• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Werrington grade separation updates

Status
Not open for further replies.

HSTEd

Veteran Member
Joined
14 Jul 2011
Messages
16,825
If true its a particularly appalling example of value engineering. The dive under project is solely for freight to be diverted from the ECML, now even more important as HS2 will no longer relieve it. According to DfT the rail network has to be decarbonised by 2040, yet for freight there is no known alternative to electric traction, as hydrogen and battery technology can't do the job. For that reason NR's own Traction Decarbonisation Network Strategy - Interim Programme Business Case (networkrail.co.uk) marks the line as 'core electrification' so why on earth would you not design the dive under to be capable of being wired?!

Strikes me as standard railway short termism to be honest.

It probably saved £1m or something, but will cost many tens of millions to fix later.
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
1,671
Location
Nottingham
The Modern Railways article says the diveunder is designed to accept electrification with a conductor bar and converting from ballasted to slab track. Which was probably the right choice when the decision was made.
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
23,415
Location
Bolton
The Modern Railways article says the diveunder is designed to accept electrification with a conductor bar and converting from ballasted to slab track. Which was probably the right choice when the decision was made.
Indeed. The additional cost of using 'slab track' today, when there's no electrification to come for many years, would have been significant.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,784
Location
Leeds
The Modern Railways article says the diveunder is designed to accept electrification with a conductor bar and converting from ballasted to slab track. Which was probably the right choice when the decision was made.
I can't find the specific reference to slab track in my copy, where the wording is as I quoted in #626. Maybe it's different if you have access to the online version.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,511
Location
Between Peterborough & Bedlington
ORR has Authorised the Werrington dive under into use this afternoon.
Full EIS due on Sunday!

Indeed. The additional cost of using 'slab track' today, when there's no electrification to come for many years, would have been significant.
Especially as electrification plans for the PMJ route (the Stamford lines, and onwards to the MML/WCML etc.) and the Joint Line haven't materialised yet. Wiring the Joint Line and the Stamfords would be best done as part of another, separate project, as the OLE on the ECML would also need to be altered along the entire length of the realigned Up Stamford. Structures may even need to be 'shared' between the diveunder (at its southern extremities in the sheet piles) and the Up Stamford; this is of course just speculation on my part.
 
Last edited:

InOban

Established Member
Joined
12 Mar 2017
Messages
4,226
Full EIS due on Sunday!


Especially as electrification plans for the PMJ route (the Stamford lines, and onwards to the MML/WCML etc.) and the Joint Line haven't materialised yet. Wiring the Joint Line and the Stamfords would be best done as part of another, separate project, as the OLE on the ECML would also need to be altered along the entire length of the realigned Up Stamford. Structures may even need to be 'shared' between the diveunder (at its southern extremities in the sheet piles) and the Up Stamford; this is of course just speculation on my part.
Apologies for ignorance, but EIS stands for? (Apart from my old trade union )
 

norbitonflyer

Established Member
Joined
24 Mar 2020
Messages
2,512
Location
SW London
The only one which could probably use the dive-under is the 18:35 Lincoln to Peterborough, as that will form the 20:12 Peterborough to Nottingham via Melton service. Just to save that Nottingham service having to cross over from platform 2 towards the Stamford lines.
RTT for dates after the timetable change shows that service is scheduled to use platform 2B
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
13,541
Location
Bristol
But we will end up paying for it long term. ECML wiring - in the past couple of years its having work done to it to 'physically' strengthen it, never mind the power upgrades.
But doing it to the minimum first time got it done. It's not a perfect world, and you sometimes just can't stretch the budget far enough.
I suspect the diveunder won't be wired for a long time yet, and that it will save more disruption by eliminating the flat crossings in it's un-wired life than it will take to convert it to slab track and wire it up when it's time comes. It's also entirely possible that by the time we do come to electrify the GNGE better understanding and equipment means they can use smaller clearances and not need to touch the track at all.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
29,261
But we will end up paying for it long term. ECML wiring - in the past couple of years its having work done to it to 'physically' strengthen it, never mind the power upgrades.

I agree that it seems an odd decision, sufficiently so that there must be a good reason for it. Knowing how the box was built, making it another 300mm taller (or whatever it needs) would have cost essentially nothing. Therefore if it really doesn’t have electrification clearances, there must be something site specific about gradient or ground conditions that required it to be the dimensions it is.

Regardless, at least it has W12 clearance :)
 

IrishDave

Member
Joined
30 Jun 2009
Messages
380
Location
Brighton
It's unlikely diverted passenger services would need to use it, as a diversion is only necessary if the ECML towards Grantham is closed, in which case there is no conflict using the flat junction. (Just possibly, if the closure is between Grantham and Newark, a northbound passenger service for Doncaster or beyond might use the diveunder to avoid conflict with a southbound Liverpool - Grantham - Norwich train)
The only circumstance in which diverted trains would need to use the diveunder would be a block at the flat junction at Werrington itself, since that would entail blocking the ECML and the flat route to Lincoln. As it happens, such circumstances are planned for the weekends of 12th/13th and 19th/20th November 2022 according to the Engineering Access Statement (that's weeks 33 and 34 for those who think in weeks!). This is to permit renewal of the S&C at Werrington Junction; the notes explicitly state:

"TRAINS TO TRAVEL FROM MARHOLME JN TO GLINTON JN VIA THE DIVE UNDER, THEN DIVERTED VIA GNGE BETWEEN GLINTON JN JN AND DONCASTER. NO ACCESS TO THE GNGE VIA WERRINGTON JN"

Those weekends could therefore be the first non-charter passenger trains over the diveunder.
 

Brissle Girl

Established Member
Joined
17 Jul 2018
Messages
2,808
I agree that it seems an odd decision, sufficiently so that there must be a good reason for it. Knowing how the box was built, making it another 300mm taller (or whatever it needs) would have cost essentially nothing. Therefore if it really doesn’t have electrification clearances, there must be something site specific about gradient or ground conditions that required it to be the dimensions it is.

Regardless, at least it has W12 clearance :)
I believe the level of the underpass was significantly constrained by drainage issues, so it may have been quite expensive to provide that extra clearance.
 

RichE

Member
Joined
30 Oct 2017
Messages
6
On at least one site visit I asked about OHLE clearance and I was told the box has sufficient headroom within it for electrification.

Incidentally the track is still not in use as at lunchtime today.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,528
They had to install a siphon on the stream that crosses the track. I wonder if they could have built that at a slightly lower level?
There seems no reason why not - although it’s quite massive and complex it wouldn’t be any more complex if a metre deeper.

For anyone who missed it post #613 in this thread has a video simulation of the siphon and associated stuff.
 

55002

Established Member
Joined
16 Aug 2019
Messages
2,920
Location
Ldn
4E21 Felixstowe to Tinsley used the dive under today apparently according to a twitter post.
 

OxtedL

Established Member
Associate Staff
Quizmaster
Joined
23 Mar 2011
Messages
2,574
RTT showing “No report” at Werrington Junction would also substantiate that, I think?
RTT also shows all three of the above trains as joining the Down Stamford after leaving Peterborough, which would also strongly support the use of the diveunder.
 
Status
Not open for further replies.

Top