• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Issues North of Newcastle - Plessey Viaduct - 09/10 (onwards)

Deepgreen

Established Member
Joined
12 Jun 2013
Messages
6,408
Location
Betchworth, Surrey
Shows why they have issues


Is it going to withstand that? Can’t see pax being happy taken over that.
99.9% of them will have no idea. The others will either be nervous or confident that it's safe.

Not really a surprise but LNER staff being briefed today that the repair is going to take multiple weeks
Does that mean 'several'...?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
6,174
Location
Surrey
From what my friend told me its more than a couple of weeks but less than several months, multiple was the term he said was used when he was told
Need to scaffold that side on bridge 4-5 days, prepare the structure and then rebuild 7-10 days, 2 days to reinstate the track add in 2-3 days to sort site access and some contingency and 3/11 becomes potentially feasible if its 24hr working.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
30,879
Location
Scotland
Engineering question, and one that I know might be impossible to answer, but would I be correct in the assumption that the parapets aren't structural to the viaduct itself? In other words, the structural part of the viaduct is flat topped and the parapets were built on top of that.
 

Bletchleyite

Veteran Member
Joined
20 Oct 2014
Messages
98,104
Location
"Marston Vale mafia"
Engineering question, and one that I know might be impossible to answer, but would I be correct in the assumption that the parapets aren't structural to the viaduct itself? In other words, the structural part of the viaduct is flat topped and the parapets were built on top of that.

I believe so yes, the parapets are concrete and obviously retrofitted when you look at a photo of it (e.g. post 116).
 

HurdyGurdy

Member
Joined
30 Aug 2023
Messages
296
Location
Bulbourne
Engineering question, and one that I know might be impossible to answer, but would I be correct in the assumption that the parapets aren't structural to the viaduct itself?

If you study civil engineering your degree course will hardly mention masonry arches at all, so even well qualified engineers nowadays use the term 'parapet' fairly loosely. But my interpretation is that on a masonry bridge or viaduct a parapet is a non-loadbearing wall or barrier.

Many masonry arch railway bridges and viaducts were built without parapet walls and had railings or other barriers added at a later date. From the photos posted on this thread, it looks to me that Plessey viaduct is one of those. So I would not describe the part of the structure which has collapsed as a parapet. To me it's part of the spandrel wall, which supports the backfill above the arch(es) right up to track level, so definitely is structural and loadbearing.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,505
If you study civil engineering your degree course will hardly mention masonry arches at all, so even well qualified engineers nowadays use the term 'parapet' fairly loosely. But my interpretation is that on a masonry bridge or viaduct a parapet is a non-loadbearing wall or barrier.

Many masonry arch railway bridges and viaducts were built without parapet walls and had railings or other barriers added at a later date. From the photos posted on this thread, it looks to me that Plessey viaduct is one of those. So I would not describe the part of the structure which has collapsed as a parapet. To me it's part of the spandrel wall, which supports the backfill above the arch(es) right up to track level, so definitely is structural and loadbearing.
Makes it rather incredible that in that earlier Twitter feed NR’s PR people refer to the parapet having “moved”, and then there’s a rather worrying implication that they were unable to “quickly move the parapet back to its original position”. Are we supposed to believe all this heavy stuff just sits there unsecured, held in the right position by its own weight?

They're not engineers though, just PR people - and I wonder if they intentionally lose detail in the process, to try and sound reassuring…
 

HurdyGurdy

Member
Joined
30 Aug 2023
Messages
296
Location
Bulbourne
Are we supposed to believe all this heavy stuff just sits there unsecured, held in the right position by its own weight?

Not just by its own weight, but a masonry arch supports the imposed load (dead and live) because its elements stay in compression. Similarly, a masonry wall can be loadbearing.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,505
Not just by its own weight, but a masonry arch supports the imposed load (dead and live) because its elements stay in compression. Similarly, a masonry wall can be loadbearing.
Sorry I meant only the bit that NR claims to have “moved” (I’m assuming sideways), - surely the idea that if it moves you can just move it back seems to be a major simplification?
 

