• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Transpennine Route Upgrade and Electrification updates

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
26,597
Location
Nottingham
Hard to see exactly what they're planning but from the limited information available they don't look like the sort of barriers that would be needed to protect the properties (and their occupants) from a 25kV OHL. I suspect it's taking the opportunity to make the barriers more robust and prevent trespass.
I suspect they're putting a PES here on the nearer (Up) track. Up trains are on a descending gradient and with the station move stopping trains should have got up some speed when they get here, so the risk of stranding is likely to be manageable.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,710
Location
Between Beeston (Notts) & Bedlington
My in-expert eye seems to think that there is sufficient distance from the OLE, with the fence being up, to mitigate the distance without the need for a PES. The fencing *could* also be non-conductive (e.g. Glass-Reinforced Plastic/GRP), but I suspect a metal fence, with screen, bonded to traction earth, would be sufficient too.
Additionally, based on the curve of the track, the OLE is staggered as a "push-off" towards the cottages (in an easterly direction), meaning that, if the wires were to lose tension, they would return to the centre (in this case, westwards, and away from the cottages).
 

AM9

Veteran Member
Joined
13 May 2014
Messages
15,217
Location
St Albans
I suspect they're putting a PES here on the nearer (Up) track. Up trains are on a descending gradient and with the station move stopping trains should have got up some speed when they get here, so the risk of stranding is likely to be manageable.
PES?
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,447
Testing update on the E1 electrification
Last night, we successfully completed OLE Lineside Compatibility Testing / Load Bank Monitoring, on the TRU East Alliance Project E1, marking a major milestone in our testing and commissioning programme. This brings us one step closer to introducing the new electrification between Colton Junction and Church Fenton into passenger service.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
9,327
Location
Dalton GA USA & Preston Lancs
I thought a summary reminder of progress and a reminder what the project sections are would be useful.

W1 – Manchester Victoria Stalybridge - Complete
W2a – Stalybridge station - Complete
(I assume these includes Guide Bridge to Stalybridge which is also complete)

W2b – Stalybridge – Marsden – in design
W2c – Marsden to Huddersfield – in design
W3 – Huddersfield- Ravensthorpe – boots on the ground (TWAO)
W4 – Ravensthorpe - Leeds
W5– Morley station - work in progress

E1 – Church Fenton – Colton Jct – awaiting final commissioning
E2 – Leeds station and to Crossgates – some boots on the ground - some piling seen
E3 – Crossgates – Micklefield - some boots on the ground - some piling seen
E4 – Micklefield – Church Fenton-some boots on the ground - some piling seen

There is some evidence E2, E3 and E4 have been combined into 1 project. If the same contractors for all schemes that would sort of make sense.
 
Last edited:

Halish Railway

Established Member
Joined
26 Apr 2017
Messages
2,020
Location
West Yorkshire / Birmingham
E1 – Church Fenton – Colton Jct – awaiting final commissioning
E2 – Leeds station and to Crossgates – in design
E3 – Crossgates – Micklefield - in design
E4 – Micklefield – Church Fenton
I’m not sure if ‘in design’ is the right description for E3 given that there are already piles for the OLE installed. Presumably we’re not far from seeing steelwork going up, although I haven’t heard of any reports of steelwork being spotted in any of the works compounds. The work to close and divert Rose Lane to the south of Church Fenton still seems like a long way off though.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,710
Location
Between Beeston (Notts) & Bedlington
I’m not sure if ‘in design’ is the right description for E3 given that there are already piles for the OLE installed. Presumably we’re not far from seeing steelwork going up, although I haven’t heard of any reports of steelwork being spotted in any of the works compounds. The work to close and divert Rose Lane to the south of Church Fenton still seems like a long way off though.
IIRC, E2, E3 & E4 all seems to have been combined into "E234". There's certainly been lots of piling activity in "E4", and a little in "E3". "E2" even has some steelwork in around Neville Hill!
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
9,327
Location
Dalton GA USA & Preston Lancs
I’m not sure if ‘in design’ is the right description for E3 given that there are already piles for the OLE installed. Presumably we’re not far from seeing steelwork going up, although I haven’t heard of any reports of steelwork being spotted in any of the works compounds. The work to close and divert Rose Lane to the south of Church Fenton still seems like a long way off though.
Thanks. Post now edited.

