380s, 700s now 800s. Can't remember other stock having so much trouble with commissioning.
Have there been many issues with commissioning the class 800 series trains? I haven't seen anything major reported: As far as I am aware, it looks as if the first trains are still likely to be accepted by the operator on schedule in around two months time as per the terms of the Great Western franchise agreement.
With regard to the class 380s, their teething troubles seemed somewhat less significant than those that plagued their, in some respects, forerunners the class 303s, which suffered from a spectacular series of transformer explosions in their first weeks of service that saw the whole fleet withdrawn from service!
Class 87s and 90s had a quick spin with half a dozen coaches in tow and they were into traffic the next day. Is this the result of buying 'foreign' or just over complicated electronically?
Class 87s and 90s were both fairly straightforward developments of existing traction and technology (The latter being developed as an evolution of the former, and the groundwork for thyristor control having been laid by 87101 some years previously), and even the early examples of class 90 underwent a period of pre-service testing of several months before examples of the class entered service.
Preliminary?
The first set arrived over two years ago last week.
Someone is paying a bomb for all this testing. The stuff has been built, so money has changed hands in the supply chain, but the trains still aren't earning.
While the class 800 series units are part of the same family of trains as the existing class 395, there's a lot of unproven features that need to be tested, key amongst these being the trains bi-mode capability of the trains and any potential electrical interference issues. Remember that the last national programme of new Intercity trains, the HST, undertook three years of testing from the release from works of a prototype train in June 1972 to it entering regular passenger service in May 1975 (Actually two and a half years of testing admittedly, as the train was the subject of a union dispute over double manning until December 1972), and over a year more until the first production train entered passenger service.
During the last major main line electrification project, of the ECML nearly thirty years ago, the first batch of ten class 91s also spent around twelve months undergoing testing between delivery of the first loco and the class entering passenger service.