MartinaLooksAt
New Member
Hello. I have looked on here before for research but not posted.Welcome to the forum. Your first post I see.
Hello. I have looked on here before for research but not posted.Welcome to the forum. Your first post I see.
Yoo it's the man himself! We're big fans over here. Your videos are routinely posted.Uhh I didn't mean to imply that the 2nd Bromford TBM had launched, only that Mary Ann was underway and that the 2nd TBM had arrived. Unless you're going by the footage itself in which case you know more than me.
I imagine it depends a lot on TBM depth and the type of soil/rock between the cutting head and the surface. Both of those will affect how much vibration reaches the surface.Do people who live above the TBM feel anything?
A team of 90 specialist engineers have completed the assembly of HS2’s giant tunnel boring machine (TBM) which will start digging the second bore of the 3.5 mile Bromford Tunnel into Birmingham in the new year. In one of the most impressive assembly operations to move sections of the machine into a 12 metre deep launch pit, two 600 tonne cranes lifted the huge new cutterhead into place at the front of the 125 metre long machine in the pit bottom. The first TBM, named ‘Mary Ann’ after Mary Ann Evans – the real name of Victorian writer George Eliot who was born in Nuneaton – started digging the first bore from the east portal site near Water Orton in August this year. It has already built more than 500 tunnel rings, which is 0.6 miles of the 3.5 mile long tunnel between North Warwickshire and Washwood Heath in Birmingham. The name of the second TBM will be revealed before it launches in Spring next year. ‘Mary Ann’ is set to break through at the end of 2024, with the second TBM planned to complete its journey in the middle of 2025.
I suggest that (not that I watched much of it) after his performance on I'm a Celebrity, the name for that borer should be Nigel.2nd TBM for Bromford Tunnel to begin tunneling in the new year, name is yet to be announced
Is Bromford one of the tunnels with a slightly smaller diameter due to lower speeds? If so I guess there’s a new shield and cutter head.It is.
But I believe it has been largely modified for Bromford which might justify a new name.
The TBM startup dates have evidently shifted back.
Yes there is that.Is Bromford one of the tunnels with a slightly smaller diameter due to lower speeds? If so I guess there’s a new shield and cutter head.
Is there a reason for this or is it just due to the geology of the land?I think Chiltern and Long Itchington have the largest diameter, with the others being somewhat smaller..
Speed - you need wider tunnels for higher speeds, because of the airflow.Is there a reason for this or is it just due to the geology of the land?
Chiltern tunnels dug by Florence and Cecilia will be completed next year, the others I don't believe have been stated by HS2 for certain, although very likely Lydia will finish the access tunnel next year.When abouts will the tunnel be completed? They said it would next year...
Ah thanks, do we not know when during next year? Like spring, summer....?Chiltern tunnels dug by Florence and Cecilia will be completed next year, the others I don't believe have been stated by HS2 for certain, although very likely Lydia will finish the access tunnel next year.
I think Florence has less than 2 months work (but might be stopped over Christmas and New Year).Ah thanks, do we not know when during next year? Like spring, summer....?
One of the directors of the venture working on the Chiltern tunnels said 'early next year' a few days ago, no more specific than that. The Chiltern drives just managed to pass 90% before Christmas so I would say Spring or even Winter for completion.Ah thanks, do we not know when during next year? Like spring, summer....?
I think Florence has less than 2 months work (but might be stopped over Christmas and New Year).
Because the TBMs need specialist crews, they are often timed so next one is set up and ready to go with crew transferring over.
Also they are often paused few metres short for week or two, if there is a PR and media breakthrough day booked.
ThanksOne of the directors of the venture working on the Chiltern tunnels said 'early next year' a few days ago, no more specific than that. The Chiltern drives just managed to pass 90% before Christmas so I would say Spring or even Winter for completion.
The tunnel segment factory there is now entirely complete, and is being shut down.The tunnel segment factory at Hyde will be winding down, but an adjacent facility is still producing the segments for the Colne Valley Viaduct.
The TBMs are currently undergoing routine maintenance whilst they are within our South Ruislip Vent Shaft site (behind the Victoria Retail Park). See the map overleaf for key dates (under the current programme) and locations once tunnelling is resumed
Worth remembering the Chiltern TBMs have had the advantage of having tunnel sections manufactured on site, whereas the Northolt ones are manufactured in Kent and delivered, however can’t say obviously if this is actually the limiting factor in progress.The progress on Northolt west is MUCH slower than the Chilterns - broadly, the chiltern TBMs have done a little under 500m per month, the Northolt TBMs less than 200m. At this rate they have more than 2 more years of tunnelling to go. Although if they could hit the chiltern rate, they’d be done by Christmas this year.
I guess the other half of the tunnel hasn’t been started yet, but I’d have thought getting it done quicker rather than slower would be cheaper?
The Northolt West TBMs certainly had some logistics issues at startup over segment supply and spoil removal, and had to make TBM modifications after early ground breeches.Worth remembering the Chiltern TBMs have had the advantage of having tunnel sections manufactured on site, whereas the Northolt ones are manufactured in Kent and delivered, however can’t say obviously if this is actually the limiting factor in progress.