• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Wigan-Bolton electrification. Construction updates only please

Status
Not open for further replies.

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,251
Location
Surrey
No different to any work site other than scale of operation over the last 25 years or so. Co-ordination, Planning and Communication.
and a will between different contractors to collaborate which can't be taken as read when NRs imposed so much pressure on not overrunning possessions that contractors can have introverted thinking which can prevent the most efficient use being made of the possession. Im not sure what the arrangements are on this project though but given the relatively short length of the project and high number of possessions required for civil works should be plenty of opportunities to get supporting works completed.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

hwl

Established Member
Joined
5 Feb 2012
Messages
7,624
It is also such a short section that pre-planned well in advance Rail Replacement busses should be relatively easy one would have thought.
Unique in that respect for a recent scheme south of the Border
 

Gricer99

Member
Joined
21 Jun 2020
Messages
256
Location
Hindley
I trust they will give people living near the line some proper advance notice of the dates they are piling close to their homes?
Hopefully not just a three month period either!
 

Elecman

Established Member
Joined
31 Dec 2013
Messages
3,200
Location
Lancashire
Given the relatively short distance im surprised it’s not being done in a complete Blockade, cheaper and quicker once all the ground investigations are complete so piling could be done during the day.given Northern aren’t taking and franchise financial risk now then no need for compensation payments for the line blockages.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
9,332
Location
Dalton GA USA & Preston Lancs
Indeed. Get all bridge work and platform lengthening ground surveys done. Blockade and get all piling done during the day but use the blockade to do work at nighttime that is much less noisy. Rinses and repeat for steelwork erection. Rinse and repeat for SPS installation. Rinse and repeat for wiring.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,251
Location
Surrey
Given the relatively short distance im surprised it’s not being done in a complete Blockade, cheaper and quicker once all the ground investigations are complete so piling could be done during the day.given Northern aren’t taking and franchise financial risk now then no need for compensation payments for the line blockages.
Agreed and if there was a full on national programme would also allow resources to effectively utilised and get the wires up quicker but no sign of that coming currently.
Indeed. Get all bridge work and platform lengthening ground surveys done. Blockade and get all piling done during the day but use the blockade to do work at nighttime that is much less noisy. Rinses and repeat for steelwork erection. Rinse and repeat for SPS installation. Rinse and repeat for wiring.
Ditto
 

Class 170101

Established Member
Joined
1 Mar 2014
Messages
8,358
I think blockades are the only way to get costs back to where the govenment wants them, realistic or otherwise.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
9,332
Location
Dalton GA USA & Preston Lancs
I think blockades are the only way to get costs back to where the government wants them, realistic or otherwise.
I agree they (blockades) are a good way - if they are the ONLY way I am not as sure of. Shutting down at say 22.00 on a Friday evening and opening up again at 05.00 on a Monday morning over a few weekends advertised and announced well in advance with a good RRB service could get a huge amount done.
 

furnessvale

Established Member
Joined
14 Jul 2015
Messages
4,730
I agree they (blockades) are a good way - if they are the ONLY way I am not as sure of. Shutting down at say 22.00 on a Friday evening and opening up again at 05.00 on a Monday morning over a few weekends advertised and announced well in advance with a good RRB service could get a huge amount done.
I would prefer to see RAIL diversions wherever a route is available NOT busses because they suit the operator.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,251
Location
Surrey
I agree they (blockades) are a good way - if they are the ONLY way I am not as sure of. Shutting down at say 22.00 on a Friday evening and opening up again at 05.00 on a Monday morning over a few weekends advertised and announced well in advance with a good RRB service could get a huge amount done.
Thats a possession a blockade is really something in excess of a 4 day Easter closure in my book.

A route of this length could be dealt with in 3 months although would need several months to stockpile sufficient materials but would considerably lower the cost.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
14,983
Location
Bristol
To me, it is unrealistic of Network Rail/TOCs etc to bustitute on long blockades where a diversionary route is available.
The diversionary route from Wigan to Bolton and Manchester is available through existing trains, changing at Preston (or Warrington/Earlestown). If the Atherton line remains open, those trains can also be used. Why run additional trains in areas of congested capacity when there are existing services that cover the options?
 