HurdyGurdy

Member
Joined
30 Aug 2023
Messages
296
Location
Bulbourne
Sorry I meant only the bit that NR claims to have “moved” (I’m assuming sideways), - surely the idea that if it moves you can just move it back seems to be a major simplification?

As mentioned by several members upthread, what NR posted on X oversimplifies and plays down the extent of the damage shown in the photos.
 

DelW

Established Member
Joined
15 Jan 2015
Messages
3,906
Engineering question, and one that I know might be impossible to answer, but would I be correct in the assumption that the parapets aren't structural to the viaduct itself? In other words, the structural part of the viaduct is flat topped and the parapets were built on top of that.
There wasn't normally a slab or equivalent at track level, though there might be transverse tie rods. Normally once the arches were complete, and probably while they were still supported by centering, the spandrel walls (side walls) were built up to track level, then upwards as parapets. The volume above the arches and between the spandrels was backfilled to support the track. Sometimes viaducts with structural problems have been retrofitted with slabs at track level to relieve loads on the masonry.

Sorry I meant only the bit that NR claims to have “moved” (I’m assuming sideways), - surely the idea that if it moves you can just move it back seems to be a major simplification?
I took "moved" to have been a less scary euphemism for "fell off into the valley", but I may be wrong. The possibility of pushing a parapet that had moved back into place does seem unlikely even if it hadn't fallen off completely.
 

HurdyGurdy

Member
Joined
30 Aug 2023
Messages
296
Location
Bulbourne
probably while they were still supported by centering, the spandrel walls (side walls) were built up to track level, then upwards as parapets.

Once everything was backfilled and built up to track level there would inevitably be a displacement of the arch(es) and spandrels when the centering was struck. Anything previously built straight or level would then appear to sag. So usually the centering would be struck before topping off the spandrels and laying a straight or level string course or coping. If required, the string course would be the footing for the parapet wall.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,763
Location
Leeds
Many masonry arch railway bridges and viaducts were built without parapet walls
A bit like Pontcysyllte, where there is nothing on the non-towpath side of the canal to stop a person falling off a boat and 120ft down.

Are open boats allowed?
 

alf

On Moderation
Joined
1 Mar 2021
Messages
356
Location
Bournemouth
It appears there is at least one & a half metres of ballast sitting atop the viaduct at the collapse point. Is that normal?
At 1.5 tonnes a cubic metre of dry compressed ballast that is a load over & above track & train of almost 11 tonnes per meter length for the double track. Over the length of a 23 metre coach that is 253 tonnesover the width of the viaduct. Then there is the coach weight of 40 tonnes plus the rail & sleeper weight.
That is an amazing extra load. And is based on the ballast being dry.

I bet the 1840 engineers did not calculate for anything like this massive dynamic load downwards & a vector of it sideways into the ballast holding walls.
 

DelW

Established Member
Joined
15 Jan 2015
Messages
3,906
Once everything was backfilled and built up to track level there would inevitably be a displacement of the arch(es) and spandrels when the centering was struck. Anything previously built straight or level would then appear to sag. So usually the centering would be struck before topping off the spandrels and laying a straight or level string course or coping. If required, the string course would be the footing for the parapet wall.
Yes, good point. IIRC from my bridge building days, we always struck the deck soffit supports before finally levelling in the coping formwork for exactly that reason.
 

Trestrol

Member
Joined
12 Apr 2022
Messages
210
Location
Newcastle
Apologies for going off topic, do you know when this is planned for? Thanks!
Not sure but I think after the reprieve of Tyneside IECC and it's upgraded to a mini ROC it won't be long. Although all three NML boxes have had new panels. With the expansion of the operating floor there was also talk of moving stuff from York ROC. York ROC is very crowded as it was underestimated the size of the equipment in the equipment room would take. When York IECC moved to the ROC the only thing that moved were the workstations. All the equipment is still in the IECC as there's no room in the ROC. This of course didn't stop NR property coming round trying to flog the land off.
 

