• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Would electrifying the WEML, Marshlink, North Downs and Uckfield lines with third rail be possible under the ORR's current policy?

yorksrob

Veteran Member
Joined
6 Aug 2009
Messages
41,299
Location
Yorks
It's the difference between travelling with your enthusiast hat on, and travelling because you need to be somewhere!

You say that, but as a current traveller on both modern and thumper stock, I still find the thumper more comfortable.

Infact, if the thumper were on a service train, I'd probably be more likely to get a double (or triple) seat to myself than on a railtour, making it even more comfortable !
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Joined
2 Feb 2019
Messages
512
ORR may consent to a system where short sections are livened up as trains approach then discharge after passage
The battery ground charging kit at West Ealing for the Greenford branch is only live when the train's charging contact kit is above the ground kit, so if a person came in contact with the ground kit at any other time there's no risk of electrocution. If it's possible to have a third rail section that works like this (and doesn't activate if other "conductors" make contact) that would be safer, particularly where it's installed in stations (the RAIL article cited this as being critical as accelerating out of stations is a key energy demand).
It appears from the interview with Neil Drury of SWR at 36 to 39 minutes of the following Green Signals Episode 57 that the plan for the West of England railway is for third rail sections which are only switched on and live when there is a train in section that needs it.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,245
Location
Surrey
It appears from the interview with Neil Drury of SWR at 36 to 39 minutes of the following Green Signals Episode 57 that the plan for the West of England railway is for third rail sections which are only switched on and live when there is a train in section that needs it.
Heard that interview although have to wonder how much 3rd rail would cost down the WoE as you will need a lot of extra kit and interface to the signal system and presumably remote control as well to avoid stranded trains situation although with some battery backup that might simplify things.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
31,976
When does nice talk about doing something with the Uckfield line move to having to do something as the Class 171 fleet need replacing? They were built in 2003 I believe so are 21 years old. There are, I think, 24 cars and each car is 23m long.

Potentially another 20 years to go then


Any battery train needs the ability to sit at Crowborough or Ashurst for a couple of hours without losing sufficient charge to get to a charging point!

Evidence for that?

Given that there are battery trains in service that could do Hurst Green to Uckfield and back without needing a charge.
 

yorksrob

Veteran Member
Joined
6 Aug 2009
Messages
41,299
Location
Yorks
If Uckfield - Lewes had not closed in the 60s would the Oxted line have been electrified by now?

It wouldn't surprise me if it had been one of the 1980's infills (including to Tunbridge Wells).
 

30907

Veteran Member
Joined
30 Sep 2012
Messages
20,520
Location
Airedale
It wouldn't surprise me if it had been one of the 1980's infills (including to Tunbridge Wells).
Or Hurst Green to Birchden Jn would have closed, which I believe was an option in the late 60s? Either way, Oxted would have gone electric.
 

yorksrob

Veteran Member
Joined
6 Aug 2009
Messages
41,299
Location
Yorks
Or Hurst Green to Birchden Jn would have closed, which I believe was an option in the late 60s? Either way, Oxted would have gone electric.

You'll have to remind me which curve that was !
 

Chrisgr31

Established Member
Joined
2 Aug 2011
Messages
1,682
Evidence for that?

Given that there are battery trains in service that could do Hurst Green to Uckfield and back without needing a charge.

Relatively regularly units get stuck at Crowborough or indeed Uckfield or Ashurst because the line is shut somewhere, either because a lorry has hit a bridge or because of a signalling fault. So they sit at the station waiting for an hour or two, or it has been even longer. So you wouldn’t want a situation where they were sat somewhere for so long they used all their charge and could no longer make it back.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
31,976
Relatively regularly units get stuck at Crowborough or indeed Uckfield or Ashurst because the line is shut somewhere, either because a lorry has hit a bridge or because of a signalling fault. So they sit at the station waiting for an hour or two, or it has been even longer. So you wouldn’t want a situation where they were sat somewhere for so long they used all their charge and could no longer make it back.

Sorry I misread your post. I thought you meant a battery trsin would be required to sit there for a coouple of hours to charge.

In any event, the ‘hotel’ load of a train sat still doing nothing is relatively small in the scale of battery sizes needed for traction. A 4 car BEMU might use 20kw sat still, it could be there for 5 hours and barely dent a 1MWh battery.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,245
Location
Surrey
Sorry I misread your post. I thought you meant a battery trsin would be required to sit there for a coouple of hours to charge.

