Techniquest
Veteran Member
This is sure turning into a monster of a challenge! Hopefully it'll be worth the wait!
I would expect that track work was part of this summer’s blockade https://www.networkrail.co.uk/runni...re/oxfordshire-signalling-and-track-upgrades/Took a look at south of the station yesterday. A set of points has been installed already, and a few yards off track. I don't know when that was done.
On the north side of the station, not much to see yet but the former buildings of the signal box are demolished.View attachment 149311View attachment 149312
During our nine-day upgrade in Summer 2023 (29 July – 6 August), we installed high speed crossovers, updated signals and made changes to Osney Lane footbridge. We demolished the old brick pillar to make space for installation of track that will later serve the new platform 5.
Piles for the new platform 5 are now going in, and the long (very, very long) process of sorting out the utilities under the Botley Road bridge continues - video from the last weekly update email here https://network-rail.wistia.com/medias/92mzr6zxzm - there are also updates on a Facebook page https://www.facebook.com/oxfordshireconnectThis thread hasn't seen a post this year, but it's been stated in the MML thread that remodelling at Oxford is currently happening.
The recording of Kier's Teams meeting (in late March 2024?) with local residents and councillors contains much of interest - thanks for the link! In particular I had not understood that work to prepare for the new entrance on the west side will not begin until late 2024. Interesting also to note Kier's wariness about the timing of the mooted additional through line on the east side of the station, using the replacement footbridge which is to be future-proofed to be capable of becoming a rail line.Piles for the new platform 5 are now going in, and the long (very, very long) process of sorting out the utilities under the Botley Road bridge continues - video from the last weekly update email here https://network-rail.wistia.com/medias/92mzr6zxzm - there are also updates on a Facebook page https://www.facebook.com/oxfordshireconnect
Thursday 11 Jul 2024
Oxford’s major rail and road improvement project is progressing but more time is needed before Botley Road can reopen
Region & Route: Wales & Western: Western | Wales & Western
Network Rail has confirmed that significant progress is being made on the multi-million-pound programme to upgrade Oxford Station, enhance the railway infrastructure in the area and improve the local transport network, however more time is required to complete the highly complex utility diversion works including mains water and sewer pipes under Botley Road.
The replacement of the railway bridge, which was scheduled to take place at end of this month, has been postponed as, despite concerted effort by all organisations involved, the work to divert the complex layout of utility pipes and cables under the road, including the sewer system, cannot be completed in time. Unfortunately as a result Botley Road, which has been closed under the rail bridge since April 2023, will not now reopen in October as planned. Network Rail and its contractor, Kier, are working with the local authorities to agree the best way forward to complete the project and minimise impact on the city.
Anna Holbrook, industry programme director at Network Rail said: “Although our work is progressing well on most aspects of this major programme, including the construction of the new platform on the western side of the station, the bridge replacement has unfortunately had to be postponed as the work to divert the complex layout of utility pipes and cables under the road, including the sewer system, will not be ready in time. We have informed the councils that Botley Road will not now be able to be reopened in October. We know how important Botley Road is to Oxford and apologise to local residents and businesses for the ongoing inconvenience. We are working out the best way forward and will continue to engage with the local community as our plans develop.”
Kier and the 11 different utility providers involved continue to make progress on diverting the large number of pipes and cables, including the water main and sewer, which need to be completed before the bridge can be replaced. Working on this outdated maze of pipes and cables spread out below the highway, in a severely constrained space, with poor ground conditions and significant water levels, continues to make this work very challenging.
Once fully complete, the upgrades will result in a bigger and better station, more rail services for passengers and an improved road network near Oxford station with safer junctions, and more space for cyclists and pedestrians through the addition of a four-metre cycle/footway on each side of the main road.
Notes to Editors
Passenger information:
Summary of progress on utility diversion work:
- The planned closure of rail lines through Oxford at the end of July will now only be for two days – Saturday 27 and Sunday 28. During this time there will be work taking place on the new platform and continuation of the resignalling programme. There will also be an upgrade to tracks to the south of Oxford near Culham.
- Over that weekend, there will be no train services between Didcot and Oxford, with a Rail Replacement Service operating from Becket Street car park.
- There is additional work to the north of Oxford, which will affect train services between Oxford and Banbury, between Saturday 27 and Wednesday 31 July.
