My understanding from previous posts is that bridges that required work were sorted out, but there are bridges on the route that would have to be replaced for electrification.
During the EWR TWAO public inquiry I asked a couple of questions about this.
Questions and responses from NR below. From Inquiry Doc NR 211
3. The cost of replacing those existing bridges between Bicester and Bletchley
that would need to be replaced/subject to some works to enable electrification
but which are not currently proposed to be replaced?
There are 5 structures along this route which would require partial or complete
demolition followed by replacement with new structures to provide for future
electrification. The total cost to the project of these works would be
approximately £34.5m.
4. The cost difference between works to those bridges before EWR2 becomes
operational as compared to after it has become operational?
The total cost of the above works once EWR2 has become operational would be
approximately £41.8m. This means that the difference in cost between doing the
works before EWR2 becomes operational and afterwards is approximately £7.3m.