FLOOD DAMAGE UPDATE
Monday 19th November 2007.
1. Oldbury Viaduct.
• Civils work at south end completed.
• Drainage system installed.
• Track bed handed back by contractors to SVR.
• New embankment hydroseeded. Completed
• Work above Daniels Mill to be completed before site considered finished, but does not impact on railway operation at this stage.
• Signal post re-erected.
• Cable troughing being laid.
• Track from viaduct relayed by volunteers. Completed
• Track ballast in place. Completed
• Track tamped. Completed
2. Knowlesands.
• All slips now repaired. Completed
• Drainage system installed.
• Track bed handed back by contractor to SVR.
• Bank hydroseeded. Completed
• Drainage ditch completed
• Cutting faces near tunnel inspected by specialists and loose debris/material removed.
• Cleaning of contaminated ballast completed by Shorthouse in trading estate.
• Cleaned / screened ballast returned to track bed.
• S & T cable to be installed.
• Cable troughing being laid.
• Track from viaduct relayed by volunteers. Completed
• Track ballast in place. Completed
• Track tamped. Completed
3. South of Knowlesands.
• Both areas of damage to cutting walls rebuilt. Completed
• New sections hydroseeded. Completed
• Contaminated ballast dug out.
• Cleaning of contaminated ballast completed by Shorthouse in trading estate.
• Cleaned / screened ballast returned to trackbed. Completed
• Drainage ditch to tunnel to be completed.
• S & T cable to be installed.
• Track relayed. Completed
• Track ballast in place. Completed
• Track tamped. Completed
5. Sterns Cottage Culvert.
• Track lifted.
• Culvert to be replaced.
• Agreement from EA and Bridgnorth Council now received.
• Track removed to permit civils work, started 12/11.
• Following completion of civils track to replace, ballast and tamp.
6. Sterns Cottage Slip.
• Track lifted.
• Piling machine on site, piles being installed, vertical and raking (45m length of piled wall required).
• Once piling complete caping beam required.
• Following completion of civils track to replace, ballast and tamp.
7. Sterns (historic slip).
• Track to inspect and tamp as necessary.
9. Waterworks to Hampton Loade.
• Repair to small slip by Up Distant Signal completed.
• Main slip now re-instated. Civil work completed
• New drainage system installed. Completed
• New drainage pipework across caravan site to river completed.
• Track back in place waiting ballast and tamping.
• Small slip by bracket signal completed.
• Slips to hydroseed.
• S & T cable troughing now laid.
• New signal cable to be installed.
10. Hampton Loade to Highley.
• Previously unrecorded culverts found.
• 25 culverts inspected by camera, jet washed/pressure cleaned as necessary.
• Culvert at 144 3/4 replaced by new thrust bore culvert.
• Culvert near Highley station to replace (by pipe bursting technique).
• Many culvert headwalls replaced/rebuild.
• New drainage systems provided in some areas.
• Track to inspect and tamp as necessary.
11. Highley.
• Signalling to re-instate when track back in situ.
• When embankment work finished the approaches to the Engine House will be completed.
12. Highley to Fisherman’s Crossing.
• Started on site. (Including modifications to access road for plant).
• Track to relay, ballast and tamp when complete.
• Signal cable to be replaced following track re-instatement.
13. Borle Viaduct.
• Training walls deteriorated significantly since July.
• Access agreements in place.
• EA approvals now received (to permit work to start)
• Access roads now built. Completed
• Trees cleared for machinery access. Completed
• Nailing machines now on site.
• Altenative solution to SE wall agreed.
14. Bridge 18.
• Clearance work completed.
15. Highley to Arley.
• Work started on inspection, clearing of culverts. Additional previously unrecorded culverts found.
16. Victoria Bridge.
• Slips now repaired. Completed
• New drainage system installed Completed.
• Track bed handed back to SVR.
• Temporary track in place.
• Contaminated ballast dug out.
• Signal re-erected.
• Contractors relaying track from 19/11.
• Signalling cable to install when track back in situ.
• Signal troughing run to Arley being laid. 19/11
17. Eymore Cutting.
• Temporary track in place.
• Contaminated ballast dug out.
• Tree clearance work in progress.
• Culverts inspected by camera, jet washed/pressure cleaned as necessary.
• Contractors relaying track from 19/11.
• Signalling cable to install when track in situ.
• Rock netting inspected for damage and debris removed by specialists.
18. Trimpley.
• Work on two replacement culverts completed.
• Work required near STW pipe under railway.
• Several hundred tons of spoil to move off site once rail connection established.
19. Folly Point.
• Work below track complete (to prevent undercutting of embankment by river).
• Track in place requires tamping.
• One track panel to be lifted for consolidation of embankment.
• Spider crawler (specialist machine) completed work above track to clear loose debris and lay drains.
• Gabion wall completed above track (to catch future small slips) will require ongoing inspection and maintenance programme.
• Culverts inspected by camera, jet washed/pressure cleaned as necessary.
• S & T cable troughing to install.
• Replacement signalling cable to install.
21. Northwood to Bewdley.
• Some drainage and culvert work to complete (does not impact on railway operation).
• Handed back to railway.
22. General
• Many areas cleared of vegetation.
• Sight lines improved at Fisherman’s and other crossings.
• All culverts/drains now recorded by GPS and construction details recorded.
• Many other locations will require minor work to track (eg Kinlet).
• All track bed and track alignment to be inspected and signed off before services restart.
• Work in many areas has been subject to obtaining agreements and negotiations with adjacent landowners, this has involved land agents, solicitors, legal agreements, easements, approvals from statutory bodies etc, etc.
Dewi Jones
Traffic Manager
Deleted as Appropriate
Note to paul1609, still haven't had your reply yet. Remember we're on about a heritage railway, none of the big ones can physically do checks like NR on a daily basis.