The presentation (in PDF form) from the recent 'NR + public' meetings at places north of Mkt Harboro' has been published on NR's website.
It also gives locations of work compounds and substations (compounds in yellow, substations in pink):
It also gives locations of work compounds and substations (compounds in yellow, substations in pink):
- One at East Langton (where there'll also be a substation; East Langton ATS if memory serves),
- One at Kibworth Harcourt (Wistow Rd; no substation), and
- One at South Wigston (either side of Blaby Rd Overbridge; compound to the north, substation (South Wigston SATS) to the south).
- Ground Trial Holes: started 15/7/22, planned to run to 29/10/22;
- Compound Setup & Road Rail Access Point (RRAP) install: started 15/7/22, planned to run to 27/10/22;
- Vegetation Management: started 15/7/22, planned to run to 6/6/23;
- Piling: planned to run from October 2022 to August 2023;
- Steel installation (assuming main steel & small part steel): planned to run from November 2022 to September 2023;
- Wiring: planned to run from January 2023 to December 2023; and
- Adjustments & Assurance: planned to run from February 2023 to January 2024.