IIRC, E2, E3 & E4 all seems to have been combined into "E234". There's certainly been lots of piling activity in "E4", and a little in "E3". "E2" even has some steelwork in around Neville Hill!
 

superkev

Established Member
Joined
1 Mar 2015
Messages
2,760
Location
west yorkshire
I thought a summary reminder of progress and a reminder what the project sections are would be useful.

W1 – Manchester Victoria Stalybridge - Complete
W2a – Stalybridge station - Complete
W2b – Stalybridge – Marsden – in design
W2c – Marsden to Huddersfield – in design
W3 – Huddersfield- Ravensthorpe – boots on the ground (TWAO)
W4 – Ravensthorpe - Leeds
W5– Morley station - work in progress

E1 – Church Fenton – Colton Jct – awaiting final commissioning
E2 – Leeds station and to Crossgates – some boots on the ground - some piling seen
E3 – Crossgates – Micklefield - some boots on the ground - some piling seen
E4 – Micklefield – Church Fenton-some boots on the ground - some piling seen

There is some evidence E2, E3 and E4 have been combined into 1 project. If the same contractors for all schemes that would sort of make sense.
Thanks, most interesting.
No mention of Guide Bridge to Stalybridge there.
Although theres been mention of clearance of tunnel and bridge works on the west side (example Staly tunnel) are there any still to do on the east side.
Thanks.
K
 

Legolash2o

Member
Joined
27 Sep 2018
Messages
666
I thought a summary reminder of progress and a reminder what the project sections are would be useful.

W1 – Manchester Victoria Stalybridge - Complete
W2a – Stalybridge station - Complete
W2b – Stalybridge – Marsden – in design
W2c – Marsden to Huddersfield – in design
W3 – Huddersfield- Ravensthorpe – boots on the ground (TWAO)
W4 – Ravensthorpe - Leeds
W5– Morley station - work in progress

E1 – Church Fenton – Colton Jct – awaiting final commissioning
E2 – Leeds station and to Crossgates – some boots on the ground - some piling seen
E3 – Crossgates – Micklefield - some boots on the ground - some piling seen
E4 – Micklefield – Church Fenton-some boots on the ground - some piling seen

There is some evidence E2, E3 and E4 have been combined into 1 project. If the same contractors for all schemes that would sort of make sense.
Thanks for this info! I shall update my maps accordingly.

Any sections with piling I tag as under construction.
 
Last edited:

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
9,327
Location
Dalton GA USA & Preston Lancs
Thanks, most interesting.
No mention of Guide Bridge to Stalybridge there.
Although theres been mention of clearance of tunnel and bridge works on the west side (example Staly tunnel) are there any still to do on the east side.
Thanks.
K
Guide Bridge to Stalybridge is indeed complete but it never ( afaik ) got an E or W number - however, I have annotated and edited my post.
 

superkev

Established Member
Joined
1 Mar 2015
Messages
2,760
Location
west yorkshire
Guide Bridge to Stalybridge is indeed complete but it never ( afaik ) got an E or W number - however, I have annotated and edited my post.
Thanks. Is guide bridge to Stayly wiring completed and fully usable. Are any services actually using the new overhead.
K
 
Last edited:

plugwash

Established Member
Joined
29 May 2015
Messages
1,785
and are any services actually using it.
If there are, I don't think there will be very many of them. The TPEs that run via guide bridge tend to be the shorter distance services which are normally run with 185s.

Maybe some ECS or diverted services will use it, but I don't think it will get used much until the electrification reaches at least huddersfield and TPE get some EMUs from somewhere..
 