In any event, the ‘hotel’ load of a train sat still doing nothing is relatively small in the scale of battery sizes needed for traction. A 4 car BEMU might use 20kw sat still, it could be there for 5 hours and barely dent a 1MWh battery.
Lieberr roof air con units are nearly 40kw in cooling mode albeit as long as train has been pre cooled it shouldn't need to run flat out then you have other aux loads. So in a worst case scenario it could easily use more than 20kW/carriage given you have other auxiliaries as well. Hitachi BEMU trials in Japan nearly a decade ago showed that hotel load was quite a factor in range when operating at the worst case upper and lower operating temp albeit those trains only had a 360kW battery / 2 car. Im wondering if managing state of charge (SoC) is exercising the standard setters and regulators at the moment in how to define what the operational characteristics that a BEMU has to achieve. ie how low should SoC go. The battery suppliers tell us that life is extended running at 20-80% range but presumably that doesn't prevent the odd excursion below that level. So like planes
whereby most airport require a min of 30mins of fuel to hold in the stack what is the equivalent time for a BEMU.
 

alf

On Moderation
Joined
1 Mar 2021
Messages
390
Location
Bournemouth
Air con & heating on a cold Sussex night can draw 50kw per 23 metres length coach.
Stuck for 2 hours with lights & compressors working uses 120KWH.
No worries if the heavy 1MWH(=1000kwh) is fully charged.
But if it has worked off the third rail & been drained going south from Hurst Green to Uckfield, sat there for ten minutes & then worked back north to remote Cowden it’s 1000kwh battery may be holding less than 120KWH so the lights, heat & front & rear lights will be off.
Oh dear.
 

DerekC

Established Member
Joined
26 Oct 2015
Messages
2,287
Location
Hampshire (nearly a Hog)
Relatively regularly units get stuck at Crowborough or indeed Uckfield or Ashurst because the line is shut somewhere, either because a lorry has hit a bridge or because of a signalling fault. So they sit at the station waiting for an hour or two, or it has been even longer. So you wouldn’t want a situation where they were sat somewhere for so long they used all their charge and could no longer make it back.
There's a very simple solution to that - put a third rail section in at each station. See the following thread for lots of information.

https://www.railforums.co.uk/threads/battery-450s-replacing-159s-on-west-of-england-line.275439/
 

Trainbike46

Established Member
Joined
18 Sep 2021
Messages
3,168
Location
belfast

DerekC

Established Member
Joined
26 Oct 2015
Messages
2,287
Location
Hampshire (nearly a Hog)
Third rail in stations is ISTR the most common situation for injuries and deaths, - so not much chance of that.
Worth reading the thread I highlighted- "Battery 450s replacing 159s on West of England Line". Third rail at/approaching and leaving stations; energised when the train is in section. If this approach could work for Worting Junction - Exeter, it could work for North Downs Line, Marshlink etc.
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
21,099
Network Rail and GWR have published a report which confirms that electrification of the North Downs Line represents 'very poor' value for money, that battery powered trains could have a good financial case, that an extra stopping service between Reading and Guildford each hour could be viable, and that there is no financial case for extending services at either end.


The combined appraisal suggests that traction power choices are independent of any strategic service
choices. A rolling stock technology decision can be made for the 2030s without full infill electrification being
progressed, as traction power choices did not materially affect the case for new services and vice versa.
Decarbonisation
•Battery trains are a credible option and could deliver high value for money, subject to confirmation of any infrastructure requirements.
•Full electrification is unlikely to be value for money, a strategic priority, or affordable in the medium-term.
•Interim solutions such as diesel-electric trains have a weaker case than battery but could deliver value for money and reduce carbon emissions.
•Battery or diesel-electric trains both have potential to deliver strategic benefits such as journey time savings.
•Resourcing efficiencies may emerge as traction technology decisions are taken for the wider region
 
Last edited:

Chrisgr31

Established Member
Joined
2 Aug 2011
Messages
1,682
If going battery electric it would make sense to buy the units for the other diesel lines in the south east at the same time
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
21,099
If going battery electric it would make sense to buy the units for the other diesel lines in the south east at the same time
Yes, but the other expectation must be that the 19% of the Southern region which isn't electrified never will be.
 

brad465

Established Member
Joined
11 Aug 2010
Messages
8,550
Location
Taunton or Kent
This route will have one of the strongest cases for battery viability, not just given the traffic demand (serving a major airport and some notable large towns), but third rail provision existing at both ends and a notable island in the middle of the route should allow for them without any further electrification/charging point installation. Uckfield will likely need something at the Uckfield end as a minimum; not sure about the Marshlink.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,245
Location
Surrey
Network Rail and GWR have published a report which confirms that electrification of the North Downs Line represents 'very poor' value for money, that battery powered trains could have a good financial case, that an extra stopping service between Reading and Guildford each hour could be viable, and that there is no financial case for extending services at either end.

Its an ideal route for BEMUs with electrification at the remote ends and a section in the middle for a power boost. This like multiple routes that part operate under the wires should be ideal candidates for a standard unit procured nationally by GBR.
 

