asbestos must now be removed or encapsulated regardless of cost.
WAO
Encapsulation means not shedding fibres into an occupied space, if so leave well alone.
Im aware of what it means however, i refer to my previous post where you have made a claim that all must be removed or encapsulated. Unless the guidance has changed, this is simply not true. As long as its left intact asbestos can be left in situ.Encapsulation means not shedding fibres into an occupied space, if so leave well alone.
WAO
6. No significant geographic extension of third rail electrification has taken place on theThe FBC does not say that the ORR would have no problems with third rail, because the decision to use batteries instead was made before the third rail safety case was presented to the ORR for approval.
Section 14.2, Option Development Process, says:
The "outstanding determinations" presumably means approval of the safety case. But the ORR third rail policy predates the Headbolt Lane project, so the project would not have progressed to the OBC stage unless there was a reasonable expectation that the third rail extension would be approved. The case would no doubt have relied on section 6 of the ORR policy:
Your "intact" is my "encapsulation" - I actually agree with you!Im aware of what it means however, i refer to my previous post where you have made a claim that all must be removed or encapsulated. Unless the guidance has changed, this is simply not true. As long as its left intact asbestos can be left in situ.
ORR haven't said they won't give permission although they are making pretty clear they can't see how a duty holder could ever convince them they can comply with legislation. However, they acknowledge LUL have made the case because access to the infrastructure is far more restrictive when your up on a viaduct but seemingly the most obvious point of access at a station was made acceptable. Maybe for the latter the fact a member of staff is on duty throughout operating hours provides sufficient mitigation. Personally I would have thought palisade fencing provides sufficient mitigation against access from the lineside but full time staffing of stations will be a challenge outside of large cities but given most stations are flooded with CCTV these days im sure some sort of motion sensing could be used.6. No significant geographic extension of third rail electrification has taken place on the
mainline railway for many years. However, smaller third rail renewal and very minor
extension schemes have been – and continue to be – proposed. For these small-
scale projects, duty holders may be able to demonstrate that simple extension or
replacement of the third rail is the only viable option in the circumstances.
Ah, so the ORR can actually get out of having to give permission for something so dangerous as third rail electrification by stating "use battery powered trains" (even if 99% of the time they'd not be needed, and would adversely affect the flexibility of the operators train fleet).
AIUI the ORR did not instruct Merseytravel to use battery powered trains. It would have been open to Merseytravel to argue that it was not "a viable option" to retrofit batteries to seven units just to work an extension less than 1km long. Instead the LCR/Merseytravel volunteered to fit the batteries. So we do not know whether or not the ORR would have accepted that argument.Ah, so the ORR can actually get out of having to give permission for something so dangerous as third rail electrification by stating "use battery powered trains" (even if 99% of the time they'd not be needed, and would adversely affect the flexibility of the operators train fleet).
It is bizarre, when you consider some of the basket case lines that have been electrified in Belgium. Presumably the running costs of the EMUs are much lower. Even Hasselt to Mol has been wired now. I remember when it was a two hourly loco hauled service with steam heating.I also don't want to look at the latest Quail map showing the partial electrification of the Valleys lines, the incomplete electrification of the GWML and those bits of the West Midlands Metro which haven't been wired for whatever reason.
As a lifelong railway enthusiast and a fiftysomething social conservative curmudgeon with an engineering background it makes me lose the will to live.
I suspect that, after a few weeks of 777s, the Wrexham to Bidston passengers would be asking to have the 230s back.However, having been forced to go down this route, this does open up the possibilities for additional use of battery powered trains e.g. Borderlands.
I will never forget the conversation with my then five year old son about fences at the end of platforms. I explained they are to stop people walking off the end of the platform and quick as a flash he said "that's pointless, you could just jump off the side of the platform!" No DNA test required there!Partly open air, and you can just hop down from the platforms. Not that anybody does, of course.