Meerkat

Established Member
Joined
14 Jul 2018
Messages
9,174
Without wandering into “what should happen” am I the only one a bit depressed that Leeds to Micklefield seems to be getting electrified as is, making any capacity upgrades of a congested line even more expensive and disruptive?
 

Legolash2o

Member
Joined
27 Sep 2018
Messages
666
Without wandering into “what should happen” am I the only one a bit depressed that Leeds to Micklefield seems to be getting electrified as is, making any capacity upgrades of a congested line even more expensive and disruptive?
How congested is that section?
 

takno

Established Member
Joined
9 Jul 2016
Messages
6,063
Without wandering into “what should happen” am I the only one a bit depressed that Leeds to Micklefield seems to be getting electrified as is, making any capacity upgrades of a congested line even more expensive and disruptive?
If it waited then the electrification would never happen. This section isn't as busy or mixed as the central section, better acceleration from emus combined with digital signalling is likely to see most of the benefits of quad tracking without a lot of the cost
 

geordieblue

Member
Joined
11 Jan 2020
Messages
704
Location
Leeds
Without wandering into “what should happen” am I the only one a bit depressed that Leeds to Micklefield seems to be getting electrified as is, making any capacity upgrades of a congested line even more expensive and disruptive?
I can’t remember where I read it now but a Leeds City Council document that came out relatively recently showed four-tracking somewhere between Leeds and Garforth - I think it ended before Thorpe Park. So if it isn’t happening then it must have been descoped in the last few months. Alternatively it doesn’t need planning permission, because it’s on railway land, and so details haven’t been communicated to the public? But that would seem unusual for a project which seems to love re-issuing old news stories!
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
9,327
Location
Dalton GA USA & Preston Lancs
If it waited then the electrification would never happen. This section isn't as busy or mixed as the central section, better acceleration from emus combined with digital signalling is likely to see most of the benefits of quad tracking without a lot of the cost.
Which is a sensible pragmatic approach imho.
 

Snapper

Established Member
Joined
28 May 2006
Messages
2,440
Location
All over the place
Was done about 2-3 months ago to be fair. Doesn't seem to be any more going down in a hurry though
True, it's hardly fresh this week, but it is the first track. I think there's a lot more muck to be moved before any more can be laid. I have noticed ballasted track in the Huddersfield compound but that's not connected to anything yet either.
 

coxxy

Member
Joined
16 Aug 2013
Messages
369
Yeah I think there's lots of little goings OK starting to appear.. noticed little red flags near Deighton, Heaton Lodge and mirfield that appear to be placed to show the future track placement, as well as more and more groundworks taking place everywhere. I think the Thornhill area seems to be very busy atm!
 

Snapper

Established Member
Joined
28 May 2006
Messages
2,440
Location
All over the place
Yeah I think there's lots of little goings OK starting to appear.. noticed little red flags near Deighton, Heaton Lodge and mirfield that appear to be placed to show the future track placement, as well as more and more groundworks taking place everywhere. I think the Thornhill area seems to be very busy atm!
Indeed. I hope to get out and about again to have a look at some other locations - if it ever stops raining!
 

stibz

Member
Joined
7 May 2014
Messages
72
Also lots of tree clearing going on slowly between Ravensthorpe & Mirfield, plus new bridge work next to existing calder rd bridge Nr Ravensthorpe station.
True, it's hardly fresh this week, but it is the first track. I think there's a lot more muck to be moved before any more can be laid. I have noticed ballasted track in the Huddersfield compound but that's not connected to anything yet either.
As observed, nothing happens quickly when it's taxpayer funded. When I worked in construction, it was get it done asap. but railway is a different thing lol The Only deadline is, whenever it's done!!
 

185

Established Member
Joined
29 Aug 2010
Messages
5,474
Whilst I've not seen it yet, I'm told DFT have published the Transport & Works Act for Leeds-Micklefield earlier today. I can't post my colleagues twitter, but I'm quite sure it's online somewhere. Mention of alterations to four bridges for electrification.
 

Top