from Paul Clifton:
Network Rail has announced a recovery plan for the Reading-London Paddington route after months of poor performance.
It made national headlines when broken wires left 4,000 passengers stranded on trains for four hours at night, near Ladbroke Grove, on 7 December.
Most passengers had to walk along the tracks to reach safety. There have also been a spate of failures, including broken rails and signalling faults.
The route is now set to be overhauled in three phases over 18 months.
[…]
For the next four weeks, there will be fewer trains late at night, while engineers carry out remedial work to the tracks, signalling and overhead wires.
For the last couple of hours each evening, only two of the four tracks will be open.
A six-month period of work to stabilise performance will follow, then a year-long programme to put long-term solutions in place.
Beyond that, the overhead wires will be replaced in west London. They are 30 years old and were installed when the Heathrow Express began.
Reading-London Paddington route set for overhaul
A spate of failures include broken rails, signal faults and passengers stranded due to damaged cables.