• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

MML Electrification: progress updates

Merle Haggard

Established Member
Joined
20 Oct 2019
Messages
1,979
Location
Northampton
I hope the following is of interest and includes something new.
I travelled on the MML today, and noticed the following;
On the down, riding on the east side so I could also see the mileposts; up (and presumably down) fully wired from Kettering to a run-off about MP77; after a gap, further wiring to another run-off about MP81. Odd stretches of foundations for masts including MP90-91.
Returning on the up, riding on the west side and therefore unable to see MPs; mast uprights (but no more) furthest North start about 10 columns North of Kilby Bridge (A6 under). Other noticeable point is that there's only foundations through Desborough (site of station) - noticeably in the area of the over bridge, but columns (at least) each side. Maybe waiting work on the overbridge.
On this electrification use is made of OLE supports with a column on only one side therefore if you are viewing from a train and only able to see one side, absence of bases/foundations might just mean the base is on the other side.
All in all, quite remarkable progress beyond the M.H. turn back.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
29,489
And you’d have been one of the first passengers to experience of slightly lower track under Wistow Road bridge at Kibworth :)
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
1,779
Location
Nottingham
According to HS2, the Ratcliffe-on-Soar grid connection was to be located just opposite the power station where the 400kV lines cross the MML. See the map in post #5168, copied below.

... The 400kV tap was indeed the second pylon outside the power station. It looks like they planned to feed the Kegworth ATFS with a +25kV/0/-25kV cable buried along the southern side of the A453 between these two sites.

View attachment 113230
I had a look today. On the ground, there was no sign of any activity at all, but there was a notice from Rushcliffe Council about a Local Development Order for the power station site and the land where I thought the Grid Supply Point was going to be.

According to the LDO, the GSP site is now destined to be a car park and "Tree Buffer Areas".

See https://www.rushcliffe.gov.uk/planningpolicy/ratcliffelocaldevelopmentorder/
and Masterplan maps at: https://www.rushcliffe.gov.uk/media/1rushcliffe/media/documents/pdf/planningandbuilding/planningpolicy/ratcliffeldo/Ratcliffe LDO Display Boards August 2022.pdf

So does anyone know where the 400kV Grid Supply Point is now going to go? I'm told upthread that the electrical equipment is already on order. So presumably they know where it's going to be installed.
 
Last edited:

InTheEastMids

Member
Joined
31 Jan 2016
Messages
753
That'll be the work for the ATF then. I'd suspect that the ATF insulators atop little stovepipes above the booms will be in by Monday morning.
There is new wiring mounted on insulators in Harborough. It's mounted high up on the steelwork and starts at the heavyweight portal next to Bellfields Lane and heads South.

So does anyone know where the 400kV Grid Supply Point is now going to go?
So, the pictures you showed were the proposed HS2 grid supply point, and I'm not sure I've ever seen evidence that this was tied into whatever NR were going to do for MML. It's likely that given they'd each want a lot of power, then they might need to be connected to different 400 kV circuits (assuming HS2 ever gets this far).

So, if you look at the transmission network around Ratcliffe on Soar...
(the link shows this on the open infrastructure map: https://openinframap.org/#14.59/52.84907/-1.26296)

What I gather from the HS2 drawings linked in the above post is that the HS2 point of connection would be to the circuit labelled ZD. I have a very dim recollection (which I can't source/support) that the MML point of connection was just South of the Ratcliffe redevelopment area, so if my memory's right then I would guess a connection and substation to the 4YZ circuit where it crosses the MML next to Kegworth Road.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,538
Location
Between Peterborough & Bedlington
There is new wiring mounted on insulators in Harborough. It's mounted high up on the steelwork and starts at the heavyweight portal next to Bellfields Lane and heads South.
Excellent - that's the ATF definitely in as far south as Little Bowden Footbridge. I don't know if the ATF has gone in south of the footbridge yet, but I suspect it might well have done.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,538
Location
Between Peterborough & Bedlington
LinkedIn post with an update on the weekend works just gone - https://www.linkedin.com/posts/capi...VW?utm_source=share&utm_medium=member_desktop

In summary - the new con-arches and concrete parapets at SPC3-10 (Glen Station Bridge) have been landed, the track lowering beneath bridge SPC3-15 (Wistow Rd, Kibworth) is complete, and 6 more wire runs (3 pairs) have now bee completed.
The wiring images look as if they're in the Braybrooke footbridge area.
 

Kneedown

Established Member
Joined
29 Dec 2007
Messages
1,770
Location
Nottinghamshire
Thanks. It's quite hard spotting stuff at speed, takes some concentration! I hope I got it all correct. I am quite certain about North of Kilby Bridge, not sure exact no. of masts.
I fear you may be mistaken regarding work at Kilby Bridge. Driving the route yesterday I noted only vegetation clearance in that area. The first piling location was North of Newton Harcourt, just shy of milepost 93 IIRR. The piles are then pretty much continuous to Kibworth with only small gaps, and the first structure in place is at Kibworth Bridge No 23a.
 

