Buckle up everyone!
For ease, I have repeated my questions, and added in the answers received:
The answer to both questions (in total) appears the be £250m. Hmm.
Answer: Haven’t done it.
Answer: possibility not even considered.
Answer: It’s done in Frankfurt, occasionally.
Answer: no costs allowed for.
Answer - some crayons on a picture, and no costs allowed for.
Answer: someone else‘s problem.
Answer: someone else’s problem.
Answer: someone else’s problem.
Now to a few other points:
If it were, then the railway would be in a much healthier state than it is today. It is more than 10 times that now, and that is an average, including easy sites with easy access, which this is not (not least as there’s bridges in the way, as you keep saying). You have also missed that when moving tracks, you have to move other elements - Overhead line for example, signals that will need re-siting (and re-sighting), pointwork that has different clearance points due to the wider gauge, trackside equipment that is now foul to gauge of the lower wide profile of GC (including viaduct parapets).
So I’m afraid we have to dismiss your competence as an estimator of railway engineering works.
You are absolutely right, it is not rocket science. TfL trains are limited to 20mph through Camden Road station through all routes. Any train (TfL or otherwise) heading to or from the Kings Cross Incline or St Pancras is limited to 15mph. Any train heading to or from Primrose Hill is limited to 15mph from a point about 150 metres to the west of Camden Road Junction. This is all as per the Sectional Appendix (in the public domain on NRs website), and signed on the ground, to which all train drivers are obliged to comply. If you are aware of any trains exceeding thse speed limits, please let me know so I can take it up with the appropriate operations director.
I’m afraid we have to dismiss your competence as a Railway Operstions expert.
They also clearly show doing this for only one line at GC gauge, not two. That is, to get GC gauge in, you have to move both tracks (and signals, and OLE, and any other equipment in the way), to get just one track available at GC gauge.
They really don’t.
Here is tomorrow’s evening peak Southeastern High Speed departures from St Pancras for the two hours from 1707.
View attachment 177471
Please can you point out which of these 13 trains “only go to Ashford”.
I’m afraid we have to dismiss your competence as a reader of timetables.
Aside from the Elizabeth Line Class 345s (205m) there are no TfL services that are 200 metres long, and none that have planned turnrounds in 2 minutes (not even the Waterloo and City Line, with 65 metre trains.) The Elizabeth line’s shortest planned turnrounds are (IIRC, please correct me if I’m wrong) 8 minutes, with a 10 minute departure to departure cycle off the same terminus platform, in the peak only.
1)
there will be 400m trains. HS2 Birmingham services will be 400m from the off, as will services to Scotland when they start. Most peak Javelin trains are 240m long also. And then you mention Eurostars going to OOC. They are 390m.
2) Your 7.5minutes is the time between successive departures on the same platform. That is:
a) train 1 departs
b) train 1 clears the junction for a subsequent train to arrive
c) signalling system resets the route from departure to arrival
d) train 2 approaches, having been no closer than the ‘home’ signal, then arrives
e) passengers alight
f) any train servicing requirements (restock, cleaning, running repairs)
g) staff changeover / handover
h) passengers board
i) signalling system resets the route for a departure
j) proceed aspect displayed
k) dispatch procedure initiated
l) dispatch prociedure completed, train departs.
All in 7.5 minutes (correct me if I have this wrong).
Given that the minimum junction margin at St Pancras is 3 minutes for conflicting moves anywhere on the international part of the layout, and the minimum reoccupation time is three minutes for the domestic platforms and 4 minutes for the international platforms (as per the Timetable Planning Rules), that means 6 or 7 minutes of your 7.5 minute turnrounds are taken up by a) to d). That leaves 30-90 seconds for e) to l). Bear in mind these are for departures to from HS1, and not for your proposed lower speed route to HS2.
I’m afraid we are going to have to dismiss your ability as a timetable planner.
It isn’t. It is new railway, with change of land use as well. You will need primary consent. I assume that you consider this to be a strategic proposal in the national interest, in other words a Nationally Significant Infrastructure Project. That automatically requires a Development Consent Order, and given what has already happened with this project I wouldn’t bet against it being called in for Parliamentary debate, ie requiring an Act.
