• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

HS2 TBM Progress

Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Fazaar1889

Member
Joined
5 Oct 2022
Messages
486
Location
South East
Uhh I didn't mean to imply that the 2nd Bromford TBM had launched, only that Mary Ann was underway and that the 2nd TBM had arrived. Unless you're going by the footage itself in which case you know more than me.
Yoo it's the man himself! We're big fans over here. Your videos are routinely posted.
 

jfowkes

Member
Joined
20 Jul 2017
Messages
907
Do people who live above the TBM feel anything?
I imagine it depends a lot on TBM depth and the type of soil/rock between the cutting head and the surface. Both of those will affect how much vibration reaches the surface.

And some people are probably more sensitive than others too.
 

Fazaar1889

Member
Joined
5 Oct 2022
Messages
486
Location
South East
2nd TBM for Bromford Tunnel to begin tunneling in the new year, name is yet to be announced
A team of 90 specialist engineers have completed the assembly of HS2’s giant tunnel boring machine (TBM) which will start digging the second bore of the 3.5 mile Bromford Tunnel into Birmingham in the new year. In one of the most impressive assembly operations to move sections of the machine into a 12 metre deep launch pit, two 600 tonne cranes lifted the huge new cutterhead into place at the front of the 125 metre long machine in the pit bottom. The first TBM, named ‘Mary Ann’ after Mary Ann Evans – the real name of Victorian writer George Eliot who was born in Nuneaton – started digging the first bore from the east portal site near Water Orton in August this year. It has already built more than 500 tunnel rings, which is 0.6 miles of the 3.5 mile long tunnel between North Warwickshire and Washwood Heath in Birmingham. The name of the second TBM will be revealed before it launches in Spring next year. ‘Mary Ann’ is set to break through at the end of 2024, with the second TBM planned to complete its journey in the middle of 2025.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,792
Location
Leeds
Surely this is the same TBM that has already completed both bores at Long Itchington Wood under the name Dorothy?
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
19,779
Location
Mold, Clwyd
It is.
But I believe it has been largely modified for Bromford which might justify a new name.
The TBM startup dates have evidently shifted back.
 

Yindee8191

Member
Joined
16 Mar 2019
Messages
165
It is.
But I believe it has been largely modified for Bromford which might justify a new name.
The TBM startup dates have evidently shifted back.
Is Bromford one of the tunnels with a slightly smaller diameter due to lower speeds? If so I guess there’s a new shield and cutter head.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
19,779
Location
Mold, Clwyd
Is Bromford one of the tunnels with a slightly smaller diameter due to lower speeds? If so I guess there’s a new shield and cutter head.
Yes there is that.
I think Chiltern and Long Itchington have the largest diameter, with the others being somewhat smaller..
The geology will be different too.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
19,779
Location
Mold, Clwyd
The TBM updates from HS2 Ltd, for 18/19 December, look likely to be the last before the extended break over Christmas/New Year.

As usual the Chiltern pair are going well, and look likely to complete their drives in February - Florence has only 762m to go, or about 40 days work.
Mary Ann at Bromford has done 22% of its drive towards Washwood Heath.
But everything at the London end seems to be stopped, with no progress for weeks.
Shushila hasn't moved for 3 months, Caroline for 2.
Even Lydia at OOC, which only has 116m of its 753m drive to do, was seemingly stopped for December.

Perhaps this, along with the later start-up times for the remaining TBMs, reflects revised HS2 Ltd plans for more economical completion of the tunnelling works.
 

chris2

Member
Joined
25 Apr 2023
Messages
92
Location
Southampton
Thanks for the update, it’s great to know the progress and when they’re likely to be finished. It’s curious about the London drives…I’m wondering if deliveries of tunnel segments have also been paused? If six trains a week are still running they’re going to run out of room at some point!
 

Benjwri

Established Member
Joined
16 Jan 2022
Messages
1,909
Location
Bath
When abouts will the tunnel be completed? They said it would next year...
Chiltern tunnels dug by Florence and Cecilia will be completed next year, the others I don't believe have been stated by HS2 for certain, although very likely Lydia will finish the access tunnel next year.
 

Fazaar1889

Member
Joined
5 Oct 2022
Messages
486
Location
South East
Chiltern tunnels dug by Florence and Cecilia will be completed next year, the others I don't believe have been stated by HS2 for certain, although very likely Lydia will finish the access tunnel next year.
Ah thanks, do we not know when during next year? Like spring, summer....?
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
6,465
Location
West Wiltshire
Ah thanks, do we not know when during next year? Like spring, summer....?
I think Florence has less than 2 months work (but might be stopped over Christmas and New Year).

Because the TBMs need specialist crews, they are often timed so next one is set up and ready to go with crew transferring over.

Also they are often paused few metres short for week or two, if there is a PR and media breakthrough day booked.
 