AM9

Veteran Member
Joined
13 May 2014
Messages
15,215
Location
St Albans
In the linked document (I should have said 18.3%, not 19%)

Presumably route miles.
Which in terms of the impact of diesel use irrelevant. The three main routes, BML, SWML and Portsmouth direct probably account for over half the total.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
31,976
Network Rail and GWR have published a report which confirms that electrification of the North Downs Line represents 'very poor' value for money, that battery powered trains could have a good financial case, that an extra stopping service between Reading and Guildford each hour could be viable, and that there is no financial case for extending services at either end.


Well, nobody likes a smart alec*, but I have been saying this for nearly a decade on these pages.

* other four letter words beginning with “a” are available

In the linked document (I should have said 18.3%, not 19%)

Presumably route miles.

Yep, the lines through Salisbury are doing a fair bit of the work in that 18% of course.

The real figure to worry about is vehicle miles, and at a guess diesel vehicle miles are a much smaller proportion, even allowing for the Voyagers to Bournemouth etc.
 

stevieinselby

Member
Joined
6 Jan 2013
Messages
679
Location
Selby
This route will have one of the strongest cases for battery viability, not just given the traffic demand (serving a major airport and some notable large towns), but third rail provision existing at both ends and a notable island in the middle of the route should allow for them without any further electrification/charging point installation. Uckfield will likely need something at the Uckfield end as a minimum; not sure about the Marshlink.
Wokingham to Ash is 12 miles, and Shalford to Reigate is 17 miles.
Ashford to Ore is also 25 miles each way, but with the opportunity to top-up during the layover at Ashford.
Uckfield to Hurst Green is 25 miles each way, making a 50 mile round trip off the juice. Would that be beyond the range of a BEMU on a line that is mostly 70mph running?
 

brad465

Established Member
Joined
11 Aug 2010
Messages
8,550
Location
Taunton or Kent
Wokingham to Ash is 12 miles, and Shalford to Reigate is 17 miles.
Ashford to Ore is also 25 miles each way, but with the opportunity to top-up during the layover at Ashford.
Uckfield to Hurst Green is 25 miles each way, making a 50 mile round trip off the juice. Would that be beyond the range of a BEMU on a line that is mostly 70mph running?
Ashford to Ore should be sufficient looking at that. Even if 50 miles is in range, I think there should be some charging means available at Uckfield, or at least close to that end, for resilience. Also worth noting the line is not the flattest going, it has to navigate the High Weald with some notable gradients, so power demand would be higher than 50 miles on a relatively flat route like the Marshlink.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
31,976
Uckfield to Hurst Green is 25 miles each way, making a 50 mile round trip off the juice. Would that be beyond the range of a BEMU on a line that is mostly 70mph running?

Well within range; it comes down to how big the battery is.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
14,956
Location
Bristol
Ashford to Ore should be sufficient looking at that. Even if 50 miles is in range, I think there should be some charging means available at Uckfield, or at least close to that end, for resilience. Also worth noting the line is not the flattest going, it has to navigate the High Weald with some notable gradients, so power demand would be higher than 50 miles on a relatively flat route like the Marshlink.
Remembering that whatever goes up must come down, although the power drain is larger on a hilly line the opportunities for energy recovery are also similarly larger. Obviously the laws of themodynamics mean you'll still have a greater net expenditure of power if you are applying and recovering than coasting (impossible to achieve 100% efficient transfer of energy type), but the difference isn't as large as is maybe being suggested.

Fitting a 100-mile range battery to a 4-car EMU should not be particularly impossible, especially if it's a currently manufactured design. That would comfortably cover Hurst Green to Uckfield and back with room to spare. There are various options for emergency-only shore supplies at station. Additionally, a short extension of the third rail, 'around the corner' as it were, to allow trains to accelerate away from the junction or hold at a red on the juice rail would be a perfectly sensible provision.
 

AM9

Veteran Member
Joined
13 May 2014
Messages
15,215
Location
St Albans
Remembering that whatever goes up must come down, although the power drain is larger on a hilly line the opportunities for energy recovery are also similarly larger. Obviously the laws of themodynamics mean you'll still have a greater net expenditure of power if you are applying and recovering than coasting (impossible to achieve 100% efficient transfer of energy type), but the difference isn't as large as is maybe being suggested.

Fitting a 100-mile range battery to a 4-car EMU should not be particularly impossible, especially if it's a currently manufactured design. That would comfortably cover Hurst Green to Uckfield and back with room to spare. There are various options for emergency-only shore supplies at station. Additionally, a short extension of the third rail, 'around the corner' as it were, to allow trains to accelerate away from the junction or hold at a red on the juice rail would be a perfectly sensible provision.
Given that most recent and all new (main line) EMU designs have provision for mounting an pantograph, in a DC-only region, it would be worth fitting a pantograph optimised for static charging so that short overhead conductors could be fitted in likely emergency locations, (e.g. a turn-round station, a busy junction signal). The feed could be 25kV (c. 5MW) from a DNO connection or even DC if the transformer primary was suitably protected.
 

Top