Bantamzen
Established Member
A very sensible list.
I would also add the Atherton line, if the bridge at Wigan Wallgate could be sorted out.
Thank you, and I'd agree that the Atherton line would be a good addition.
A very sensible list.
I would also add the Atherton line, if the bridge at Wigan Wallgate could be sorted out.
I suppose that begs the question as to what would the journey time be? Given the frequencies are already there (4 fast tph) plus the rest, would 35-40 mins be achievable and would that be considered ‘good enough’?
I suppose that begs the question as to what would the journey time be? Given the frequencies are already there (4 fast tph) plus the rest, would 35-40 mins be achievable and would that be considered ‘good enough’?
NPR (or whatever it gets called) will have to do something to overcome the problem of only double track between Stalybridge and Diggle. A new base tunnel is the answer to both this and the running time problem between Manchester and Leeds. Build a new electrified tunnel for the fast trains and (electric only) freight from Oldham to Huddersfield.Honestly, not much quicker given the mixture of services, although the planned four tracking between Huddersfield & Ravensthorpe alongside wiring will help bring times down. However the big win would be in dwell times, longer, quicker off their feet units (which generally speaking EMUs are better at) means less chance of following services catching up and being slowed down.
Personally I would do lines with at least 4 tph per single track so:
- Didcot-Oxford
- Slough-Windsor
- Twyford-Henley
- Valley Lines network
- Reading-Basingstoke
- Bristol Parkway-Exeter St. David’s
There are probably many more I’ve missed out. I can’t understand why Basingstoke- Exeter keeps getting suggested, not enough services there IMO.
Personally I would do lines with at least 4 tph per single track so:
- Didcot-Oxford
- Slough-Windsor
- Twyford-Henley
- Valley Lines network
- Reading-Basingstoke
- Bristol Parkway-Exeter St. David’s
There are probably many more I’ve missed out. I can’t understand why Basingstoke- Exeter keeps getting suggested, not enough services there IMO.
The DfT's half-hearted response was:"Now is a critical time for rail electrification.
"There will likely be a significant hiatus before new projects are ready for construction. This could lead to a loss of capability and skills in the supply chain.
"The stop-start nature of electrification is one of the key factors in cost increases. With a long-term rolling programme that provides visibility and consistency to rail suppliers so they can build up and retain expertise, electrification could be delivered at up to half the cost of past projects."
Edit, to add further details & quotes available at https://www.riagb.org.uk/RIA/Newsroom/Press_Releases/Electrification.aspxThe Telegraph said:A spokesman for the Department for Transport said: "This government has set the bold target of being net zero by 2050 and we are working tirelessly to cut emissions across every single mode of transport. Rail electrification is key to this strategy.
So keep the MML team going North, and the GW team going down Filton and toward Bath.
I assume the Northwest triangle team have disbanded so start mobilising a northern team and a West Midland team
One possibility that has been doing the rounds is Totnes to Plymouth, or part thereof, over the South Devon Banks. The 802s, despite their up-rated performance, are noticeably slower on the gradients than their predecessors. Dainton is particularly bad, having the steepest section and most incessant curvature. Cross-Country are also likely to be inflicted with the b****y things in due course. Most of the over-bridges on the Rattery to Hemerdon section date from the 1893 doubling so no 'Steventon' issues, although Marley Tunnel has twin bores and may require a 'Farnworth' solution. The line is low-speed so does not need the 'battleship' OHLE seen on the South Wales ML and the 400kV National Grid trunk follows the route closely. It is also 'something for the South West' to use a phrase up-thread.
To cover the south Devon Banks you'd have to electrify between Newton Abbot - Plymouth. If one is going to do that you might as well electrify as far as Exeter/Bristol/Birmingham etc. Also, my experience of the 802s is they are better on the gradients than the former class 43s, although I've only travelled on the Totnes - Newton Abbot (Dainton Bank - steepest of the three) section.
My wish list (some of which will have already been mentioned).
