IIRC it was said TPE management felt changeover in a station was safer.
its not really a safety matter. More of a potential Performance matter. I suspect TPE may soon be reminded who is paying their bills.
IIRC it was said TPE management felt changeover in a station was safer.
Yes, maybe I should have said they’re risk averse.its not really a safety matter. More of a potential Performance matter. I suspect TPE may soon be reminded who is paying their bills.
Just about sums up todays railway. This is standard operating practice and operators can't be allowed to be selective.I agree, however in previous discussions insiders seemed to be suggesting it wasn’t going to be done on the section either side of Berwick on the ECML, despite NR installing the necessary track side control equipment. IIRC it was said TPE management felt changeover in a station was safer.
Another thing for GBR to sort out.
Yes, maybe I should have said they’re risk averse.
Precisely. Independently tensioned contact/catenary (i.e. one Tensorex or Balance Weight Assembly per wire) makes it easier to achieve. (All the new OLE on E1 is independently tensioned, while Colton Jn - York still has BWAs with Equalising plates, giving 11kN in each wire. Wouldn't surprise me if the new OLE has 12kN in the catenary, with 15kN in the contact)IIRC, the conditions for changeover (pan up) above 20mph were straight contact wire, correctly tensioned, without overlaps. That's easier to provide on new OLE than existing.
WAO
Afraid not on the linespeed front. Is it confirmed to be those explicit points?Is there any idea of when the linespeed on the Leeds lines between Church Fenton and the Holgate area will be raised to 125mph? And will any modifications have to be made to the existing electrification between Colton Jn and York?
its not really a safety matter. More of a potential Performance matter. I suspect TPE may soon be reminded who is paying their bills.
Perhaps charging for electricity use for all trains with pantograph when under the wires would put a suitable financial incentive in place. This would then only be voided/refunded if said electricity supply were unavailable.
That would be another case of a Governement funded organisation charging another Governement funded organisation.
Far easier to write a letter that says “Dear Matthew, I hereby require you to....
Well indeed. I was thinking of solving the problem in this and other situations - such that the excess costs sits with the concession holder.
Presumably the signalling will migrate to Manchester ROC, in the same group as Stalybridge and Ashton?Noticed this in the Weekly Operating Notice.
Forthcoming changes from Monday 6th June 2022 between Manchester Victoria & Stalybridge.
TRU W1 upgrade works.
* Track circuits replaced with axle counters
* Speed increase on the Rochdale Slow lines
* Closure of Baguley Fold Jn signalbox
* Speed increase on the Ashton lines
* Conversion of Clayton Bridge LC to MCB-OD
Only a very small area, essentially the signals immediately either side of Baguley Fold Jn (where the south-to-east curve from Philips Park South Jn on the Philips Park-Ashburys line meets the Victoria-Stalybridge line).What does Baguley Fold SB control?
Logic (!) would dictate Manchester North workstation within the ROC gains control, as they currently control either side of Baguley.Presumably the signalling will migrate to Manchester ROC, in the same group as Stalybridge and Ashton?
I assume that the signs maybe good that other electrification will get done so the extra takes us beyond Stalyvegas station to the tunnel mouth plus a really good over run on the Rochdale line plus to Guide Bridge etc. since been as good as confirmed from IRP that Stalybridge to Huddersfield will happen so no waste of piles and masts etc.I've just been re-reading some old posts in this thread. From #4074 on page 136 it appears that in May last year the Manchester-Stalybridge "dashboard" site,
, gave the total number of piles to be installed as 473. However it's now 543 and I think it has been for quite a long time. So 70 extra piles appeared at some stage - maybe the Guide Bridge line (which we have believed for a while now to be included) ?
Take it you meant Rochdale?I assume that the signs maybe good that other electrification will get done so the extra takes us beyond Stalyvegas station to the tunnel mouth plus a really good over run on the Rochelle line plus to Guide Bridge etc. since been as good as confirmed from IRP that Stalybridge to Huddersfield will happen so no waste of piles and masts etc.
Stalybridge construction limit is Waterloo Road.I assume that the signs maybe good that other electrification will get done so the extra takes us beyond Stalyvegas station to the tunnel mouth plus a really good over run on the Rochelle line plus to Guide Bridge etc. since been as good as confirmed from IRP that Stalybridge to Huddersfield will happen so no waste of piles and masts etc.
If the Stalybridge OLE ends at Waterloo, does that imply that Stalybridge Tunnel (i.e. beneath Stamford St) remains unwired? I guess that the RRAP at Spring St (pictured) would be the easternmost access point for works.Stalybridge construction limit is Waterloo Road.
Miles Platting has only the junction triangle wired but no plain line towards Rochdale.
Stalybridge to Guide Bridge IS included as far as Guide Bridge station.
Stalybridge tunnel has never been part of the Manchester-Stalybridge scheme. It's a difficult location (I think a bigger problem than Standedge, despite all the talk about the latter). No doubt it will be wired eventually as part of Stalybridge to Huddersfield, but it wouldn't surprise me to learn that some of the basic questions about how to do it have not yet been settled.If the Stalybridge OLE ends at Waterloo, does that imply that Stalybridge Tunnel (i.e. beneath Stamford St) remains unwired? I guess that the RRAP at Spring St (pictured) would be the easternmost access point for works.
I don't think they would put up a few masts and then stop, so presumably they'll continue.Is there works still ongoing or are they waiting for the next announcement to carry on with the OLE works?
I have been looking at the dashboard but looks like it hasn't been updated for a long time.Stalybridge tunnel has never been part of the Manchester-Stalybridge scheme. It's a difficult location (I think a bigger problem than Standedge, despite all the talk about the latter). No doubt it will be wired eventually as part of Stalybridge to Huddersfield, but it wouldn't surprise me to learn that some of the basic questions about how to do it have not yet been settled.
I don't think they would put up a few masts and then stop, so presumably they'll continue.
The absence of information is frustrating.
Might we hear something at the turn of the financial year???
\it's been saying 40% for months, I think.I have been looking at the dashboard but looks like it hasn't been updated for a long time.