Craggle

New Member
Joined
10 Oct 2023
Messages
1
Location
Northumberland
New user here, this happened very close to where I live and I usually walk the dog along the riverside path under the viaduct. Saw this sign this afternoon in Plessey Woods country park, informing said path is shut giving a finished date of 27th November. It's a council sign so make of that what you will.
 

Attachments

  • 20231010_180151.jpg
    20231010_180151.jpg
    2 MB · Views: 121

TrackLad

New Member
Joined
10 Oct 2023
Messages
1
Location
York
The structure is listed and details of strengthening works as well as cross sections of the original construction are available on the planning portal.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
6,174
Location
Surrey
The structure is listed and details of strengthening works as well as cross sections of the original construction are available on the planning portal.
Good find. So the concrete walkway lintels were added back in 1978 and then in 2014 permission was sought to strengthen the walkways due to

The most recent detailed structural examination report for the structure has highlighted that the precast concrete walkway units on the structure are showing signs of outward lateral movement and it is recommended that stitching bars are installed through the walkway units to restrain this movement.
Also cross section of bridge provided
1696969504313.png

So with those rods tying it all together if the top started to overturn it could take a fair part of the structure with it compounded by the supporting safety barrier tying it altogether longitudinally

1696969796224.png
 

HurdyGurdy

Member
Joined
30 Aug 2023
Messages
296
Location
Bulbourne
Good find.

Excellent. It clarifies the construction. Apart from the walkway with handrail and the original vertical dowel bars fixing it into the plinth and copings, you can see the reinforced concrete lining of the arches.

The section shown must be at the crown of the arch, where the angled 1500mm long stitching dowels are fixed into the voussoirs, which are the external face elements of the arch rings. The dead load of backfill holds the arch ring in compression. If the dowels were the same length at a section further from the crown of the arch, they would only penetrate the plinth, copings and spandrel wall. These are not held in the same compression, so will have a more limited resistance to overturning and support less vertical and/or lateral load on the overhanging walkway.

Overturning of the spandrel wall is one of the modes of structural failure described in the document found by @najaB, upthread.
 

GuyGibsonVC

Member
Joined
29 Nov 2019
Messages
40
Location
Up North
The SIMBID running between Plessey and Morpeth is scheduled to continue until 04/11/23 and the speed over the Down on the viaduct is 50mph.

The independent coffee shop in Morpeth station has endured quite a torrid 18 months with weeks of industrial action, engineering blockades and now this!
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
23,407
Location
Bolton
The actual viaduct and the track bed is solid and safe.
Indeed - they're just as safe as the hundreds of other similar railway bridges that go through the same regime of inspection and maintenance.
 

Amlag

Member
Joined
8 Jul 2018
Messages
228
Indeed - they're just as safe as the hundreds of other similar railway bridges that go through the same regime of inspection and maintenance.

AND with the added safety hazard of the damage being caused by roots of increasingly large bushes and trees growing in their structures.
 

PM77

Member
Joined
14 Aug 2022
Messages
24
Location
York
When York IECC moved to the ROC the only thing that moved were the workstations. All the equipment is still in the IECC as there's no room in the ROC. This of course didn't stop NR property coming round trying to flog the land off.
Not entirely true. When the IECC moved to the ROC the IECC part went with it, although on a more modern compact system. Some interlockings have been migrated into the ROC and more are planned to go next year.
 
Joined
1 Nov 2021
Messages
117
Location
Berwick
My daughter has just crossed southbound and took a video, there's obviously lots of activity in the field leading up to it. Her quote is that "it is off putting"
 

Attachments

  • f2a29b5c-264b-4438-8a84-e433330713ba.mov
    6 MB

Senex

Established Member
Joined
1 Apr 2014
Messages
2,755
Location
York
There was an item on BBC Look North yesterday evening (https://www.bbc.co.uk/iplayer/episo...-north-east-and-cumbria-evening-news-10102023 - about 6 minutes in) which gave a clear and concise explanation of what's happened and wht is going on. The NR spokesman was Paul Rutter, whom I take to be one of the senior engineers dealing with it all — certainly miles away from the sort of PR waffle the TOCs generally seem to offer.
 

Top