WCML disruption from Birmingham NS to Rugby

Status
Not open for further replies.

MarkWi72

Member
Joined
13 Nov 2017
Messages
243
Currently at Hampton-In-Arden. It’s a bit disrupted to say the least! Pendos-aplenty. Three freights , two 350s and a couple of XC Voyagers in 40 minutes. The Colwich work is having an impact along this stretch of line. 2 Brum- Euston LNWR services have been cancelled(13.49 &14.19).
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
16,023
Currently at Hampton-In-Arden. It’s a bit disrupted to say the least! Pendos-aplenty. Three freights , two 350s and a couple of XC Voyagers in 40 minutes. The Colwich work is having an impact along this stretch of line. 2 Brum- Euston LNWR services have been cancelled(13.49 &14.19).
Points failure at Stechford, the crossover in the down direction. 1500 minutes and counting.
 

MarkWi72

Member
Joined
13 Nov 2017
Messages
243
Someone just mentioned this. The last thing they need on such a week.
 

Oxfordblues

Member
Joined
22 Dec 2013
Messages
665
Easy to say in retrospect I know, but surely the critical facing crossover at Stechford should have received some preventative maintenance in advance of the diversions?
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
13,441
Location
Bristol
Easy to say in retrospect I know, but surely the critical facing crossover at Stechford should have received some preventative maintenance in advance of the diversions?
There's only so much preventive work can do. The failure could be anything, and many of them would have happened whether or not a P-Way team had visited with some spanners in the weeks before.
 

800001

Established Member
Joined
24 Oct 2015
Messages
3,609
Easy to say in retrospect I know, but surely the critical facing crossover at Stechford should have received some preventative maintenance in advance of the diversions?
How much work would you like them to do? The best maintained equipment in the world can still have issues.

I’m sure NWR had done all the required work to maintain their asset.
 
Status