SteveRainhill
Member
- Joined
- 6 Jan 2013
- Messages
- 22
They seem to date from July 2012 (and have indeed been posted in this thread before).
Doing it incrementally is sensible enough if you want the extra capacity but don't have the funding/land to do it all at once. It can clearly be seen that the 2 phase approach was designed in such a way that you weren't really undoing much of the stage 1 work at stage 2, which was going to essentially be just throwing in an extra track and a touch more pointwork.
Thinking may well have moved on since then, and as you say doing it all at once if possible is also sensible, and is consistent with the week long blockade that appears to be planned for July 2014.
Thanks for the reminder of my original post.
Had a wander round Roby the other day. One can get fairly close to the embankment works as they are next to a playing field. But not much is to be seen. All the vegetation is stripped away, and there is what looks like a new haul road. There are patches of newish-looking rubble, perhaps where excavations have been made. But no sheet piling or signs of new concrete. Perhaps the work had been done using 'ground nails' (whatever they are!) that aren't visible from 20m or so.
The trackbed west of Roby is now somewhat clearer, and has guidelines sprayed on it. But large piles of logs and branches are still in situ between Roby and Huyton. At Roby some kind of structure was being put up on the farther disused platform, probably around the subway entrance or where they will excavate the lift shaft. The disused platforms are partially cut back and there are stacks of recovered bricks. At Huyton the infill between the disused platforms has not yet been removed. Visible progress remains pretty glacial.
A mystery is the work taking place half a mile east at the site of Huyton Quarry station. A new substation is the only thing I can think of to explain it, but I've not read anything indicating that.
Lineside residents in the vicinity (e.g. Rainhill) have received notification from NR of overnight piling works starting imminently.
Meagre news snippets I know!