AndyY1951
Member
It would be nice to think that Network rail could do something to progress the GCR job while the are at it!
Here is a picture of the repaired bridge 348 with its lattice parapet.
View attachment 113328
Also a picture of the A 60 bridge, which is to be replaced in October by a new bridge.
View attachment 113329
The cable is in concrete troughs on each side of the bridge, but there doesn't seem to be space to use troughs across the bridge without getting too close to the tracks.With Bridge 348, was there any (technical) reason why the signalling cable couldn't have been laid at ballast level?
With Bridge 348, was there any (technical) reason why the signalling cable couldn't have been laid at ballast level?
If it is Fibre-Optic then there much more restriction on the curvature such cable can be given. To dodge round the abutment pillars at low level would have needed bends that would have been too sharp. And Nottingham59's comments above are also valid for either electrical or fibre-optic cables.Hi Railfan
I think that those cables are part of a fibre optic network and so not owned by the GCR. Having that extra loop may have been part of the rebuilding of that bridge and to give a degree of resilience in case of future work...possibly?
The A60 Bridge work is starting this coming weekend.
"Temporary road closures are will be in place on the A60 Nottingham Road between the junction of Station Boulevard, Loughborough, and the junction of Loughborough Road, Cotes, from 01st October 2022 to allow Volker Laser, on behalf of the GCR to safely undertake works to replace the rail overbridge.
The existing 120 year old structure is life expired and has been struck many times by over height lorries. Replacing it with a twin track structure, will allow freight trains from the national rail network to use the line again as well as paving the way for heritage trains to run between Leicestershire and Nottinghamshire as part of the Reunification project."
Sounds good.News from the GCR website.
The A60 Bridge work is starting this coming weekend.
"Temporary road closures are will be in place on the A60 Nottingham Road between the junction of Station Boulevard, Loughborough, and the junction of Loughborough Road, Cotes, from 01st October 2022 to allow Volker Laser, on behalf of the GCR to safely undertake works to replace the rail overbridge.
The existing 120 year old structure is life expired and has been struck many times by over height lorries. Replacing it with a twin track structure, will allow freight trains from the national rail network to use the line again as well as paving the way for heritage trains to run between Leicestershire and Nottinghamshire as part of the Reunification project."
Let's hope it is either a much shallower deck (higher above the road) or the road is lowered - or that there are massive girders placed at bridge height either side to stop "over-height lorries" continuing to hit it in the future.The existing 120 year old structure is life expired and has been struck many times by over height lorries. Replacing it with a twin track structure, will allow freight trains from the national rail network to use the line again as well as paving the way for heritage trains to run between Leicestershire and Nottinghamshire as part of the Reunification project."
Presumably rebuilding the railway to provide the full clearance was not practical, understandably so. Collision beams will add to the cost though, and their presence suggests there's a regular enough lorry traffic on this route to make a collision a probability.The GCR have said that the bridge will have a greater clearance by virtue of design using all available techniques. The road cannot be lowered further as it is next to a brook which floods. There are "collision beams" in the design.
Excellent, will you be out with the camera following progress Phil?I have just been e mailed this...."the A60 bridge, there are two excavators on the track bed removing the ballast, so its begun!!!!!
I will try. I am at Rothley on the Windcutter Information/Sales Stand on Sat and Sunday so will try to pop along to Lbro to see progress.Excellent, will you be out with the camera following progress Phil?
That’ll be good if you can - hopefully this will enable things on the NHR to slowly start to come back again. Best of luck for the weekend, I need to pop up to the GCR sometime and have a look at the windcutter rake.I will try. I am at Rothley on the Windcutter Information/Sales Stand on Sat and Sunday so will try to pop along to Lbro to see progress.
Excuse my ignorance, but what is the windcutter rake.?That’ll be good if you can - hopefully this will enable things on the NHR to slowly start to come back again. Best of luck for the weekend, I need to pop up to the GCR sometime and have a look at the windcutter rake.
Hi StevieboyExcuse my ignorance, but what is the windcutter rake.?
Very nice they are too, along with the other freight wagons they do set the GCR apart in how it is able to operate, multiple long freights passing each other is a sight (and sound!) to see.Hi Stevieboy
A major feature of all railways (- indeed their very reason) was to move bulk loads from where they are to where they are needed. In the UK, for over 100 years, small four wheel wagons were used. Initially these had wooden bodies but, in the 1930's, more steel bodies became common and in WW2 a standard specification was drawn up. The 16 Ton mineral wagon. Over 220,000 were built and they were everywhere! Long trains, 40 or more trundled slowly (- because most had no vacuum brakes only handbrakes. At the top of inclines they were stopped and the guard would "Pin Down" a certain proportion to maintain a degree of control, plus the locomotive and manual brake van brakes) the length and breadth of Britain.
On the GCR they wanted to speed up the traffic so assembled trains with more vac brakes and "through pipes" so the driver had much more control. These fast freights were called "Windcutters" or Annesley "Runners".
By 1992 virtually All of these wagons had been scrapped but "Steam Railway" magazine organised a fund to buy the ones remaining to recreate that "Lengthy train" of 16T mineral wagons, the "Windcutter Rake" This was offered space and running on the GCR.
A small number of volunteers has been maintaining them ever since. The number of running vehicles has varied from 14 to 24 and we have 30 (with 6 on loan to the P&B Rly). We are trying to get a train of 30 running for our 30th anniversary in November......
I believe there is a bridge just to the North of East Leake which is a cause for concern when the locomotive runs round.....but I do not know the details.Is this bridge the only obstacle stopping The Gypsum Trains running again or are there more bridges on the Northern section which need attention?
Brilliant, thank you very much for this explanation, very informative, I know that type of wagons, but did not know they had that name. Cheers.Hi Stevieboy
A major feature of all railways (- indeed their very reason) was to move bulk loads from where they are to where they are needed. In the UK, for over 100 years, small four wheel wagons were used. Initially these had wooden bodies but, in the 1930's, more steel bodies became common and in WW2 a standard specification was drawn up. The 16 Ton mineral wagon. Over 220,000 were built and they were everywhere! Long trains, 40 or more trundled slowly (- because most had no vacuum brakes only handbrakes. At the top of inclines they were stopped and the guard would "Pin Down" a certain proportion to maintain a degree of control, plus the locomotive and manual brake van brakes) the length and breadth of Britain.
On the GCR they wanted to speed up the traffic so assembled trains with more vac brakes and "through pipes" so the driver had much more control. These fast freights were called "Windcutters" or Annesley "Runners".
By 1992 virtually All of these wagons had been scrapped but "Steam Railway" magazine organised a fund to buy the ones remaining to recreate that "Lengthy train" of 16T mineral wagons, the "Windcutter Rake" This was offered space and running on the GCR.
A small number of volunteers has been maintaining them ever since. The number of running vehicles has varied from 14 to 24 and we have 30 (with 6 on loan to the P&B Rly). We are trying to get a train of 30 running for our 30th anniversary in November......