Flying Phil

Established Member
Joined
18 Apr 2016
Messages
1,960
I had a look today and there is still a 1/4 mile mast "Gap" North of the Braybrooke supply point. That is still not connected to the 400Kv power line. Through Desborough there are still no masts (1/2 mile) but all the piles appear to have been driven.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,538
Location
Between Peterborough & Bedlington
Lots of work going on at East Hyde neutral section today.
Indeed - I saw a few pics on LinkedIn from SPL to that effect. They've cut in the contact/catenary insulation either side of the cantilevers, and put in the white Neutral Section boards immediately north of the NS structure (which I remember to be F/42/06).
The MMLe Map had this in for "South of Bedford - April 2023":
1680507902028.png

So looks as if East Hyde was commissioned this weekend just gone, and Luton Hoo TSC (near the top of the white line) is being decommissioned at the moment (or certainly will be by Easter Monday if things all go to plan).

LinkedIn picture from an SPL operative on site at the Neutral Section:
1680506423337


LinkedIn pictures from Capital Delivery Eastern showing the disconnection of Luton Hoo TSC from the OLE:
1680511644626

1680511643875
 
Last edited:

Edvid

Established Member
Joined
7 Feb 2008
Messages
1,408
Certainly looks like a weekend well spent. Wasn't expecting the insulators on that NS portal to be removed just a weekend later!

So other than (perhaps) Luton Hoo, what's left of the London-Bedford KO1a works besides the 125mph OLE mods?
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,538
Location
Between Peterborough & Bedlington
Certainly looks like a weekend well spent. Wasn't expecting the insulators on that NS portal to be removed just a weekend later!

So other than (perhaps) Luton Hoo, what's left of the London-Bedford KO1a works besides the 125mph OLE mods?
The new TSC at Napsbury has yet to be commissioned AIUI, and the existing TSCs at Radlett and Sandridge (MPTSC) also need to be decommissioned. Sandridge also needs to have its Neutral Section removed; I don't know what the bypass arrangements there are, if any, for that. (I suppose East Hyde must have its bypassing enabled so that Long Meadow Farm/Chalton (AT)FS can still feed south to Sandridge while Borehamwood ATFS feeds northwards to Sandridge, and I'm also assuming this will persist until Sandridge goes.)
While the TSC at Radlett will go, new switching arrangements (manually controlled) will be installed in place of the existing ones.
The old FS building at Sundon is still in situ the last time I looked.

On a smaller scale, the bonding works to remove old mid-point connections (redundant now that the Return Conductors have been converted to Earth Wires) are still ongoing AIUI.
There's also the Cubed works going on to re-register structures, and the BWA conversion programme to Siemens Anti-Fall assemblies. IIRC there's also a mini-project at Luton (town) to reposition the crossover between Platforms 4 & 5, either by lengthening the crossover to allow higher speeds or moving it further northwards like-for-like (or a combination of the two).
 

Edvid

Established Member
Joined
7 Feb 2008
Messages
1,408
Speaking of the OLE Cubed works, here's another example from near Ampthill, that same weekend:

This is one of the deboostered overlaps, I believe.
1680508766374

1680508766756

1680508766581

1680508766584

1680508767039


----------

Going back a month or so, some shots from within the GSP compound at Braybrooke:

1677080877961

1677080874799

1677080870964

1677080877134
 
Last edited:

Edvid

Established Member
Joined
7 Feb 2008
Messages
1,408
You're welcome.

Incidentally the East Hyde OHNS (F42/06) was previously a regular Mk3b headspan - the start of its conversion (installing a boom) can be seen in a timelapse:
 

Merle Haggard

Established Member
Joined
20 Oct 2019
Messages
1,979
Location
Northampton
I fear you may be mistaken regarding work at Kilby Bridge. Driving the route yesterday I noted only vegetation clearance in that area. The first piling location was North of Newton Harcourt, just shy of milepost 93 IIRR. The piles are then pretty much continuous to Kibworth with only small gaps, and the first structure in place is at Kibworth Bridge No 23a.

Sorry for the delay in responding, didn't get reminders for this thread. I meant the bridge over the A6 near Kibworth which I always thought was called Kilby Bridge.
Obviously I was wrong - also explains

Don't believe the A6 goes near the MML at Kilby Bridge - perhaps you mean the A5199? (interestingly this used to be the A50)
View attachment 131761
I apologise for my error.
 

