Consultation opened for remodelling of Oxford Road station to relocate terminating bay platform to centre and have just 2 lengthened through platforms:
https://www.networkrailmediacentre....ans-to-improve-manchester-oxford-road-station
https://www.networkrailmediacentre....ans-to-improve-manchester-oxford-road-station
The consultation launched today (Monday 20 January), will consider upgrades including longer platforms, track and signalling improvements, as well as construction of a new station footbridge with lifts serving all platforms.
Outline proposals being brought forward by Network Rail include reconfiguring the platform layout, leaving a total of three platforms each capable of accommodating longer trains. The two, longer through-platforms will be able to take eight car trains, while a new turn-back platform will accommodate six car trains; an increase in capacity of two cars per platform.
Proposed track layout and signalling improvements will reduce congestion by removing conflicting train movements. Overhead line equipment will also be upgraded, as well as over 900m of new track being laid.
The remodelling scheme includes improvements to accessibility throughout the station, featuring a new footbridge with increased movement space for passengers and new lifts allowing step free access to all platforms. Wider, resurfaced platforms and improvements to existing lifts are also planned