This calls into question your expertise in town planning matters.
Yes you do. And I’m afraid you are wrong.
One small example - To get the extra tracks round the corner towards Gospel Oak from Camden Road needs the permanent acquisition of part of the playground of Hawley Primary School to widen the viaduct. How do you get access to that land to pile the foundations of the new viaduct? Just outside school hours? Or perhaps only during lessons (excluding outdoor PE?)
You also mentioned earlier that to get GC gauge on the existing viaducts you could demolish the parapet walls and cantilever walkways off the side. Leaving aside the practicality of that, that is oversailing others’ property.
I’m afraid this means we can discount your understanding of the land required for major railway constructuon projects.
The diesel freight trains would still be there, along with an extra 16tph HS2 trains (by your estimate) and 8tph Javelins trundling through Camden. That will be more noise, and lots of it. There is also the noise during construction. I have lived and worked next to major railway construction sites, indeed worked on them and had to deal with neighbours - have you?
They didn’t chose to live beside a new, wider railway with an extra 24 trains per hour (minimum) running past their back doors, nor a major construction site. The compensation for the Agar Grove bridge superstructure renewal in Camden ran to significant sums (that I can’t quote here). The compensation bill for HS2 is billions.
Agar Grove in Camden was (and still is) closed for 9 months for a deck replacement. Other durations of closure are of course possible. But six weeks on site is fundamentally impractical.
I’m afraid we are going to have to dismiss your competence in construction planning.
They are in the process of thinking about it. They have no confirmed plans to implement ETCS - and no need to as the current TVM430 is barely 20 years old. The (different) KVB system at St Pancras turns 18 this year. The interface between the KVB and Conventional NR Computer Based interlocking signalling on the North London Line at Camden (controlled from Upminster) has never been commissioned.
We are going to have to dismiss your understanding of railway signalling systems.
“Almost”.
I’m sure you know that when designing a new railway ”it does, or does not; there is no almost”. (with apologies to Yoda)
You appear to have missed the central supporting columns down the middle of that covered way. Also the connections to Temple Mills and the height difference of that line.
We can therefore dismiss your competence as a track designer, as this is basic stuff.
A solution - It would be possible to provide the crossover, at the cost of building a new depot for Eurostar somewhere else (Temple Mills cost £400m 20 years ago), and rebuilding the covered way, with signifcant closures and temproary propping, and closing the DLR and freight lines above while you did it. Allow £2bn.
Indeed, but you propose building a viaduct right through it, which would render it unusable, at least during the constructuon period and probably permanently (if they have to move out for months, they may as well go permanently). You will need to find another site for the business, and it needs to be in the vicinity as concrete has a limited time from being mixed at the batching plant to being used on site (which is why the site is there now).
The HS2 route from OOC to Euston is almost entirely a 100mph+ railway; a third of it is 140mph+. All of the section from Primrose Hill to OOC in 100mph+. This is shown by the linespeed profiles on the HS2 sectional drawings, in the public domain on the DfT website.
Please check things like this before stating them as fact. What you are writing is not true.
As written, you are suggesting that more than half the demand for London to the West Midlands / North West and Scotland origninates on the Thameslink network. I don’t believe this is true, but have not got to hand the data to prove otherwise.
Please can you provide a source for this; as above you do have form for stating as fact things that are not supported by evidence and are not true.
No, you don’t. In my opinion you need more trains from London - Paris / Brussels / other destinations, perhaps coupled with bigger incentives to travel by rail vs air, ie higher Air Passenger Duty. All of which comes at no additional cost in terms of capital expenditure on infrastructure in the UK.
A final point.
Why would HS1 want to go to the expense of remodelling, resignalling and reconfiguring their infrastrucutre at St Pancras, Stratford, Ebbslefft and the like with no guarantees of a return on their investment?
Please don’t reply with copies of your presentation again, we’ve all seen enough of it, and know what your proposal is