Kneedown

Established Member
Joined
29 Dec 2007
Messages
1,770
Location
Nottinghamshire
Sorry for the delay in responding, didn't get reminders for this thread. I meant the bridge over the A6 near Kibworth which I always thought was called Kilby Bridge.
Obviously I was wrong
No problem at all.
The location you were referring to is simply known as Kibworth, or Kibworth Harcourt.
Kilby Bridge Junction is between Newton Harcourt and Wigston South, and is where the Up/Down Slow line to Wigston commences/ends.
No further updates to report as of today. Passing through on my mighty 180 it looks pretty much the same.
 

Trainben

Member
Joined
18 Aug 2021
Messages
33
Location
Leicestershire
Copper contact wires now being installed in Market Harborough, appears to be just from Kettering Road bridge, then over Rockingham road into the mouth of the station.
 

Flying Phil

Established Member
Joined
18 Apr 2016
Messages
1,960
Inspired by Trainben I popped along with my camera to Hbro station....
DSC02562.JPG

The view to the South above
and the view to the North..
DSC02563.JPG

So contact wire on the Northbound line, but still some stovepipes and gubbins needed for the other line yet.
 

londonmidland

Established Member
Joined
22 Dec 2009
Messages
1,886
Location
Leicester
Some pictures taken from my train today, not far from Market Harborough (north)

(Apologies for basic terminology but there seems to be more STC & TTC placed, as well as the wires from the pylon ‘connected’ to ground equipment)
 

Attachments

  • 617C5971-4C27-4242-B357-7E9C40AB9F86.jpeg
    617C5971-4C27-4242-B357-7E9C40AB9F86.jpeg
    313.3 KB · Views: 112
  • A56BE97C-2B4A-4AD9-B63C-989921562C67.jpeg
    A56BE97C-2B4A-4AD9-B63C-989921562C67.jpeg
    322.1 KB · Views: 112
  • 9514952B-3846-4DFF-86C5-0020D9D7D2AA.jpeg
    9514952B-3846-4DFF-86C5-0020D9D7D2AA.jpeg
    370.3 KB · Views: 116

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,538
Location
Between Peterborough & Bedlington
Some pictures taken from my train today, not far from Market Harborough (north)

(Apologies for basic terminology but there seems to be more STC & TTC placed, as well as the wires from the pylon ‘connected’ to ground equipment)
They're powering through now (get it? :lol:)
Good to see the pylon connected (physically) to the new substation at Braybrooke though - or at least half-connected.
Looks as if the "London end" of the pylon isn't connected yet.

This application has been superceded by application 23/00249/PDN, which is basically the same, but now states that the bridge no longer needs to be lifted (which was part of the original application).

A new application has also gone in for bridge SPC3/9 (Wistow Road), numbered 23/00203/PDN: https://pa2.harborough.gov.uk/onlin...s.do?activeTab=documents&keyVal=RPPTYMHW06O00
Time to add more Planning Applications!
23/00057/PDN | Application for Prior Approval for alterations to bridge SPC3/7 Wigston Road Bridge (increase in height and replacement of parapets and infill of 2 smaller arches, installation of safety barriers and pallisade fencing): https://pa2.harborough.gov.uk/onlin...s.do?activeTab=documents&keyVal=RODFODHW0KU00 (not sure how I missed this!)
23/00447/PDN | Application for Prior Approval for alterations to bridge SPC3-18 Grammar School Bridge (same as the above): https://pa2.harborough.gov.uk/onlin....do?caseType=Application&keyVal=RRZA7NHW06O00

This means that, out of all the bridges under Harborough DC's jurisdiction, only FB SPC3-16B & O/B SPC3-16 (Warwick Rd) remain as unknowns.
 
Last edited:

ABB125

Established Member
Joined
23 Jul 2016
Messages
3,813
Location
University of Birmingham
Looks as if the "London end" of the pylon isn't connected yet.
Are they definitely taking power from both circuits on the pylons? Surely one circuit would be sufficient?
For anyone interested, based on what I can work out using OpenInfraMap and Google maps, the circuit currently connected runs from Grendon to Staythorpe, the circuit currently unconnected from Grendon to Cottam (bypassing Staythorpe).
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,538
Location
Between Peterborough & Bedlington
Are they definitely taking power from both circuits on the pylons? Surely one circuit would be sufficient?
For anyone interested, based on what I can work out using OpenInfraMap and Google maps, the circuit currently connected runs from Grendon to Staythorpe, the circuit currently unconnected from Grendon to Cottam (bypassing Staythorpe).
Based on the way the pylon arms are arranged, and the fact that I can see the other HV switching site off to the right, I think they're using both circuits. There are two 400kV to 25kV transformers, after all...

See the mark-up I've made of @londonmidland's image below.
braybrooke missing connections.jpeg
 

Top