Water main and sewer work
With two weeks of testing the new water main successfully completed, the old pipe has now been disconnected and the ends will be grouted up. This means the site between Mill Street and Abbey Road (see image above) can be removed, with the road due to be reinstated.
The next phase will see work on the connection area for the smaller water main pipe, as well as a start to preparations for the sewer diversion beside the Westgate Hotel. Direct access onto Botley Road to/from Mill Street will be restored and the walkway diverted, with an entrance/exit being created next to The One restaurant (see image below). Unless any issues arise, the schedule will be as follows:
* Ongoing – Reinstatement of the road between Mill Street and Abbey Road
* Thursday 1 May – Change to traffic management, with reopening of direct access to/from Mill Street onto Botley Road. The pedestrian crossing will be moved back to beside The One restaurant, between Mill Street and Abbey Road
* Thursday 1 to Tuesday 5 May – Construction of walkway diversion
* Tuesday 6 May – Change to new walkway route.