Benjwri

Established Member
Joined
16 Jan 2022
Messages
1,909
Location
Bath
Ah thanks, do we not know when during next year? Like spring, summer....?
One of the directors of the venture working on the Chiltern tunnels said 'early next year' a few days ago, no more specific than that. The Chiltern drives just managed to pass 90% before Christmas so I would say Spring or even Winter for completion.
 

Fazaar1889

Member
Joined
5 Oct 2022
Messages
486
Location
South East
I think Florence has less than 2 months work (but might be stopped over Christmas and New Year).

Because the TBMs need specialist crews, they are often timed so next one is set up and ready to go with crew transferring over.

Also they are often paused few metres short for week or two, if there is a PR and media breakthrough day booked.
One of the directors of the venture working on the Chiltern tunnels said 'early next year' a few days ago, no more specific than that. The Chiltern drives just managed to pass 90% before Christmas so I would say Spring or even Winter for completion.
Thanks
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
19,779
Location
Mold, Clwyd
Florence has 762m to go.
The rates when working are usually between 15m and 25m per day, and 762/20 (average) gives c40 days.
Cecilia is currently about 400m behind, so will take another 20-odd days.
The final portal area might be slower, with more broken ground, and there will no doubt be a media event.
So assuming progress resumes in early January, I'd expect Florence to finish in mid-Feb and Cecilia a month later.

Whether the three TBMs being readied for work in the new year (that's the two at Northolt East, plus the second one at Bromford) will have started by then is unknown.
The Chiltern crews might then transfer to the other working TBMs (although the TBM contracts are with three different subcontractors).
The tunnel segment factory at Hyde will be winding down, but an adjacent facility is still producing the segments for the Colne Valley Viaduct.
 

Benjwri

Established Member
Joined
16 Jan 2022
Messages
1,909
Location
Bath
The tunnel segment factory at Hyde will be winding down, but an adjacent facility is still producing the segments for the Colne Valley Viaduct.
The tunnel segment factory there is now entirely complete, and is being shut down.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
19,779
Location
Mold, Clwyd
The first update for the new year is now visible on the TBM progress map.
On January 8, the Chiltern pair (Florence and Cecilia) are at 15468m and 15001m respectively.
This looks like steady progress if we take out the holiday stoppage period (Dec 22-Jan 3).

Nothing yet on the other TBMs.
There is a report and map on the Northolt West TBMs for December which doesn't yet match the map positions, but that may change this week.
The map also shows the location of cross-passages and where monitoring instrumants have been installed.
The TBMs are currently undergoing routine maintenance whilst they are within our South Ruislip Vent Shaft site (behind the Victoria Retail Park). See the map overleaf for key dates (under the current programme) and locations once tunnelling is resumed
 

chris2

Member
Joined
25 Apr 2023
Messages
92
Location
Southampton
The progress on Northolt west is MUCH slower than the Chilterns - broadly, the chiltern TBMs have done a little under 500m per month, the Northolt TBMs less than 200m. At this rate they have more than 2 more years of tunnelling to go. Although if they could hit the chiltern rate, they’d be done by Christmas this year.

I guess the other half of the tunnel hasn’t been started yet, but I’d have thought getting it done quicker rather than slower would be cheaper?
 

Benjwri

Established Member
Joined
16 Jan 2022
Messages
1,909
Location
Bath
The progress on Northolt west is MUCH slower than the Chilterns - broadly, the chiltern TBMs have done a little under 500m per month, the Northolt TBMs less than 200m. At this rate they have more than 2 more years of tunnelling to go. Although if they could hit the chiltern rate, they’d be done by Christmas this year.

I guess the other half of the tunnel hasn’t been started yet, but I’d have thought getting it done quicker rather than slower would be cheaper?
Worth remembering the Chiltern TBMs have had the advantage of having tunnel sections manufactured on site, whereas the Northolt ones are manufactured in Kent and delivered, however can’t say obviously if this is actually the limiting factor in progress.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
19,779
Location
Mold, Clwyd
Worth remembering the Chiltern TBMs have had the advantage of having tunnel sections manufactured on site, whereas the Northolt ones are manufactured in Kent and delivered, however can’t say obviously if this is actually the limiting factor in progress.
The Northolt West TBMs certainly had some logistics issues at startup over segment supply and spoil removal, and had to make TBM modifications after early ground breeches.
But after 8/13 weeks stopped for maintenance at South Ruislip there's probably now a stockpile of segments waiting to be installed.
Another stockpile (sourced from Hartlepool) is also starting to build up at OOC for the Northolt East TBMs about to start.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
19,779
Location
Mold, Clwyd
The Chiltern TBMs continue to storm onwards:
On Jan 15: Florence 15648m, Cecila 15167m, both moving close to 25m/day.
They have 412m and 893m left respectively to reach the north portal.

Of the other TBMs, nary a word since the pre-Christmas update on December 19.
 

Top