A classic example to prove the need for this work to go ahead asap. In the plan of the designed work at Dore above you can see the tracks redoubled through the station with optional crossovers at each end of the section, presumably to allow for bi-directional running.
Today the
Northern 12.14 stopping service from Sheffield started only 4 minutes late, was held to let the a
lso late preceding TPE service through and arrived at Dore 11 minutes late. Situation so far fairly normal!
But the Northern train then sat there from 12.31 until 13.11. According to Twitter it was congestion. The TPE service was not delaying it. There was nothing due the other way. However an
East Midlands Liverpool - Norwich seems to have been held between Totley Tunnel East (12.34) and Dore West Junction (13.17) to wait for it. It was then cancelled at Sheffield. It might have been a points failure at Dore West? It seems more likely that something had gone wrong with the Northern train but there is no evidence for congestion being the cause. That may be fair comment for the
next Northern train coming from Manchester which was then delayed.
Whatever the cause of that failure today, if the redoubling had been completed with bi-directional working possible, the marooned train could have been passed in either direction.
Maybe by 2022/3 that may be an option. Until then, if anything goes wrong between Dore West and Dore Station Junctions the entire service on all three TOCs between Sheffield and Manchester is wrecked, with further knock on delays and cancellations to Manchester Airport, Cleethorpes, Liverpool, Nottingham and Norwich.
(Last year there was an incident at about 10.30 one morning at Dore station. It took 3 hours to resolve that. With bi-directional working available on two tracks it should have been possible to resume services an hour or more earlier.)