Penzance/Plymouth - Birmingham New Street via Bristol Temple Meads and Bristol Parkway
Newbury - Cogload Junction
Market Harborough - Derby/Sheffield/Nottingham/Leeds
Chippenham - Bristol Temple Meads
Cardiff - Swansea
Swindon - Gloucester/Cheltenham (now the Kemble section has been re-doubled)
South Wales valley lines e.g. Cardiff - Treherbert, Cardiff - Rhymney, Cardiff - Merthyr Tydfil
Main lines London - Kent/Surrey/Sussex etc. which are currently third rail
Oxford - Cambridge via Bletchley/Bedford (once East West Rail is completed)
London Marylebone - Birmingham Snow Hill
ECML - Hull
Heart of Wales Line (that was a joke)
An experimental minimum cost project using a static frequency converter substation to avoid hardcore grid reinforcement, wooden and concrete masts and any other cost savings they can come up with.
Find two similar line segments, close to one another and do one in the normal way and one with tota blockade.
We desperately need good data.
As to what routes to do, there are several good options, Morecambe and it's environs as suggested, or perhaps the Buxton line or similar.
If you do Buxton you can do New Mills Central as a comparison line in the same valley.
With the proviso that rail infrastructure hasn't been develoved to Wales (except the Valley Lines), so that's still funded through UK coffers.So what ever is done in the near future needs to be planned initially round the electrification teams in place in England - Scotland and Wales will do their own thing
Suggestions to electrify the Heart of Wales may need to be accompanied by a health warning, or at least a defibrilator.Heart of Wales Line (that was a joke)
Presumably it would be possible to get a lightweight system to and running fairly quickly, but then over time upgrade it (within other engineering closures) so that it gets more robust as time goes by.
Obviously this could mean that is more costly to get to a finished end scheme, however many of those costs could be offset by being able to use EMU's sooner. Also by having a shorter initial work programme and then using other closures (i.e. you are needing to run rail replacement buses anyway) the extra costs might not be that much more anyway.
In the case of Morecambe the lightweight system would be the end scheme. No need to later upgrade.
Lessons learnt would be applicable to Windermere, Blackpool South, Fleetwood...
I would think that going for a lightweight scheme to Morecambe would prove that it's a failure with the first westerly winter storm!In the case of Morecambe the lightweight system would be the end scheme. No need to later upgrade.
Lessons learnt would be applicable to Windermere, Blackpool South, Fleetwood...
...Apart from when it's not working, of course. How are those replacement portals coming along?Lightweight solutions get a bad rap but even ECML standard equipment is perfectly adequate.
Despite occasional dewirements it is clearly still an operational railway.
The railway North of Newcastle is still operational on electric powerI would think that going for a lightweight scheme to Morecambe would prove that it's a failure with the first westerly winter storm!
...Apart from when it's not working, of course.
I wasn't aware that was a "lightweight" scheme. I would hope that no-one would have dared to try out an experimental cheapo solution on an international main line.The railway North of Newcastle is still operational on electric power
Does it? Why are they trialling an upgrade then?Could say that about any railway.
The ECML electrification delivers 95% of the benefits of a "heavier" solution.
The ECML electrification scheme is the ultimate example of BR-era value engineering.I wasn't aware that was a "lightweight" scheme. I would hope that no-one would have dared to try out an experimental cheapo solution on an international main line.
Amongst other things, that project was committed back when Network Rail could get money for virtually anything it wanted, and was based on erroneous costings for newfit equipment thanks to high productivity plant that turned out to be ridiculously inaccurate.Does it? Why are they trialling an upgrade then?
Do you have any evidence it's availability is anything like that bad?Maybe being out of action for 1 day in 20 because of OLE failures is acceptable to you, but If I was commuting on a railway with that level of unavailability I would be looking for a different way to travel - or a job that I could reach by a different route or mode of transport!
You obviously know little about the development of electrification in the UKI would think that going for a lightweight scheme to Morecambe would prove that it's a failure with the first westerly winter storm!
I bet it wasn't intentionally designed as a "lightweight" system though.You obviously know little about the development of electrification in the UK
Morecambe was first electrified in 1908 and that ran until 1953. It was then converted and ran in a revised form until 1966.
I think you'll find that was the longest surviving overhead route in the UK - and some of the poles were wood, some concrete. It worked then, it can work now
You obviously know little about the development of electrification in the UK
Morecambe was first electrified in 1908 and that ran until 1953. It was then converted and ran in a revised form until 1966.
I think you'll find that was the longest surviving overhead route in the UK - and some of the poles were wood, some concrete. It worked then, it can work now