Levenmouth Rail Link project gets underway
Levenmouth moves a step closer to the reintroduction of passenger services for the first time in more than fifty years, bringing with it exciting new journey opportunities and economic benefits for the area.
www.networkrailmediacentre.co.uk
Levenmouth moves a step closer to the reintroduction of passenger services for the first time in more than fifty years, bringing with it exciting new journey opportunities and economic benefits for the area.
Following the green light from Transport Scotland for the £116.6m scheme, Network Rail has started construction of the Levenmouth Rail Link. The work includes the removal of the old track bed and other route preparation activities in advance of the re-instatement of a double track railway and passenger services to Leven.
By utilising much of the existing double track bed it allows a cost-effective delivery of capacity for passenger, charter and freight service growth and a step-change in new journey opportunities across the wider economic area to places of education, work and leisure.
The first services to run on the line will be diesel operated before conversion to electric operation at the earliest opportunity. Electrification now, as part of the Scottish Government’s decarbonisation action plan, will enable the earliest possible transition to electric services minimising future passenger disruption and ensuring work is delivered at the most efficient cost.
Two new fully accessible stations will be constructed at Cameron Bridge and Leven, both benefiting from active travel access infrastructure linking local communities and places.
The programme will also explore the potential opportunities for freight and tourist/charter train operations to maximise the value this transformational investment can bring to the Levenmouth area.