Totally agree, they should have extended to Wigan, would have made much more sense.The batteries would have enabled an easy extension to Wigan Wallgate, simplifying operations there (the hourly service is a pest in a generally 2tph pattern)....had the station not been built on two levels with a gap between the lines to save a few quid on changing the level of the trackbed further along. I really think that was a huge missed opportunity. It almost seems like connecting Ormskirk back up is more likely now.
We do know how to do it as we still renewing miles of old 1930's conductor every year and upgrading or replacing trackside substations. It wouldn't be cheap though and better done at 25kV and an ideal candidate for discontinuous elecn ie battery for x km then OH for x km to recharge batteries followed by x km on batteries etc etc.My father-in-law is a railway engineer. It is difficult to get his attention in a magnificent space because he is lost in wonder. We were at Clapmham Junction together years ago and I asked him what it would cost to put third rail on the West of England line. I will never forget his answer… 'We can’t, we don’t know how to do it.'
I do find this strange. One of the key upsides of 3rd rail is how cheap and easy it is to install.We do know how to do it as we still renewing miles of old 1930's conductor every year and upgrading or replacing trackside substations. It wouldn't be cheap though ...
Yes running out the conductor rail and installing it is cheap compared to OLE. However this is a long way (c115m) and will require a lot of substations (25-30) for what is a low frequency service. Substations need trackside power distribution and would need to be 33kV but you would need 3 to 4 grid connections and even at that voltage they wont be cheap. Then because of the many sections of single line the substation spacing would have to be reduced as you don't get the voltage support that paralleling a double track gives so voltage regulation becomes an issue. I also suspect Exeter St Davids is simple DC track circuits so a whole load of immunisation would be required as well down that end. Of course all this presumes a case can made for more third rail!!I do find this strange. One of the key upsides of 3rd rail is how cheap and easy it is to install.
Fundamentally they are electrically the same. 3rd rail typically has a 33kV encased trackside feeder, and periodic substations to get it down to train-usable voltage. 25kV has high voltage overhead, and substations on every train (three in a 12-car set) to get it down to train voltage. The big difference is in the civil engineering installation costs. The discussion above has gone back and forth, but unfortunately many give a string of downsides of their not-favoured system, while not discussing the downsides of their own approach.
Exensions are being considered and I think thing may start moving once all 53 units are in service and the remaining 507s are gone.I think it was the other way around. Because of the third rail "police" batteries were the only way forward for Headbolt Lane.
However, having been forced to go down this route, this does open up the possibilities for additional use of battery powered trains e.g. Borderlands.
However these proposed extensions invariably seem to involve crossing out of Liverpool City Region into areas not renouned for putting their own cash in to make this happen.
Yup unless you went to AT but that would be even more expensive for no real benefitWell, if you need 3 to 4 grid connections at 33kV you would need the same number at 25kV, yes? Putting this just on the debit side of DC doesn't really represent reality.
That only works if its DC little point for an isolated AC section and if your going to use bimodes use them from BasingstokeAnd this is for electrification through to Exeter. Doing it just to Salisbury, with bi-modes for diesel operation beyond, has always seemed the most appropriate, especially as half the service, and demand, is east of there.
Not my recollection it was atypical BR of the day where the accountants used simple rules of x mile of track cost y to maintain so rationalise and save money.I'm surprised at raising the single line issue, because when Weymouth was done the section from Moreton to Dorchester was singled precisely because of substation current limits.
That was 1960s. I think you will find they were a bit more switched-on by 1988, when it was done. The sectional power restriction is what causes the restriction on double 444s west of Bournemouth, such that when there are significant events at Weymouth, eg the 2012 Olympics sailing, services are changed to double 450s instead, which have less power draw.Yup unless you went to AT but that would be even more expensive for no real benefit
That only works if its DC little point for an isolated AC section and if your going to use bimodes use them from Basingstoke
Not my recollection it was atypical BR of the day where the accountants used simple rules of x mile of track cost y to maintain so rationalise and save money.