Summary of progress on wider project:
- Gas main – Installation of pipework completed prior to connection work by SGN
- Water main – Installation of pipework underway
- Telecommunications – Shared utility trench through Frideswide Square and Becket Street car park completed. Openreach currently installing cables below the rail bridge area, with Vodafone, Virgin and Oxford University to follow
- Sewer – Work has started on the diversion through Becket Street car park
- New platform – Work is underway on the foundations for the new platform, starting with ground supports that will hold the canopy in place for platforms 4 and 5
- Sheepwash bridge – Relocation of children’s nursery into temporary building in Becket Street car park completed. Former building demolished, now tackling foundations
- Osney Lane footbridge – Relocation of the pillar to make space for new track completed last summer
- Track work – Installation of new high speed crossovers to the north of Oxford station and start of track for the new platform completed last summer
- Resignalling – Started last summer and currently ongoing
V4, which is the final version, of the Engineering Access Statement for 2025 is published tomorrow. First version of 2026 isn't far away. You can plan one less than 18 months out, but every single duck needs to be in a row, which rarely happens.I get the impression that the critical-path planning was based on over-optimistic timescales and a belief that it hardly ever rains! I was told at a possession planning meeting once that the lead-time for a 7-day blockade was at least 18 months, so we're looking at early-2026. Perhaps The Planner can clarify this?
For something like this, I wouldn't be surprised if the ducks did get pushed into alignment slightly quicker than normal once a new suitable date is known. Could still be fairly long lead though.V4, which is the final version, of the Engineering Access Statement for 2025 is published tomorrow. First version of 2026 isn't far away. You can plan one less than 18 months out, but every single duck needs to be in a row, which rarely happens.
This is one of the things which HMG needs to get a grip of. In circumstances like this regulated companies should have to accept being told when certain works have to be done (subject to the laws of physics etc!)Just as NR has its preplanned program of works, so does each of our utilities and working at the same time brings H&S risks. They will not take kindly to being told when to be on site and if, as in this case, there's a delay, then the work has list its planned timeslot and has to be rescheduled.
The council commented this afternoon:This news seems to have been announced by Network Rail rather than via a joint communication with Oxford City Council and Oxford County Council which you would expect. Although now being reported on the BBC local news there is no comment from the politicians as yet. This will have major implications for traffic in Oxford, the new filtering system supposed to be in place in November at some considerable cost, retail outlets and businesses. I suspect one almighty row is going on behind the scenes about this and how to fix it as soon as possible.
Oxfordshire County Council is extremely frustrated that Network Rail is postponing the replacement of Botley railway bridge at the end of this month and is unable to reopen Botley Road in October as a result. The council is in discussion with Network Rail to understand the implications of this.
Residents and businesses have shown incredible patience with more than a year of disruption to their lives because of this project, which has already had its timetable altered twice before and seen its closure dates extended. We have expressed our deep dissatisfaction to Network Rail and to the Department for Transport about this.
The launch of the council’s traffic filters trial planned to start in November is now in question, with various options being considered as a result. The trial aims to tackle Oxford’s chronic congestion problems and dramatically improve bus journey times. We are calling on and working with Network Rail to find an acceptable solution to this situation quickly.
The council remains incredibly supportive of improvements to the rail station for Oxford with improved capacity for passengers and freight, which is vital for the development of projects such as East West Rail.
In the meantime, we will continue to do all we can to work with partners to minimise the impact on the rest of the road network.
Thanks Benjwri. I had not seen this. Clearly they are not too happy!The council commented this afternoon:
It sounds like most of the works that have been supposed to take place so far are private sector, being utility diversions. Network Rail can't actually do much until the private sector are done.Just to say, that on daily inspection, there is almost no work ever to be seen to be taking place. The odd huddle of people in orange, and a large number of tedious persons in pink high-visibility vests telling pedestrians not to cross the road. These people add nothing to the progress of the project, and mostly spend time on their mobiles. The welfare shanty town in the car park is busy though, even though nobody is doing any work.
It is instructive to compare the speed of public sector works like this and the Kidlington roundabout with that of the construction of the A41 junction by the new Tesco in Bicester, which was funded by the retailer, and took 6 weeks.
I think the differentiation attempting to be made here is between private sector working for NR, and private sector doing their own infrastructure, as mentioned utility companies.I would have thought it was certain that such a major project is being carried out by private contractors.
Utility companies run to their own schedule and many projects struggle to hold them to account.However the responsibility for managing this evolving project still lies with NR
Utility companies have held up HS2 construction in the past. There is very little you can do.I would have thought it was certain that such a major project is being carried out by private contractors. However the discovery of unexpected archaeology will have meant that the works they bid for are very different from what is now required and indeed need skills which they didn't possess. However the responsibility for managing this evolving project still lies with NR
There is a lot that could be done, but the powers that be are too pussy footed to do it. Directors’ bonuses in utilities being dependent on true company performance not share value / profit, for a start (ie delivery of projects on time, reduction in pollution / service outage, leaks etc.).Utility companies have held up HS2 construction in the past. There is very little you can do.