furnessvale

Established Member
Joined
14 Jul 2015
Messages
4,730
The diversionary route from Wigan to Bolton and Manchester is available through existing trains, changing at Preston (or Warrington/Earlestown). If the Atherton line remains open, those trains can also be used. Why run additional trains in areas of congested capacity when there are existing services that cover the options?
In this particular case the rail alternative IS available, but in other cases buses are run for many miles where a reasonable rail diversion would be available. This is purely for the convenience of the rail industry. As in so many walks of life, they know the price of everything and the value of nothing.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
14,983
Location
Bristol
In this particular case the rail alternative IS available, but in other cases buses are run for many miles where a reasonable rail diversion would be available. This is purely for the convenience of the rail industry. As in so many walks of life, they know the price of everything and the value of nothing.
A diverted train is only of limited value to passengers between Wigan and Bolton. It is of negative value to passengers at Preston, Wigan NW, Manchester Victoria etc as trains are out of place and have to work with the diverts. You are more aware than most that the railway must look to all it's passengers and customers, not just those on one line. The best option to me would seem to be ticket acceptance on alternative trains via Preston or Eccles for the duration of a blockade, so that passengers are not financially impacted by the longer route.
 

furnessvale

Established Member
Joined
14 Jul 2015
Messages
4,730
A diverted train is only of limited value to passengers between Wigan and Bolton. It is of negative value to passengers at Preston, Wigan NW, Manchester Victoria etc as trains are out of place and have to work with the diverts. You are more aware than most that the railway must look to all it's passengers and customers, not just those on one line. The best option to me would seem to be ticket acceptance on alternative trains via Preston or Eccles for the duration of a blockade, so that passengers are not financially impacted by the longer route.
Correct for this particular line.
 

WAO

Member
Joined
10 Mar 2019
Messages
888
Why was this bridge reinstated?

It seems to serve a barn, (through a housing estate!) which could also be accessed from the A6.

Might not the farmer and residents have preferred just a better track to Manchester Road?.

WAO
 

Mollman

Established Member
Joined
21 Sep 2016
Messages
1,489
Why was this bridge reinstated?

It seems to serve a barn, (through a housing estate!) which could also be accessed from the A6.

Might not the farmer and residents have preferred just a better track to Manchester Road?.

WAO
There doesn't appear to be a suitable route for road access to the barn from the A6 direction. The bridge is also a public bridleway.
 

WAO

Member
Joined
10 Mar 2019
Messages
888
There looks to be only derelict land between the barn and Slack Lane, with a possible track on GE.

There does look to be a RRV access to a trackside site however so perhaps NR wants the bridge for its own purposes. Either way it doesn't quite look like value engineering, at £2.3M.

WAO
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
32,009
Why was this bridge reinstated?

It seems to serve a barn, (through a housing estate!) which could also be accessed from the A6.

Might not the farmer and residents have preferred just a better track to Manchester Road?.

WAO

it’s a farm, with a public bridleway to boot. £2.3m is actually pretty cheap, especially given the bridge looks to be approaching life expiry.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
17,569
Given the relatively short distance im surprised it’s not being done in a complete Blockade, cheaper and quicker once all the ground investigations are complete so piling could be done during the day.given Northern aren’t taking and franchise financial risk now then no need for compensation payments for the line blockages.
Incorrect I am afraid. Schedule 4 would still be payable as its part of their track access contract.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,251
Location
Surrey
That’s my point. schedule 4 is now pointless as DfT take all financial risk now and are NR/s paymaster
Totally correct although I suspect the cost for the rebuilding the bridge includes Sch4 as that was policy for CAPEX works when i was still at NR. So if its still does, albeit probably not that a high cost on this route, its inflating the costs unnecessarily in todays railway. Yes its appropriate to charge marginal costs over running trains, if there are any, of running RRB but nothing more.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
32,009
I’d be surprised if Schedule 4 compensation for that closure reached 5 figures.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,251
Location
Surrey
I’d be surprised if Schedule 4 compensation for that closure reached 5 figures.
I did say unlikely to be high on this route but on other busier routes it will be so all it does is inflate costs.

As designed Sch4 was supposed to incentivise NR to reduce the amount of possessions it needed but it never did well not in my route and there was a game to played recharging CAPEX projects to make it look as though operating costs had been reduced.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
17,569
That’s my point. schedule 4 is now pointless as DfT take all financial risk now and are NR/s paymaster
It might be shuffling cash, but if NR block the line then they still pay Northern compensation regardless of the bank account it ends up in.

I’d be surprised if Schedule 4 compensation for that closure reached 5 figures.
It probably wouldn't, there is a somewhat marked difference to cancelling a Northern service to an Avanti from what I have seen!
 
Status
Not open for further replies.

Top