Nym
Established Member
Just running as additionals would avoid a lot of hassle with the Metrolink Franchisee then, since they can run it under a different franchise (that would be a member of the ATOC?)
If Metrolink was to share the line with freight or other passenger trains then all Metrolink services to Altrincham would need to be tram-train. If that happened it would also allow passenger trains and freight to use the line through Sale to reach Deansgate heavy rail station, subject to other factors such as signalling and weight of units allowed on the newly laid track.
Oldham Rochdale Extension
The track and infrastructure, Overhead Line Equipment (OLE) and tram
stops works are now substantially complete to Oldham Mumps temporary
stop.
Dynamic vehicle testing required to ensure the infrastructure is ready for
passenger service will take place over the next few months.
As a result of the technical interface complexities encountered at the
junctions and subject to appropriate testing and commissioning, rather
than a phased opening as originally proposed, it is now anticipated to
commence services from Victoria Station to Oldham Mumps via Central
Park. Work is being undertaken over the next few weeks to assess the
implications for opening dates and an update will be provided to the
Combined Authority meeting on the 16th December and to the 20th
January meeting of the TfGM Policy and Capital Committee.
By introducing the service direct to Oldham Mumps the driver training
element of the works can be delivered much more effectively and
efficiently than previously envisaged with the original two staged
approach.
This stage is the section from Oldham Mumps to Rochdale Station, which
incorporates a long section of single line with bi-directional working which
will require several weeks of driver training.
Earthworks continue to progress along the line. Construction of the stops
is underway and bridge refurbishment work is ongoing. Track and OLE
works are currently being installed throughout the southern end of the
section.
Again, there is a key interface with Network rail in terms of introducing
Metrolink in the vicinity of Rochdale Railway Station and the Calder
Valley line.
With the issues experienced with the TMS programme on other parts of
the network, a 2-3 month delay to the opening date beyond Summer
2012 may arise. This will be kept under close review as TMS is rolled out
across the network.
East Manchester extension to Ashton
The entire outbound track has been laid from Manchester Piccadilly to
Droylsden, and the final sections of inbound track in the Droylsden area
are under construction. The overhead line is energised to Velopark and is
being installed along the remainder of the route.
Stop construction is progressing along the line and footway resurfacing is
also underway along Ashton New Road.
Good progress is being made on the section of line to Ashton with
construction continuing on drainage, track, tram stops and highway
works.
Consideration is also being given to the possibility of opening as far as
the Etihad Stadium, in advance of the full opening to Droylsden. This is
the subject of on-going discussions with the contractors and the operator.
The Traffic Regulation Orders (TROs) for the tramway along Ashton New
Road, Droylsden, have attracted some objections from the local
community and their representatives. In order to address these issues,
detailed discussions are on-going to develop and finalise agreed
mitigations.
As reported in the 24th June 2011 paper to the Committee, following the
changes at Droylsden to an island platform, the opening date for the East
Manchester extension was revised to Summer 2012. As a result of the
changes to the TMS implementation programme a consequential delay of
an additional 3 months to the opening of the line to Droylsden is likely.
The delivery of the line will be kept under close review as TMS is rolled
out across the system to identify whether the risk of a 3 month delay can
be mitigated.[/QUOTE]
http://www.transportforgreatermanch...ds/file/4233/item_08_metrolink_capital_update
The opening of the next phase of the £1.4bn 'big bang' Metrolink expansion looks set to be delayed by a troublesome computer system.
Transport bosses are set to tell the region's council leaders that completion work on the planned extensions to Oldham, Rochdale and Droylsden could have to be put back.
The new system, called Tram Management System (TMS), is designed to electronically 'map' the position of every tram and automatically control points and signals.
But it caused major disruption after it underwent trials at MediaCity last September and separate problems also delayed the Chorlton extension.
A report now says 'technical complexities' are delaying the roll-out of TMS across the expanding network.
Bosses said in summer that the first stage of the Oldham line to Central Park, which had been due in spring, was being put back until winter and the second phase to Oldham Mumps was being delayed from autumn to next spring.
The Central Park stage is not now expected to open until the Oldham Mumps stage opens and transport officials are assessing whether that will be put back from spring.
A report also says a delay of between two and three months 'may arise' on the already-delayed Rochdale extension putting it back to next autumn.
The report says a three month delay on the Droylsden line is also 'likely', which would also put it back to next autumn.
Progress on the Droylsden and Rochdale extensions will be kept under 'close review'.
Planned extensions to Ashton, Didsbury and Manchester Airport are unaffected.
Philip Purdy, TfGM Metrolink director, said the new system would deliver a 'great deal of benefits' for passengers including real-time passenger information.
He said: The problem is that the new system is as advanced as the current system is old and making them work together at this higher level is proving to be a significant challenge.
The 'big bang' is earmarked for completion in 2016 and would make Metrolink the biggest tram network in Britain.
Earlier this year the M.E.N. revealed that the TMS system was responsible for 24 service failures on the MediaCity 'spur' between September 2010 and February this year.
Engineers spent eight months sitting in a van next to the line watching trams go through the junction as part of 'manual monitoring' of the system.
We can today reveal that TMS has been behind tram disruption totalling more than 80 hours on the MediaCity 'spur' between January and May this year.
Data obtained under the Freedom of Information Act shows that this included a single 72-hour period of disruption due to a 'signalling irregularity' at the MediaCity junction on April 9.
TMS has not been to blame for any disruption on the spur since May.
Metrolink tram extensions to Oldham, Rochdale and Droylsden delayed by 'technical compexities'
http://menmedia.co.uk/manchestereve...nd-droylsden-delayed-by-technical-compexities
the same is on TFGM website too...
http://www.tfgm.com/tfgm_news.cfm?news_id=9008248?submenuheader=3
Thales have a lot to answer for. IMO much of the delay down to them not planning properly, and expecting hastily installed things to work first time around
Thales have a lot to answer for. IMO much of the delay down to them not planning properly, and expecting hastily installed things to work first time around.
That said, if it worked, the TMS would be a leading example of good practise. New control room seems to be coming on well at Old Trafford depot.
Thales have a lot to answer for. IMO much of the delay down to them not planning properly, and expecting hastily installed things to work first time around.
And you are the expert in shining hi-viz that will sort the problems out...... No, thought not!!! Can you prove they have done insufficient planning - no. Can you prove they have been hasty - no. Can you prove they believed solutions to work first time - no!!
There was an issue where they initially installed axle counters at ground level rather than rail height and it wasnt always picking up the vehicle going over but its mostly a software issue thats holding everything up.
Safety critical systems in any field are never simple engineering, you have to anticipate and program the system to deal with every possible combination of pathing events and hardware failures of individual or multiple components while also ensuring integrity checks so that a malfunctioning component isnt incorectly believed to be working.
Compared to some of the systems I've seen implemented by one guy in a lab, it's not that complex (Yes I am aware of the nature of safety critical programming)